BALLALESHWAR GALAXY
by BALLALESHWAR BUILDERS · Dombivli East, ThaneAlso near Vishnunagar, Dombivali I.A
Possession date of BALLALESHWAR GALAXY: 30 April 2031. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700080784, and currently active. Its completion date is now April 2031, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about BALLALESHWAR GALAXY?
How the possession date of BALLALESHWAR GALAXY has moved
31 December 2030
Completion date given when the project was registered
30 April 2031
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: BALLALESHWAR GALAXY’s extension records on MahaRERA (P51700080784), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on BALLALESHWAR GALAXY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2031 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700080784
- Status
- Registered and active
- Builder
- BALLALESHWAR BUILDERS
- Location
- Dombivli East, Thane · 421201
- Project type
- Others
- Registered on
- 7 Jul 2025
- Completion date at registration
- December 2030
- Latest completion date
- April 2031
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 36
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of BALLALESHWAR GALAXY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BLDG 2 | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on BALLALESHWAR GALAXY every month.
BALLALESHWAR GALAXY: buildings, flats and land, as filed on MahaRERA
- Buildings: BLDG 2 (8 floors)
- Land: 1,069 sq m (about 0.3 acres) · sanctioned built-up 2,498 sq m
- Boundaries filed include: VYANKATESHWAR SOCIETY, VYANKATESHVAR SOCIETY
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of BALLALESHWAR GALAXY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
BALLALESHWAR GALAXY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about BALLALESHWAR GALAXY
What is the possession date of BALLALESHWAR GALAXY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for BALLALESHWAR GALAXY in Dombivli East, Thane is 30 April 2031, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for BALLALESHWAR GALAXY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date BALLALESHWAR GALAXY's builder has filed on MahaRERA, the official one, is 30 April 2031, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of BALLALESHWAR GALAXY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of BALLALESHWAR GALAXY in Dombivli East, Thane is P51700080784.
Is BALLALESHWAR GALAXY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BALLALESHWAR GALAXY is registered as P51700080784 and its status is "Registered and active".
What is the construction status of BALLALESHWAR GALAXY?
According to GharKundli's check of MahaRERA records (updated October 2026), BALLALESHWAR GALAXY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BLDG 2 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does BALLALESHWAR GALAXY have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is BALLALESHWAR GALAXY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), BALLALESHWAR GALAXY is registered on MahaRERA as P51700080784, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if BALLALESHWAR GALAXY's possession date changes?
The latest dates are on BALLALESHWAR GALAXY's MahaRERA page (P51700080784). GharKundli's Kundli Watch sends a free WhatsApp update on BALLALESHWAR GALAXY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does BALLALESHWAR GALAXY have?
According to GharKundli's check of MahaRERA records (updated October 2026), BALLALESHWAR GALAXY has one building filed: BLDG 2 with 8 floors.
How big is the land of BALLALESHWAR GALAXY?
According to GharKundli's check of MahaRERA records (updated October 2026), BALLALESHWAR GALAXY stands on 1,069 sq m of land (about 0.3 acres), with 2,498 sq m of sanctioned built-up area.
Where can I read reviews of BALLALESHWAR GALAXY?
Google Maps has reviews of BALLALESHWAR GALAXY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is BALLALESHWAR GALAXY?
BALLALESHWAR GALAXY by BALLALESHWAR BUILDERS is in Dombivli East, Thane (pincode 421201), near Vishnunagar, Dombivali I.A, Maharashtra, and is registered on MahaRERA as P51700080784, per GharKundli's check of MahaRERA records. Its boundaries filed there include VYANKATESHWAR SOCIETY, VYANKATESHVAR SOCIETY.
How many homes are in BALLALESHWAR GALAXY?
According to GharKundli's check of MahaRERA records (updated October 2026), BALLALESHWAR GALAXY has 36 homes in 1 tower registered on MahaRERA.
When was BALLALESHWAR GALAXY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BALLALESHWAR GALAXY was registered on MahaRERA on 7 July 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on BALLALESHWAR GALAXY?
No court cases are listed for BALLALESHWAR GALAXY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of BALLALESHWAR GALAXY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is BALLALESHWAR BUILDERS.
Check it yourself on MahaRERA
- How to check the possession date of BALLALESHWAR GALAXY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2031 in Thane →
Other projects in pincode 421201
- MANGESHI DAZZLE II
- Balaji Govind
- SAGAR KUNJ HIGHLAND
- Mangeshi Dhara
- VASTU HERITAGE
- NAV SAMIDHA CO-OP HSG SOC LTD
- OM TRIMURTI DARSHAN
- SWAMI ELITE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.