by VARDHAMAN ENTERPRISES · Kamatghar, Thane 421302Also near Bhiwandi, Narpoli, Naupada
What’s in the report? →Possession date of Vardhaman Vatika (MahaRERA P51700023391): 31 July 2027, moved from 15 December 2024 (27 months later). It has 65 homes, 66% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700023391, and currently active. Its completion date has moved from December 2024 to July 2027: 27 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700023391, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Vardhaman Vatika?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Vardhaman Vatika has moved
15 December 2024
Completion date given when the project was registered
31 March 2025
Extended at the builder's request (MahaRERA application EXT51700027564)
Reason the builder gave MahaRERA: “OUR PROJECT IS ALMOST COMPLETED AND WE HAVE ALSO APPLIED FOR OC. THEREFORE WE ARE APPLYING FOR EXTENTION TILL MARCH 2025. WE ARE HOPEFUL OF GETTING OC BEFORE OC”
31 December 2025
Extended at the builder's request (MahaRERA application EA19072502108)
Reason the builder gave MahaRERA: “OUR BUILDING IS COMPLETED AND WE HAVE ALSO APPLIED FOR OC”
31 March 2027
Extended at the builder's request (MahaRERA application EA28032620419)
Reason the builder gave MahaRERA: “we have obtained part oc and we have also applied for full oc. therefore we want extenion”
31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Vardhaman Vatika’s extension records on MahaRERA (P51700023391), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vardhaman Vatika
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700023391
- Status
- Registered and active
- Builder
- VARDHAMAN ENTERPRISES
- Location
- Kamatghar, Thane · 421302
- Project type
- Residential / Group Housing
- Registered on
- 12 Dec 2019
- Completion date at registration
- December 2024
- Latest completion date
- July 2027
- Delay so far
- 27 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 65
- Sold or booked
- 66%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of Vardhaman Vatika, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| VARDHAMAN VATIKA | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- VARDHAMAN VATIKA: covers 12 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vardhaman Vatika every 1–2 months.
Vardhaman Vatika: buildings, flats and land, as filed on MahaRERA
- Buildings: VARDHAMAN VATIKA (12 floors, 65 units)
- Car parking: 18 covered
- Land: 1,242 sq m (about 0.3 acres) · sanctioned built-up 3,949 sq m · recreational space 212 sq m
- Land, as filed: SNO 123 HISSA NO 1 SNO127 HISSA NO 1 AND 2
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Gandhi AND Samani Enterprises (a group of 2 linked companies) has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 7 months late). No complaints on MahaRERA.
Read Google reviews of Vardhaman Vatika →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vardhaman Vatika: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Vardhaman Vatika
What is the possession date of Vardhaman Vatika?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vardhaman Vatika in Kamatghar, Thane is 31 July 2027 — 27 months later than 15 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 27 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Vardhaman Vatika?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vardhaman Vatika's builder has filed on MahaRERA, the official one, is 31 July 2027, already 27 months later than the 15 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vardhaman Vatika extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Vatika's builder applied to MahaRERA to extend the completion date 3 times: to 31 March 2025, giving the reason "OUR PROJECT IS ALMOST COMPLETED AND WE HAVE ALSO APPLIED FOR OC. THEREFORE WE ARE APPLYING FOR EXTENTION TILL MARCH 2025. WE ARE HOPEFUL OF GETTING OC BEFORE OC"; to 31 December 2025, giving the reason "OUR BUILDING IS COMPLETED AND WE HAVE ALSO APPLIED FOR OC"; to 31 March 2027, giving the reason "we have obtained part oc and we have also applied for full oc. therefore we want extenion". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Vardhaman Vatika?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vardhaman Vatika in Kamatghar, Thane is P51700023391.
Is Vardhaman Vatika registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Vatika is registered as P51700023391 and its status is "Registered and active".
What is the current construction status of Vardhaman Vatika? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Vatika's status on MahaRERA is "Registered and active". As filed by the builder, slab work on VARDHAMAN VATIKA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Vardhaman Vatika have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Vardhaman Vatika safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Vatika is registered on MahaRERA as P51700023391, its completion date has moved 27 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Vardhaman Vatika?
Vardhaman Vatika is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Vardhaman Vatika?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Vardhaman Vatika: gharkundli.com/tools/property-cost-calculator
Has Vardhaman Vatika received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Vatika is still under construction, with 31 July 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Vardhaman Vatika uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vardhaman Vatika was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Vardhaman Vatika's possession date changes?
The latest dates are on Vardhaman Vatika's MahaRERA page (P51700023391). GharKundli's Kundli Watch sends a free WhatsApp update on Vardhaman Vatika every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vardhaman Vatika have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Vatika has one building filed: VARDHAMAN VATIKA with 12 floors and 65 units.
How much parking does Vardhaman Vatika have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 18 covered car parking spaces for Vardhaman Vatika.
How big is the land of Vardhaman Vatika?
According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Vatika stands on 1,242 sq m of land (about 0.3 acres), with 3,949 sq m of sanctioned built-up area and 212 sq m of recreational open space.
What is the track record of Vardhaman Vatika's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Gandhi AND Samani Enterprises (a group of 2 linked companies) has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 7 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Vardhaman Vatika?
Google Maps has reviews of Vardhaman Vatika written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Vardhaman Vatika?
Vardhaman Vatika by VARDHAMAN ENTERPRISES is in Kamatghar, Thane, pincode 421302 (near Bhiwandi, Narpoli, Naupada), Maharashtra, and is registered on MahaRERA as P51700023391, per GharKundli's check of MahaRERA records. Its land is filed as SNO 123 HISSA NO 1 SNO127 HISSA NO 1 AND 2. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).
How many flats are in Vardhaman Vatika, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Vatika has 65 homes in 1 tower registered on MahaRERA, and 66% of them are sold or booked.
When was Vardhaman Vatika registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vardhaman Vatika was registered on MahaRERA on 12 December 2019. GharKundli did not find a title report on the land on file there.
Does Vardhaman Vatika have any legal issues or court cases?
No court cases are listed for Vardhaman Vatika on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Vardhaman Vatika?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VARDHAMAN ENTERPRISES, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Vardhaman Vatika
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Bhiwandi (421302)
- Shatrunjay Heights
- Sky City
- Sai Vatika Residency
- Siyara Signature
- Siyara Viva
- One Silver Avenue
- Vighnaharta Apartment
- Jangid Empire
Other projects by VARDHAMAN ENTERPRISES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.