Samyak One Silver Avenue
by SHIV SAMYAK BUILDERS & DEVELOPERS LLP · Kamatghar, Thane 421305Registered on MahaRERA as “ONE SILVER AVENUE”
What’s in the report? →Possession date of Samyak One Silver Avenue (MahaRERA P51700055921): 30 April 2030. It has 179 homes, 36% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700055921, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51700055921, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Samyak One Silver Avenue?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Samyak One Silver Avenue has moved
31 December 2029
Completion date given when the project was registered
30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Samyak One Silver Avenue’s extension records on MahaRERA (P51700055921), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Samyak One Silver Avenue
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700055921
- Status
- Registered and active
- Builder
- SHIV SAMYAK BUILDERS & DEVELOPERS LLP
- Location
- Kamatghar, Thane · 421305
- Project type
- Others
- Registered on
- 29 Apr 2024
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 179
- Sold or booked
- 36%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Samyak One Silver Avenue, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING 1 | 100% | 55% | 15% | 0% |
| BUILDING 2 | 100% | 70% | 40% | 0% |
| BUILDING 3 COMMUNITY BUILDING NOT FOR SALE | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING 1: covers 31 floors
- BUILDING 2: covers 30 floors
- BUILDING 3 COMMUNITY BUILDING NOT FOR SALE: covers 4 floors
Latest CC order on MahaRERA: dated 21/12/2023.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Samyak One Silver Avenue every 1–2 months.
Samyak One Silver Avenue: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING 1 (33 floors, 67 units) · BUILDING 2 (32 floors, 120 units) · BUILDING 3 COMMUNITY BUILDING NOT FOR SALE (5 floors, 5 units)
- Car parking: 243 covered
- Land: 6,411 sq m (about 1.6 acres) · sanctioned built-up 32,128 sq m · recreational space 658 sq m
- Land, as filed: 135/2/8, 135/3, 143/1/1, 143/1/2
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Samyak One Silver Avenue →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Samyak One Silver Avenue: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Samyak One Silver Avenue
What is the possession date of Samyak One Silver Avenue?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Samyak One Silver Avenue in Kamatghar, Thane is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Samyak One Silver Avenue?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Samyak One Silver Avenue's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Samyak One Silver Avenue?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Samyak One Silver Avenue in Kamatghar, Thane is P51700055921.
Is Samyak One Silver Avenue registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Samyak One Silver Avenue is registered as P51700055921 and its status is "Registered and active".
What is the current construction status of Samyak One Silver Avenue? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Samyak One Silver Avenue's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 70% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Samyak One Silver Avenue have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Samyak One Silver Avenue safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Samyak One Silver Avenue is registered on MahaRERA as P51700055921, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Samyak One Silver Avenue?
Samyak One Silver Avenue is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Samyak One Silver Avenue?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Samyak One Silver Avenue: gharkundli.com/tools/property-cost-calculator
Has Samyak One Silver Avenue received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Samyak One Silver Avenue is still under construction, with 30 April 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Samyak One Silver Avenue uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Samyak One Silver Avenue was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Samyak One Silver Avenue's possession date changes?
The latest dates are on Samyak One Silver Avenue's MahaRERA page (P51700055921). GharKundli's Kundli Watch sends a free WhatsApp update on Samyak One Silver Avenue every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Samyak One Silver Avenue have?
According to GharKundli's check of MahaRERA records (updated October 2026), Samyak One Silver Avenue has 3 buildings filed: BUILDING 1 with 33 floors and 67 units; BUILDING 2 with 32 floors and 120 units; BUILDING 3 COMMUNITY BUILDING NOT FOR SALE with 5 floors and 5 units.
How much parking does Samyak One Silver Avenue have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 243 covered car parking spaces for Samyak One Silver Avenue.
How big is the land of Samyak One Silver Avenue?
According to GharKundli's check of MahaRERA records (updated October 2026), Samyak One Silver Avenue stands on 6,411 sq m of land (about 1.6 acres), with 32,128 sq m of sanctioned built-up area and 658 sq m of recreational open space.
What are the reviews of Samyak One Silver Avenue?
Google Maps has reviews of Samyak One Silver Avenue written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Samyak One Silver Avenue?
Samyak One Silver Avenue by SHIV SAMYAK BUILDERS & DEVELOPERS LLP is in Kamatghar, Thane, pincode 421305, Maharashtra, and is registered on MahaRERA as P51700055921, per GharKundli's check of MahaRERA records. Its land is filed as 135/2/8, 135/3, 143/1/1, 143/1/2. GharKundli lists all 13 MahaRERA projects in Bhiwandi (421305).
How many flats are in Samyak One Silver Avenue, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Samyak One Silver Avenue has 179 homes in 3 towers registered on MahaRERA, and 36% of them are sold or booked.
When was Samyak One Silver Avenue registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Samyak One Silver Avenue was registered on MahaRERA on 29 April 2024. GharKundli did not find a title report on the land on file there.
Does Samyak One Silver Avenue have any legal issues or court cases?
No court cases are listed for Samyak One Silver Avenue on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Samyak One Silver Avenue?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHIV SAMYAK BUILDERS & DEVELOPERS LLP.
Check it yourself on MahaRERA
- How to check the possession date of Samyak One Silver Avenue
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Thane →
Other projects in Bhiwandi (421305)
- Shatrunjay Heights
- Sai Vatika Residency
- Vardhaman Vatika
- Sky City
- Siyara Signature
- Siyara Viva
- Vighnaharta Apartment
- Jangid Empire
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.