Nirvana Gardens Phase 2 Wing B Iris

by Sqylines Builders LLP · Kalyan, Thane 421301

What’s in the report? →

Possession date of Nirvana Gardens Phase 2 Wing B Iris (MahaRERA P51700076638): 30 January 2030, moved from 31 July 2028 (14 months later). It has 141 homes, 9% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700076638, and currently active. Its completion date has moved from July 2028 to January 2030: 14 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700076638, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Nirvana Gardens Phase 2 Wing B Iris?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Nirvana Gardens Phase 2 Wing B Iris has moved

  1. 31 July 2028

    Completion date given when the project was registered

  2. 30 September 2029

    Extended at the builder's request (MahaRERA application EA17042620656)

    Reason the builder gave MahaRERA: “Revised timeline in accordance with cashflow and purchase of additional TDR in the project with revised plans vide correction application applied on 17.01.2026 which is approved and revised certificate is generated on 17/04/2026”
  3. 30 January 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Nirvana Gardens Phase 2 Wing B Iris’s extension records on MahaRERA (P51700076638), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Nirvana Gardens Phase 2 Wing B Iris

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700076638
Status
Registered and active
Builder
Sqylines Builders LLP
Location
Kalyan, Thane · 421301
Project type
Others
Registered on
18 Jun 2024
Completion date at registration
July 2028
Latest completion date
January 2030
Delay so far
14 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
141
Sold or booked
9%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Nirvana Gardens Phase 2 Wing B Iris, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Nirvana Gardens Phase 2 B Iris100%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Nirvana Gardens Phase 2 B Iris: covers 16 floors

Latest CC order on MahaRERA: dated 05/01/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nirvana Gardens Phase 2 Wing B Iris every 1–2 months.

Nirvana Gardens Phase 2 Wing B Iris: buildings, flats and land, as filed on MahaRERA

  • Buildings: Nirvana Gardens Phase 2 B Iris (16 floors, 156 units)
  • Car parking: 24 covered, 35 open
  • Land: 10,743 sq m (about 2.7 acres) · sanctioned built-up 10,522 sq m · recreational space 636 sq m
  • Land, as filed: 33/1/A,33/1/B,/33/1/C/1,33/1/C/2,33/1/C/3,33/1/D,33/1/F,33/1/H,33/1/E,33/1/L,33/1/M,33/1/N
  • Map: Get directions

The builder’s record and reviews

Tharwani Properties (a group of 2 linked companies) has 8 projects on MahaRERA since 2022, this one included. Of the 8 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 4 months); 5 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Nirvana Gardens Phase 2 Wing B Iris →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Nirvana Gardens Phase 2 Wing B Iris: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Nirvana Gardens Phase 2 Wing B Iris

What is the possession date of Nirvana Gardens Phase 2 Wing B Iris?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Nirvana Gardens Phase 2 Wing B Iris in Kalyan, Thane is 30 January 2030 — 14 months later than 31 July 2028, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 14 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Nirvana Gardens Phase 2 Wing B Iris?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Nirvana Gardens Phase 2 Wing B Iris's builder has filed on MahaRERA, the official one, is 30 January 2030, already 14 months later than the 31 July 2028 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Nirvana Gardens Phase 2 Wing B Iris extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirvana Gardens Phase 2 Wing B Iris's builder applied to MahaRERA to extend the completion date once: to 30 September 2029, giving the reason "Revised timeline in accordance with cashflow and purchase of additional TDR in the project with revised plans vide correction application applied on 17.01.2026 which is approved and revised certificate is generated on 17/04/2026". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Nirvana Gardens Phase 2 Wing B Iris?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Nirvana Gardens Phase 2 Wing B Iris in Kalyan, Thane is P51700076638.

Is Nirvana Gardens Phase 2 Wing B Iris registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirvana Gardens Phase 2 Wing B Iris is registered as P51700076638 and its status is "Registered and active".

What is the current construction status of Nirvana Gardens Phase 2 Wing B Iris? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirvana Gardens Phase 2 Wing B Iris's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Nirvana Gardens Phase 2 B Iris is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Nirvana Gardens Phase 2 Wing B Iris have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Nirvana Gardens Phase 2 Wing B Iris safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirvana Gardens Phase 2 Wing B Iris is registered on MahaRERA as P51700076638, its completion date has moved 14 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Nirvana Gardens Phase 2 Wing B Iris?

Nirvana Gardens Phase 2 Wing B Iris is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Nirvana Gardens Phase 2 Wing B Iris?

For a flat in Nirvana Gardens Phase 2 Wing B Iris (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Nirvana Gardens Phase 2 Wing B Iris received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Nirvana Gardens Phase 2 Wing B Iris is still under construction, with 30 January 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Nirvana Gardens Phase 2 Wing B Iris uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Nirvana Gardens Phase 2 Wing B Iris was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Nirvana Gardens Phase 2 Wing B Iris's possession date changes?

The latest dates are on Nirvana Gardens Phase 2 Wing B Iris's MahaRERA page (P51700076638). GharKundli's Kundli Watch sends a free WhatsApp update on Nirvana Gardens Phase 2 Wing B Iris every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Nirvana Gardens Phase 2 Wing B Iris have?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirvana Gardens Phase 2 Wing B Iris has one building filed: Nirvana Gardens Phase 2 B Iris with 16 floors and 156 units.

How much parking does Nirvana Gardens Phase 2 Wing B Iris have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 24 covered and 35 open car parking spaces for Nirvana Gardens Phase 2 Wing B Iris.

How big is the land of Nirvana Gardens Phase 2 Wing B Iris?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirvana Gardens Phase 2 Wing B Iris stands on 10,743 sq m of land (about 2.7 acres), with 10,522 sq m of sanctioned built-up area and 636 sq m of recreational open space.

What is the track record of Nirvana Gardens Phase 2 Wing B Iris's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Tharwani Properties (a group of 2 linked companies) has 8 projects on MahaRERA since 2022, this one included. Of the 8 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 4 months); 5 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Nirvana Gardens Phase 2 Wing B Iris?

Google Maps has reviews of Nirvana Gardens Phase 2 Wing B Iris written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Nirvana Gardens Phase 2 Wing B Iris?

Nirvana Gardens Phase 2 Wing B Iris by Sqylines Builders LLP is in Kalyan, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700076638, per GharKundli's check of MahaRERA records. Its land is filed as 33/1/A,33/1/B,/33/1/C/1,33/1/C/2,33/1/C/3,33/1/D,33/1/F,33/1/H,33/1/E,33/1/L,33/1/M,33/1/N. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).

How many flats are in Nirvana Gardens Phase 2 Wing B Iris, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirvana Gardens Phase 2 Wing B Iris has 141 homes in 1 tower registered on MahaRERA, and 9% of them are sold or booked.

When was Nirvana Gardens Phase 2 Wing B Iris registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirvana Gardens Phase 2 Wing B Iris was registered on MahaRERA on 18 June 2024. GharKundli did not find a title report on the land on file there.

Does Nirvana Gardens Phase 2 Wing B Iris have any legal issues or court cases?

No court cases are listed for Nirvana Gardens Phase 2 Wing B Iris on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Nirvana Gardens Phase 2 Wing B Iris?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sqylines Builders LLP, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2030 in Thane →

Other projects in Kalyan (421301)

All 582 projects in Kalyan (421301) →

Other projects by Sqylines Builders LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.