by KHUSHI AXIS INFRATECH LLP · Bhiwandi, Thane 421302

What’s in the report? →

Possession date of Khushi Axis World (MahaRERA P51700031265): 30 April 2027, moved from 31 December 2024 (24 months later). It has 63 homes, 70% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700031265, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700031265, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Khushi Axis World?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Khushi Axis World has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT51700025598)

    Reason the builder gave MahaRERA:
    “We write to formally request an extension of the completion Timeline for our project. Khushi Axis World, registered under RERA with Registration No. P51700031265. This extension is sought due to unforeseen delays caused by multiple factors…” Read the full reason“We write to formally request an extension of the completion Timeline for our project. Khushi Axis World, registered under RERA with Registration No. P51700031265. This extension is sought due to unforeseen delays caused by multiple factors beyond our control, which we would like to bring to your kind attention 1 Delays in I-to-R Filing Process The 1-to-R process, which typically takes 2-3 months, extended to 8 months in our case due to corrections raised by the concerned authorities. Despite our best efforts to expedite the process, the additional time required for compliance caused signifi…”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Khushi Axis World’s extension records on MahaRERA (P51700031265), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Khushi Axis World

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700031265
Status
Registered and active
Builder
KHUSHI AXIS INFRATECH LLP
Location
Bhiwandi, Thane · 421302
Project type
Residential / Group Housing
Registered on
15 Oct 2021
Completion date at registration
December 2024
Latest completion date
April 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
63
Sold or booked
70%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Khushi Axis World, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KHUSHI AXIS WORLD100%100%100%100%
KHUSHI AXIS WORLD A WING100%68%40%10%

Commencement certificate (CC), as filed on MahaRERA

  • KHUSHI AXIS WORLD: covers BASEMENT+STILT+5 FLOORS
  • KHUSHI AXIS WORLD A WING: covers BASEMENT+STILT+8 FLOORS

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Khushi Axis World every 1–2 months.

Khushi Axis World: buildings, flats and land, as filed on MahaRERA

  • Buildings: KHUSHI AXIS WORLD (7 floors, 269 units) · KHUSHI AXIS WORLD A WING (9 floors, 63 units)
  • Land: 6,225 sq m (about 1.5 acres) · sanctioned built-up 14,725 sq m · recreational space 725 sq m
  • Land, as filed: SURVEY NO.21/1/C,21/1/E,21/1/D MANKOLI NAKA, BHIWANDI,421302
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Khushi Axis World →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Khushi Axis World: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Khushi Axis World

What is the possession date of Khushi Axis World?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Khushi Axis World in Bhiwandi, Thane is 30 April 2027 — 24 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Khushi Axis World?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Khushi Axis World's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Khushi Axis World extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Khushi Axis World's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "We write to formally request an extension of the completion Timeline for our project. Khushi Axis World, registered under RERA with Registration No. P51700031265. This extension is sought due to unforeseen delays caused by multiple factors beyond our control, which we would like to bring to your kind attention 1 Delays in I-to-R Filing Process The 1-to-R process, which typically takes 2-3 months, extended to 8 months in our case due to corrections raised by the concerned authorities. Despite our best efforts to expedite the process, the additional time required for compliance caused signifi…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Khushi Axis World?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Khushi Axis World in Bhiwandi, Thane is P51700031265.

Is Khushi Axis World registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Khushi Axis World is registered as P51700031265 and its status is "Registered and active".

What is the current construction status of Khushi Axis World? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Khushi Axis World's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 68% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Khushi Axis World have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Khushi Axis World safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Khushi Axis World is registered on MahaRERA as P51700031265, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Khushi Axis World?

Khushi Axis World is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Khushi Axis World?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Khushi Axis World: gharkundli.com/tools/property-cost-calculator

Has Khushi Axis World received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Khushi Axis World is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Khushi Axis World uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Khushi Axis World was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Khushi Axis World's possession date changes?

The latest dates are on Khushi Axis World's MahaRERA page (P51700031265). GharKundli's Kundli Watch sends a free WhatsApp update on Khushi Axis World every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Khushi Axis World have?

According to GharKundli's check of MahaRERA records (updated October 2026), Khushi Axis World has 2 buildings filed: KHUSHI AXIS WORLD with 7 floors and 269 units; KHUSHI AXIS WORLD A WING with 9 floors and 63 units.

How big is the land of Khushi Axis World?

According to GharKundli's check of MahaRERA records (updated October 2026), Khushi Axis World stands on 6,225 sq m of land (about 1.5 acres), with 14,725 sq m of sanctioned built-up area and 725 sq m of recreational open space.

What are the reviews of Khushi Axis World?

Google Maps has reviews of Khushi Axis World written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Khushi Axis World?

Khushi Axis World by KHUSHI AXIS INFRATECH LLP is in Bhiwandi, Thane, pincode 421302, Maharashtra, and is registered on MahaRERA as P51700031265, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO.21/1/C,21/1/E,21/1/D MANKOLI NAKA, BHIWANDI,421302. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).

How many flats are in Khushi Axis World, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Khushi Axis World has 63 homes in 2 towers registered on MahaRERA, and 70% of them are sold or booked.

When was Khushi Axis World registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Khushi Axis World was registered on MahaRERA on 15 October 2021. GharKundli did not find a title report on the land on file there.

Does Khushi Axis World have any legal issues or court cases?

No court cases are listed for Khushi Axis World on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Khushi Axis World?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KHUSHI AXIS INFRATECH LLP.

All projects with possession due in 2027 in Thane →

Other projects in Bhiwandi (421302)

All 382 projects in Bhiwandi (421302) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.