Sai Vatika Residency
by MOHD HASIM ABDUL SATTAR KHAN · Kamatghar, Thane 421302Also near Bhiwandi, Narpoli, Naupada
What’s in the report? →Possession date of Sai Vatika Residency (MahaRERA P51700028797): 30 April 2028, moved from 30 June 2025 (30 months later). It has 28 homes, 34% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700028797, and currently active. Its completion date has moved from June 2025 to April 2028: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700028797, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Sai Vatika Residency?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sai Vatika Residency has moved
30 June 2025
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA25042620737)
Reason the builder gave MahaRERA: “PROJECT WAS DELAYE DUE TO PERSONAL MEDICAL ISSUES”
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sai Vatika Residency’s extension records on MahaRERA (P51700028797), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sai Vatika Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700028797
- Status
- Registered and active
- Builder
- MOHD HASIM ABDUL SATTAR KHAN
- Location
- Kamatghar, Thane · 421302
- Project type
- Others
- Registered on
- 30 Mar 2021
- Completion date at registration
- June 2025
- Latest completion date
- April 2028
- Delay so far
- 30 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 28
- Sold or booked
- 34%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Sai Vatika Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAI VATIKA RESIDENCY | 100% | 95% | 25% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SAI VATIKA RESIDENCY: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sai Vatika Residency every 1–2 months.
Sai Vatika Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: SAI VATIKA RESIDENCY (8 floors, 32 units)
- Car parking: 16 open
- Land: 1,011 sq m (about 0.2 acres) · sanctioned built-up 993 sq m
- Land, as filed: S NO 164/6, 137/1, 137/4/A
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Sai Vatika Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sai Vatika Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sai Vatika Residency
What is the possession date of Sai Vatika Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sai Vatika Residency in Kamatghar, Thane is 30 April 2028 — 30 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 30 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Sai Vatika Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sai Vatika Residency's builder has filed on MahaRERA, the official one, is 30 April 2028, already 30 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sai Vatika Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Vatika Residency's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "PROJECT WAS DELAYE DUE TO PERSONAL MEDICAL ISSUES". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sai Vatika Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sai Vatika Residency in Kamatghar, Thane is P51700028797.
Is Sai Vatika Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Vatika Residency is registered as P51700028797 and its status is "Registered and active".
What is the current construction status of Sai Vatika Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Vatika Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAI VATIKA RESIDENCY is 95% done and internal work 25%. GharKundli's full report compares construction progress with the deadline.
Does Sai Vatika Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sai Vatika Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Vatika Residency is registered on MahaRERA as P51700028797, its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sai Vatika Residency?
Sai Vatika Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sai Vatika Residency?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Sai Vatika Residency: gharkundli.com/tools/property-cost-calculator
Has Sai Vatika Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sai Vatika Residency is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Sai Vatika Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sai Vatika Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Sai Vatika Residency's possession date changes?
The latest dates are on Sai Vatika Residency's MahaRERA page (P51700028797). GharKundli's Kundli Watch sends a free WhatsApp update on Sai Vatika Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sai Vatika Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Vatika Residency has one building filed: SAI VATIKA RESIDENCY with 8 floors and 32 units.
How much parking does Sai Vatika Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 16 open car parking spaces for Sai Vatika Residency.
How big is the land of Sai Vatika Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Vatika Residency stands on 1,011 sq m of land (about 0.2 acres), with 993 sq m of sanctioned built-up area.
What are the reviews of Sai Vatika Residency?
Google Maps has reviews of Sai Vatika Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sai Vatika Residency?
Sai Vatika Residency by MOHD HASIM ABDUL SATTAR KHAN is in Kamatghar, Thane, pincode 421302 (near Bhiwandi, Narpoli, Naupada), Maharashtra, and is registered on MahaRERA as P51700028797, per GharKundli's check of MahaRERA records. Its land is filed as S NO 164/6, 137/1, 137/4/A. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).
How many flats are in Sai Vatika Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Vatika Residency has 28 homes in 1 tower registered on MahaRERA, and 34% of them are sold or booked.
When was Sai Vatika Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Vatika Residency was registered on MahaRERA on 30 March 2021. GharKundli did not find a title report on the land on file there.
Does Sai Vatika Residency have any legal issues or court cases?
No court cases are listed for Sai Vatika Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Sai Vatika Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MOHD HASIM ABDUL SATTAR KHAN.
Check it yourself on MahaRERA
- How to check the possession date of Sai Vatika Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Bhiwandi (421302)
- Shatrunjay Heights
- Sky City
- Vardhaman Vatika
- Siyara Signature
- Siyara Viva
- One Silver Avenue
- Vighnaharta Apartment
- Jangid Empire
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.