Regency Luxuria Phase I
by REGENCY NIRMAN LTD · Dombivli, Thane
Possession date of Regency Luxuria Phase I: 31 December 2025, moved from 30 September 2025 (3 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700031251. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Regency Luxuria Phase I?
How the possession date of Regency Luxuria Phase I has moved
30 September 2025
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51700012085)
Reason the builder gave MahaRERA:
“The project is under construction & we are putting our full efforts to complete it at the earliest. As we are constructing high rise building and we need skilled and experienced labour to complete the project on time, but it is getting dela…” Read the full reason
“The project is under construction & we are putting our full efforts to complete it at the earliest. As we are constructing high rise building and we need skilled and experienced labour to complete the project on time, but it is getting delayed due to unavailability of such labour in mofussil area where the project is situated. Further due to onset of monsoon we are facing difficulties. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to the reasons explained above it is getting delayed.”
Source: Regency Luxuria Phase I’s extension records on MahaRERA (P51700031251), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Regency Luxuria Phase I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Regency Luxuria Phase IIP51700053314 · possession 30 Apr 2027
- Regency Luxuria Phase IIIP51700078991 · possession 30 Oct 2028
- MahaRERA registration
- P51700031251
- Status
- Lapsed (registration period ended)
- Builder
- REGENCY NIRMAN LTD
- Location
- Dombivli, Thane · 421203
- Project type
- Residential / Group Housing
- Registered on
- 15 Oct 2021
- Completion date at registration
- September 2025
- Latest completion date
- December 2025
- Delay so far
- 3 months
- Homes
- 240
- Sold or booked
- 83%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 28
Construction progress of Regency Luxuria Phase I, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building No 4 | 100% | 100% | 100% | 100% |
| Building No 4 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Building No 4: covers 30 floors
- Building No 4: covers 30 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Regency Luxuria Phase I every month.
Regency Luxuria Phase I: buildings, flats and land, as filed on MahaRERA
- Buildings: Building No 4 (38 floors, 240 units) · Building No 4 (38 floors)
- Land: 11,380 sq m (about 2.8 acres) · sanctioned built-up 30,502 sq m · recreational space 783 sq m
The builder’s record and reviews
Regency Nirman (a group of 2 linked companies) has 33 projects on MahaRERA since 2017, this one included. Of the 32 GharKundli has checked: 24 finished, 19 within the promised date and 5 needed more time (typically 12 months); 6 still being built, 1 past the promised date (typically 10 months late); 2 lapsed. 9 complaints on MahaRERA across 8 projects.
Read Google reviews of Regency Luxuria Phase I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Regency Luxuria Phase I: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Regency Luxuria Phase I
What is the possession date of Regency Luxuria Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Regency Luxuria Phase I in Dombivli, Thane is 31 December 2025 — 3 months later than 30 September 2025, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Regency Luxuria Phase I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Regency Luxuria Phase I's builder has filed on MahaRERA, the official one, is 31 December 2025, already 3 months later than the 30 September 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Regency Luxuria Phase I extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Regency Luxuria Phase I's builder applied to MahaRERA to extend the completion date once: to 31 December 2025, giving the reason "The project is under construction & we are putting our full efforts to complete it at the earliest. As we are constructing high rise building and we need skilled and experienced labour to complete the project on time, but it is getting delayed due to unavailability of such labour in mofussil area where the project is situated. Further due to onset of monsoon we are facing difficulties. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to the reasons explained above it is getting delayed.".
What is the RERA number of Regency Luxuria Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Regency Luxuria Phase I in Dombivli, Thane is P51700031251.
Is Regency Luxuria Phase I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Regency Luxuria Phase I is registered as P51700031251 and its status is "Lapsed (registration period ended)".
What is the construction status of Regency Luxuria Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), Regency Luxuria Phase I's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Regency Luxuria Phase I have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Regency Luxuria Phase I safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Regency Luxuria Phase I is registered on MahaRERA as P51700031251, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 3 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Regency Luxuria Phase I have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Regency Luxuria Phase II (P51700053314, possession 30 Apr 2027); Regency Luxuria Phase III (P51700078991, possession 30 Oct 2028). Check that your agreement names the registration of your own wing.
How can I get updates if Regency Luxuria Phase I's possession date changes?
The latest dates are on Regency Luxuria Phase I's MahaRERA page (P51700031251). GharKundli's Kundli Watch sends a free WhatsApp update on Regency Luxuria Phase I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Regency Luxuria Phase I have?
According to GharKundli's check of MahaRERA records (updated November 2026), Regency Luxuria Phase I has 2 buildings filed: Building No 4 with 38 floors and 240 units; Building No 4 with 38 floors.
How big is the land of Regency Luxuria Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), Regency Luxuria Phase I stands on 11,380 sq m of land (about 2.8 acres), with 30,502 sq m of sanctioned built-up area and 783 sq m of recreational open space.
What is the track record of Regency Luxuria Phase I's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Regency Nirman (a group of 2 linked companies) has 33 projects on MahaRERA since 2017, this one included. Of the 32 GharKundli has checked: 24 finished, 19 within the promised date and 5 needed more time (typically 12 months); 6 still being built, 1 past the promised date (typically 10 months late); 2 lapsed. 9 complaints on MahaRERA across 8 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Regency Luxuria Phase I?
Google Maps has reviews of Regency Luxuria Phase I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Regency Luxuria Phase I?
Regency Luxuria Phase I by REGENCY NIRMAN LTD is in Dombivli, Thane (pincode 421203), Maharashtra, and is registered on MahaRERA as P51700031251, per GharKundli's check of MahaRERA records.
How many homes are in Regency Luxuria Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), Regency Luxuria Phase I has 240 homes in 2 towers registered on MahaRERA, and 83% of them are sold or booked.
When was Regency Luxuria Phase I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Regency Luxuria Phase I was registered on MahaRERA on 15 October 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Regency Luxuria Phase I?
No court cases are listed for Regency Luxuria Phase I on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Regency Luxuria Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is REGENCY NIRMAN LTD, which has 28 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Regency Luxuria Phase I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 421203
- LAXMI CASTLE
- USHAKIRAN ENCLAVE
- LA CENTRUM
- Trinity
- LA GRANDEUR
- Regency Luxuria Phase II
- VIDHI IMPRESSION
- SHREE EKDANT ENCLAVE
Other projects by REGENCY NIRMAN LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.