by SHREEYA PROPERTIES · Back side of DSP Bunglow, Ratnagiri

Possession date of MEGHPUSHPA: 30 June 2022, moved from 31 December 2019 (30 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52800011470. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (June 2022) has passed.

What do you want to know about MEGHPUSHPA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MEGHPUSHPA has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT52800005076)

    Reason the builder gave MahaRERA:
    “The Conveyance of the Project Land in favor of Promoter is not yet completed, due to which, construction on the project land could not be completed. The Promoter will get the Conveyance Document registered in short period and will proceed f…” Read the full reason“The Conveyance of the Project Land in favor of Promoter is not yet completed, due to which, construction on the project land could not be completed. The Promoter will get the Conveyance Document registered in short period and will proceed further for completion of the Project.”
  3. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT52800010279)

    Reason the builder gave MahaRERA:
    “Promoter has duly obtained project registration extension u/s 6 of RERA up to 30/12/2020 and further MahaRERA by virtue of MahaRERA Order No 14 /2020 dated 18/05/2020 has extended project registration automatically up to 30/06/2021. Further…” Read the full reason“Promoter has duly obtained project registration extension u/s 6 of RERA up to 30/12/2020 and further MahaRERA by virtue of MahaRERA Order No 14 /2020 dated 18/05/2020 has extended project registration automatically up to 30/06/2021. Furthermore due to present strict restrictions by Government authorities because of second wave of covid-19 and also due to migration of labour, the pace of construction activities at real estate project sites has disrupted considerably.”

Source: MEGHPUSHPA’s extension records on MahaRERA (P52800011470), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MEGHPUSHPA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52800011470
Status
Lapsed (registration period ended)
Builder
SHREEYA PROPERTIES
Location
Back side of DSP Bunglow, Ratnagiri · 415612
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
December 2019
Latest completion date
June 2022
Delay so far
30 months
Homes
59
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of MEGHPUSHPA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A AND B100%100%25%0%
WING C ROW BUNGLOW0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MEGHPUSHPA every month.

MEGHPUSHPA: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING A AND B (8 floors) · WING C ROW BUNGLOW (2 floors)
  • Land: 3,300 sq m (about 0.8 acres) · sanctioned built-up 3,960 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MEGHPUSHPA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MEGHPUSHPA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MEGHPUSHPA

What is the possession date of MEGHPUSHPA?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MEGHPUSHPA in Back side of DSP Bunglow, Ratnagiri is 30 June 2022 — 30 months later than 31 December 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for MEGHPUSHPA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MEGHPUSHPA's builder has filed on MahaRERA, the official one, is 30 June 2022, already 30 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MEGHPUSHPA extended?

According to GharKundli's check of MahaRERA records (updated November 2026), MEGHPUSHPA's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2020, giving the reason "The Conveyance of the Project Land in favor of Promoter is not yet completed, due to which, construction on the project land could not be completed. The Promoter will get the Conveyance Document registered in short period and will proceed further for completion of the Project."; to 30 June 2022, giving the reason "Promoter has duly obtained project registration extension u/s 6 of RERA up to 30/12/2020 and further MahaRERA by virtue of MahaRERA Order No 14 /2020 dated 18/05/2020 has extended project registration automatically up to 30/06/2021. Furthermore due to present strict restrictions by Government authorities because of second wave of covid-19 and also due to migration of labour, the pace of construction activities at real estate project sites has disrupted considerably.".

What is the RERA number of MEGHPUSHPA?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MEGHPUSHPA in Back side of DSP Bunglow, Ratnagiri is P52800011470.

Is MEGHPUSHPA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MEGHPUSHPA is registered as P52800011470 and its status is "Lapsed (registration period ended)".

What is the construction status of MEGHPUSHPA?

According to GharKundli's check of MahaRERA records (updated November 2026), MEGHPUSHPA's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does MEGHPUSHPA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is MEGHPUSHPA safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), MEGHPUSHPA is registered on MahaRERA as P52800011470, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MEGHPUSHPA's possession date changes?

The latest dates are on MEGHPUSHPA's MahaRERA page (P52800011470). GharKundli's Kundli Watch sends a free WhatsApp update on MEGHPUSHPA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MEGHPUSHPA have?

According to GharKundli's check of MahaRERA records (updated November 2026), MEGHPUSHPA has 2 buildings filed: WING A AND B with 8 floors; WING C ROW BUNGLOW with 2 floors.

How big is the land of MEGHPUSHPA?

According to GharKundli's check of MahaRERA records (updated November 2026), MEGHPUSHPA stands on 3,300 sq m of land (about 0.8 acres), with 3,960 sq m of sanctioned built-up area.

Where can I read reviews of MEGHPUSHPA?

Google Maps has reviews of MEGHPUSHPA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MEGHPUSHPA?

MEGHPUSHPA by SHREEYA PROPERTIES is in Back side of DSP Bunglow, Ratnagiri (pincode 415612), Maharashtra, and is registered on MahaRERA as P52800011470, per GharKundli's check of MahaRERA records.

How many homes are in MEGHPUSHPA?

According to GharKundli's check of MahaRERA records (updated November 2026), MEGHPUSHPA has 59 homes in 2 towers registered on MahaRERA.

When was MEGHPUSHPA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MEGHPUSHPA was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on MEGHPUSHPA?

No court cases are listed for MEGHPUSHPA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of MEGHPUSHPA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREEYA PROPERTIES.