PRINCE AVENUE
by SHAKTI DEVELOPERS · Kon Gaon, Thane
Possession date of PRINCE AVENUE: 30 June 2027, moved from 2 September 2023 (45 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700025661, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about PRINCE AVENUE?
How the possession date of PRINCE AVENUE has moved
2 September 2023
Completion date given when the project was registered
31 August 2024
Extended at the builder's request (MahaRERA application EXT51700017456)
Reason the builder gave MahaRERA:
“Due to Covid Lockdown, the work could not take up the pace. So we humbly request you to consider extending the completion date. Also, there has been no progress in terms of bookings as such. The update of the project on MAHARERA shall be do…” Read the full reason
“Due to Covid Lockdown, the work could not take up the pace. So we humbly request you to consider extending the completion date. Also, there has been no progress in terms of bookings as such. The update of the project on MAHARERA shall be done, post completion of Tax Audit of financials for FY 2022-23 by 31.10.2023. Thanking you in anticipation”25 November 2025
Extended at the builder's request (MahaRERA application EXT51700025422)
Reason the builder gave MahaRERA:
“• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We have been grappled with shortage of labour and a demand slump chall…” Read the full reason
“• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We have been grappled with shortage of labour and a demand slump challenge triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. • Due to unavailability of skilled labour and labour migration issues, project is affected a lot. Even contractors are asking us to allow them more time due to labour issues. • The geopolitical tension around the globe has led…”30 June 2026
Extended at the builder's request (MahaRERA application EA17112518341)
Reason the builder gave MahaRERA:
“Dear sir/Madam, I here with request you for extension of completion of the project namely Shakti Developers "PRINCE AVENUE", originally due on 25/11/2025. Due to unforeseen circumstances, we are unable to meet the original deadline. The rea…” Read the full reason
“Dear sir/Madam, I here with request you for extension of completion of the project namely Shakti Developers "PRINCE AVENUE", originally due on 25/11/2025. Due to unforeseen circumstances, we are unable to meet the original deadline. The reasons for this request include all finishing work for completion of the project. Despite our best efforts to mitigate these issues, they have significantly impacted the project timeline. Given these circumstances, we respectfully request an extension of six months, with the new proposed completion date being 25/05/2026. We are committed to completing the p…”30 June 2027
Extended at the builder's request (MahaRERA application EA12082622112)
Reason the builder gave MahaRERA:
“The Project got delayed due to an unforeseen shortage of labour, caused by health crises, migration of workers, etc. our project has faced significant delays in meeting the originally scheduled construction milestones. Despite our best effo…” Read the full reason
“The Project got delayed due to an unforeseen shortage of labour, caused by health crises, migration of workers, etc. our project has faced significant delays in meeting the originally scheduled construction milestones. Despite our best efforts to secure adequate labour resources, the unavailability of skilled labour has led to unavoidable setbacks in the progress of the work. Once the above work is completed, we will make application for Completion Certificate (CC)/Occupancy Certificate (OC) with the respective Municipal Authority. Obtaining CC/OC will take a few months; hence we make a hum…”
Source: PRINCE AVENUE’s extension records on MahaRERA (P51700025661), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PRINCE AVENUE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700025661
- Status
- Registered and active
- Builder
- SHAKTI DEVELOPERS
- Location
- Kon Gaon, Thane · 421302
- Project type
- Residential / Group Housing
- Registered on
- 1 Jul 2020
- Completion date at registration
- September 2023
- Latest completion date
- June 2027
- Delay so far
- 45 months
- Homes
- 85
- Sold or booked
- 72%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 8
Construction progress of PRINCE AVENUE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PRINCE AVENUE 1 | 100% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- PRINCE AVENUE 1: covers 11TH HABITABLE FLOORS
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PRINCE AVENUE every month.
PRINCE AVENUE: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 276 – 812 | 56 |
| 1 Room Kitchen | 276 – 573 | 29 |
- Buildings: PRINCE AVENUE 1 (11 floors, 85 units)
- Land: 2,940 sq m (about 0.7 acres) · sanctioned built-up 1,813 sq m · recreational space 289 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of PRINCE AVENUE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PRINCE AVENUE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PRINCE AVENUE
What is the possession date of PRINCE AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PRINCE AVENUE in Kon Gaon, Thane is 30 June 2027 — 45 months later than 2 September 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for PRINCE AVENUE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PRINCE AVENUE's builder has filed on MahaRERA, the official one, is 30 June 2027, already 45 months later than the 2 September 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PRINCE AVENUE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), PRINCE AVENUE's builder applied to MahaRERA to extend the completion date 4 times: to 31 August 2024, giving the reason "Due to Covid Lockdown, the work could not take up the pace. So we humbly request you to consider extending the completion date. Also, there has been no progress in terms of bookings as such. The update of the project on MAHARERA shall be done, post completion of Tax Audit of financials for FY 2022-23 by 31.10.2023. Thanking you in anticipation"; to 25 November 2025, giving the reason "• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We have been grappled with shortage of labour and a demand slump challenge triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. • Due to unavailability of skilled labour and labour migration issues, project is affected a lot. Even contractors are asking us to allow them more time due to labour issues. • The geopolitical tension around the globe has led…"; to 30 June 2026, giving the reason "Dear sir/Madam, I here with request you for extension of completion of the project namely Shakti Developers "PRINCE AVENUE", originally due on 25/11/2025. Due to unforeseen circumstances, we are unable to meet the original deadline. The reasons for this request include all finishing work for completion of the project. Despite our best efforts to mitigate these issues, they have significantly impacted the project timeline. Given these circumstances, we respectfully request an extension of six months, with the new proposed completion date being 25/05/2026. We are committed to completing the p…"; to 30 June 2027, giving the reason "The Project got delayed due to an unforeseen shortage of labour, caused by health crises, migration of workers, etc. our project has faced significant delays in meeting the originally scheduled construction milestones. Despite our best efforts to secure adequate labour resources, the unavailability of skilled labour has led to unavoidable setbacks in the progress of the work. Once the above work is completed, we will make application for Completion Certificate (CC)/Occupancy Certificate (OC) with the respective Municipal Authority. Obtaining CC/OC will take a few months; hence we make a hum…".
What is the RERA number of PRINCE AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PRINCE AVENUE in Kon Gaon, Thane is P51700025661.
Is PRINCE AVENUE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PRINCE AVENUE is registered as P51700025661 and its status is "Registered and active".
What is the construction status of PRINCE AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), PRINCE AVENUE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PRINCE AVENUE 1 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does PRINCE AVENUE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is PRINCE AVENUE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), PRINCE AVENUE is registered on MahaRERA as P51700025661, its completion date has moved 45 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PRINCE AVENUE's possession date changes?
The latest dates are on PRINCE AVENUE's MahaRERA page (P51700025661). GharKundli's Kundli Watch sends a free WhatsApp update on PRINCE AVENUE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PRINCE AVENUE have?
According to GharKundli's check of MahaRERA records (updated October 2026), PRINCE AVENUE has one building filed: PRINCE AVENUE 1 with 11 floors and 85 units.
What are the flat sizes (carpet area) in PRINCE AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for PRINCE AVENUE: 1 BHK: 276 to 812 sq ft carpet (56 homes); 1 Room Kitchen: 276 to 573 sq ft carpet (29 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of PRINCE AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), PRINCE AVENUE stands on 2,940 sq m of land (about 0.7 acres), with 1,813 sq m of sanctioned built-up area and 289 sq m of recreational open space.
Where can I read reviews of PRINCE AVENUE?
Google Maps has reviews of PRINCE AVENUE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PRINCE AVENUE?
PRINCE AVENUE by SHAKTI DEVELOPERS is in Kon Gaon, Thane (pincode 421302), Maharashtra, and is registered on MahaRERA as P51700025661, per GharKundli's check of MahaRERA records.
How many homes are in PRINCE AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), PRINCE AVENUE has 85 homes in 1 tower registered on MahaRERA, and 72% of them are sold or booked.
When was PRINCE AVENUE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PRINCE AVENUE was registered on MahaRERA on 1 July 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on PRINCE AVENUE?
No court cases are listed for PRINCE AVENUE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of PRINCE AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHAKTI DEVELOPERS, which has 8 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of PRINCE AVENUE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Bhiwandi
- CONTINENTAL FUTURA
- SAI DARSHAN D WING
- ASHOKA COMPLEX
- KOHINOOR UPTOWN T1 & T6
- REGAL SQUARE PH 4 TOWER 6 AND 8
- SAI DEEP RESIDENCY
- NEELKANTH SADAN
- THE PALLAZO
Other projects by SHAKTI DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.