SKYVIEW CHS
by HIRANIMANTHAN BUILDERS AND DEVELOPERS · Nehru Nagar, MumbaiAlso near Kurla East, Kurla West, Chembur
Possession: SKYVIEW CHS is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800008227. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SKYVIEW CHS?
How the possession date of SKYVIEW CHS has moved
30 December 2019
Completion date given when the project was registered
29 December 2020
Extended at the builder's request (MahaRERA application EXT51800003741)
Reason the builder gave MahaRERA: “In View of the further approvals received for proposed FSI/BUA, we need this time for construction of this proposed FSI area.”
1 June 2023
Extended at the builder's request (MahaRERA application EXT51800010103)
Reason the builder gave MahaRERA:
“We had completed entire development work of the project up to 16 floors as per the approved plans and shortly starting to give ‘Fit Out Possessions’ to the allottees. However we have not yet utilised full potential FSI of the project & for…” Read the full reason
“We had completed entire development work of the project up to 16 floors as per the approved plans and shortly starting to give ‘Fit Out Possessions’ to the allottees. However we have not yet utilised full potential FSI of the project & for such balance FSI we got the sanctions from the authorities just now & plans are also amended accordingly. Our structure is also designed to that capacity to absorb this FSI load. We also got consent from allottees. Hence we require additional time for completing our balance FSI construction.”30 November 2024
Extended at the builder's request (MahaRERA application EXT51800018113)
Reason the builder gave MahaRERA:
“Construction completed in full. No Development work is pending. We had applied for Full and final Occupancy Certificate. However Approving Authority has delayed OC . Hence we need extra time for completing OC Procedure and submit Form 4. We…” Read the full reason
“Construction completed in full. No Development work is pending. We had applied for Full and final Occupancy Certificate. However Approving Authority has delayed OC . Hence we need extra time for completing OC Procedure and submit Form 4. We already had received Part OC for 3 wings out of 5 wings. 3 Wings already occupied by Allottees.”30 November 2025
Extended at the builder's request (MahaRERA application EXT51800025076)
Reason the builder gave MahaRERA:
“Our project is completed in full. However due to change is development policies and procedures final Occupancy Certificate Process was halted in the area. We will get Final Full Occupancy certificate from MHADA only after completion of Poli…” Read the full reason
“Our project is completed in full. However due to change is development policies and procedures final Occupancy Certificate Process was halted in the area. We will get Final Full Occupancy certificate from MHADA only after completion of Policy Updating process by State Government. We or any other builder in vicinity do no have any idea of time line about State Government Process. Hence we had left with no option than to seek further extension of Validity RERA Registration”
Source: SKYVIEW CHS’s extension records on MahaRERA (P51800008227), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SKYVIEW CHS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the November 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800008227
- Status
- Completed
- Builder
- HIRANIMANTHAN BUILDERS AND DEVELOPERS
- Location
- Nehru Nagar, Mumbai · 400024
- Project type
- Residential / Group Housing
- Registered on
- 18 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- November 2025
- Delay so far
- 71 months
- Homes
- 283
- Sold or booked
- 92%
- Towers
- 5
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of SKYVIEW CHS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SKYVIEW CASTLE WING A | 100% | 100% | 100% | 100% |
| SKYVIEW CASTLE WING B | 100% | 100% | 100% | 100% |
| SKYVIEW CASTLE WING C | 100% | 100% | 100% | 100% |
| SKYVIEW CASTLE WING D | 100% | 100% | 100% | 100% |
| SKYVIEW CASTLE WING E | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- SKYVIEW CASTLE WING A: covers 16 floors
- SKYVIEW CASTLE WING B: covers 18 floors
- SKYVIEW CASTLE WING C: covers 18 floors
- SKYVIEW CASTLE WING D: covers 20 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SKYVIEW CHS every month.
SKYVIEW CHS: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 294 – 470 | 260 |
| 2 BHK | 673 | 18 |
| Shops | 98 – 274 | 10 |
| 1 Room Kitchen | 389 – 459 | 5 |
| Showroom | 224 | 1 |
- Buildings: SKYVIEW CASTLE WING A (18 floors, 64 units) · SKYVIEW CASTLE WING B (18 floors, 64 units) · SKYVIEW CASTLE WING C (18 floors, 64 units) · SKYVIEW CASTLE WING D (20 floors, 61 units) · SKYVIEW CASTLE WING E (20 floors, 41 units)
- Car parking: 41 covered, 5 open
- Land: 2,452 sq m (about 0.6 acres) · sanctioned built-up 12,058 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Hiranimanthan Builders AND Developers has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 5 finished, 1 within the promised date and 4 needed more time (typically 46 months); 1 lapsed. 2 complaints on MahaRERA across 2 projects.
Read Google reviews of SKYVIEW CHS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SKYVIEW CHS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SKYVIEW CHS
What is the possession date of SKYVIEW CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SKYVIEW CHS in Nehru Nagar, Mumbai is 30 November 2025 — 71 months later than 30 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SKYVIEW CHS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SKYVIEW CHS's builder has filed on MahaRERA, the official one, is 30 November 2025, already 71 months later than the 30 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SKYVIEW CHS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SKYVIEW CHS's builder applied to MahaRERA to extend the completion date 4 times: to 29 December 2020, giving the reason "In View of the further approvals received for proposed FSI/BUA, we need this time for construction of this proposed FSI area."; to 1 June 2023, giving the reason "We had completed entire development work of the project up to 16 floors as per the approved plans and shortly starting to give ‘Fit Out Possessions’ to the allottees. However we have not yet utilised full potential FSI of the project & for such balance FSI we got the sanctions from the authorities just now & plans are also amended accordingly. Our structure is also designed to that capacity to absorb this FSI load. We also got consent from allottees. Hence we require additional time for completing our balance FSI construction."; to 30 November 2024, giving the reason "Construction completed in full. No Development work is pending. We had applied for Full and final Occupancy Certificate. However Approving Authority has delayed OC . Hence we need extra time for completing OC Procedure and submit Form 4. We already had received Part OC for 3 wings out of 5 wings. 3 Wings already occupied by Allottees."; to 30 November 2025, giving the reason "Our project is completed in full. However due to change is development policies and procedures final Occupancy Certificate Process was halted in the area. We will get Final Full Occupancy certificate from MHADA only after completion of Policy Updating process by State Government. We or any other builder in vicinity do no have any idea of time line about State Government Process. Hence we had left with no option than to seek further extension of Validity RERA Registration".
What is the RERA number of SKYVIEW CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SKYVIEW CHS in Nehru Nagar, Mumbai is P51800008227.
Is SKYVIEW CHS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SKYVIEW CHS is registered as P51800008227 and its status is "Completed".
What is the construction status of SKYVIEW CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), SKYVIEW CHS's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does SKYVIEW CHS have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SKYVIEW CHS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SKYVIEW CHS is registered on MahaRERA as P51800008227, its MahaRERA status is "Completed", its completion date has moved 71 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SKYVIEW CHS's possession date changes?
The latest dates are on SKYVIEW CHS's MahaRERA page (P51800008227). GharKundli's Kundli Watch sends a free WhatsApp update on SKYVIEW CHS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SKYVIEW CHS have?
According to GharKundli's check of MahaRERA records (updated October 2026), SKYVIEW CHS has 5 buildings filed: SKYVIEW CASTLE WING A with 18 floors and 64 units; SKYVIEW CASTLE WING B with 18 floors and 64 units; SKYVIEW CASTLE WING C with 18 floors and 64 units; SKYVIEW CASTLE WING D with 20 floors and 61 units; SKYVIEW CASTLE WING E with 20 floors and 41 units.
What are the flat sizes (carpet area) in SKYVIEW CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SKYVIEW CHS: 1 BHK: 294 to 470 sq ft carpet (260 homes); 2 BHK: 673 sq ft carpet (18 homes); 1 Room Kitchen: 389 to 459 sq ft carpet (5 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does SKYVIEW CHS have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 41 covered and 5 open car parking spaces for SKYVIEW CHS.
How big is the land of SKYVIEW CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), SKYVIEW CHS stands on 2,452 sq m of land (about 0.6 acres), with 12,058 sq m of sanctioned built-up area.
What is the track record of SKYVIEW CHS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Hiranimanthan Builders AND Developers has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 5 finished, 1 within the promised date and 4 needed more time (typically 46 months); 1 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SKYVIEW CHS?
Google Maps has reviews of SKYVIEW CHS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SKYVIEW CHS?
SKYVIEW CHS by HIRANIMANTHAN BUILDERS AND DEVELOPERS is in Nehru Nagar, Mumbai (pincode 400024), near Kurla East, Kurla West, Chembur, Maharashtra, and is registered on MahaRERA as P51800008227, per GharKundli's check of MahaRERA records.
How many homes are in SKYVIEW CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), SKYVIEW CHS has 283 homes in 5 towers registered on MahaRERA, and 92% of them are sold or booked.
When was SKYVIEW CHS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SKYVIEW CHS was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SKYVIEW CHS?
No court cases are listed for SKYVIEW CHS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SKYVIEW CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is HIRANIMANTHAN BUILDERS AND DEVELOPERS, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SKYVIEW CHS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400024
- SAPTARSHI MARK
- VEER SIDDHANAK CHS LTD
- AMBARISH CHS LTD
- ROHA VATIKA-ROHA KUMUD
- RAGHAV PARIJAT
- Ruparel Crest
- SAYBA TULIP
- DTG APEX
Other projects by HIRANIMANTHAN BUILDERS AND DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.