SHATRUNJAY HEIGHTS

by ONYX BUILDCON LLP (Quba) · Kamatghar, ThaneAlso near Bhiwandi, Narpoli, Naupada

Possession date of SHATRUNJAY HEIGHTS: 30 April 2029, moved from 31 March 2026 (33 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700030901, and currently active. Its completion date has moved from March 2026 to April 2029: 33 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHATRUNJAY HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHATRUNJAY HEIGHTS has moved

  1. 31 March 2026

    Completion date given when the project was registered

  2. 31 December 2028

    Extended at the builder's request (MahaRERA application EA12092502575)

    Reason the builder gave MahaRERA: “Delayed in obtaining approval”
  3. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SHATRUNJAY HEIGHTS’s extension records on MahaRERA (P51700030901), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHATRUNJAY HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700030901
Status
Registered and active
Builder
ONYX BUILDCON LLP
Location
Kamatghar, Thane · 421302
Project type
Residential / Group Housing
Registered on
29 Sep 2021
Completion date at registration
March 2026
Latest completion date
April 2029
Delay so far
33 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
43
Sold or booked
64%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SHATRUNJAY HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHATRUNJAY HEIGHTS100%96.49%14.04%14.04%

Commencement certificate (CC), as filed on MahaRERA

  • SHATRUNJAY HEIGHTS: covers 17 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHATRUNJAY HEIGHTS every month.

SHATRUNJAY HEIGHTS: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Office Space141 – 1,094140
2 BHK758 – 77528
Shops331 – 83221
3 BHK1,09410
4 BHK1,6465

The builder’s record and reviews

Quba Realty (a group of 9 linked companies) has 12 projects on MahaRERA since 2020, this one included. Of the 12 GharKundli has checked: 10 still being built, 4 past the promised date (typically 8 months late); 2 lapsed. No complaints on MahaRERA.

Read Google reviews of SHATRUNJAY HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHATRUNJAY HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHATRUNJAY HEIGHTS

What is the possession date of SHATRUNJAY HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHATRUNJAY HEIGHTS in Kamatghar, Thane is 30 April 2029 — 33 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SHATRUNJAY HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHATRUNJAY HEIGHTS's builder has filed on MahaRERA, the official one, is 30 April 2029, already 33 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHATRUNJAY HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SHATRUNJAY HEIGHTS's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "Delayed in obtaining approval". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SHATRUNJAY HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHATRUNJAY HEIGHTS in Kamatghar, Thane is P51700030901.

Is SHATRUNJAY HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHATRUNJAY HEIGHTS is registered as P51700030901 and its status is "Registered and active".

What is the construction status of SHATRUNJAY HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), SHATRUNJAY HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHATRUNJAY HEIGHTS is 96.49% done and internal work 14.04%. GharKundli's full report compares construction progress with the deadline.

Does SHATRUNJAY HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SHATRUNJAY HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHATRUNJAY HEIGHTS is registered on MahaRERA as P51700030901, its completion date has moved 33 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHATRUNJAY HEIGHTS's possession date changes?

The latest dates are on SHATRUNJAY HEIGHTS's MahaRERA page (P51700030901). GharKundli's Kundli Watch sends a free WhatsApp update on SHATRUNJAY HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHATRUNJAY HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHATRUNJAY HEIGHTS has one building filed: SHATRUNJAY HEIGHTS with 23 floors and 204 units.

What are the flat sizes (carpet area) in SHATRUNJAY HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SHATRUNJAY HEIGHTS: 2 BHK: 758 to 775 sq ft carpet (28 homes); 3 BHK: 1094 sq ft carpet (10 homes); 4 BHK: 1646 sq ft carpet (5 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does SHATRUNJAY HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 40 covered car parking spaces for SHATRUNJAY HEIGHTS.

How big is the land of SHATRUNJAY HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), SHATRUNJAY HEIGHTS stands on 4,135 sq m of land (about 1.0 acres), with 3,912 sq m of sanctioned built-up area.

What is the track record of SHATRUNJAY HEIGHTS's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Quba Realty (a group of 9 linked companies) has 12 projects on MahaRERA since 2020, this one included. Of the 12 GharKundli has checked: 10 still being built, 4 past the promised date (typically 8 months late); 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SHATRUNJAY HEIGHTS?

Google Maps has reviews of SHATRUNJAY HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHATRUNJAY HEIGHTS?

SHATRUNJAY HEIGHTS by ONYX BUILDCON LLP (Quba) is in Kamatghar, Thane (pincode 421302), near Bhiwandi, Narpoli, Naupada, Maharashtra, and is registered on MahaRERA as P51700030901, per GharKundli's check of MahaRERA records.

How many homes are in SHATRUNJAY HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), SHATRUNJAY HEIGHTS has 43 homes in 1 tower registered on MahaRERA, and 64% of them are sold or booked.

When was SHATRUNJAY HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHATRUNJAY HEIGHTS was registered on MahaRERA on 29 September 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on SHATRUNJAY HEIGHTS?

No court cases are listed for SHATRUNJAY HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SHATRUNJAY HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ONYX BUILDCON LLP, the company Quba files this project under.

All projects with possession due in 2029 in Thane →

Other projects in Kamatghar

All 382 projects in Bhiwandi (421302) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.