Aditya Rosewood Residency Building No. 2
by ADITYA AANANDI ASSOCIATES · Village:Chikloli, Thane 421501Also near Ambernath, Badlapur East, MharalRegistered on MahaRERA as “Rosewood Residency Building No. 2”
What’s in the report? →Possession date of Aditya Rosewood Residency Building No. 2 (MahaRERA PR1331012600015): 30 March 2031. It has 95 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1331012600015, and currently active. Its completion date is now March 2031, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PR1331012600015, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Aditya Rosewood Residency Building No. 2?
1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Aditya Rosewood Residency Building No. 2 has moved
30 November 2030
Completion date given when the project was registered
30 March 2031
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Aditya Rosewood Residency Building No. 2’s extension records on MahaRERA (PR1331012600015), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Aditya Rosewood Residency Building No. 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the March 2031 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1331012600015
- Status
- Registered and active
- Builder
- ADITYA AANANDI ASSOCIATES
- Location
- Village:Chikloli, Thane · 421501
- Project type
- Residential / Group Housing
- Registered on
- 6 Apr 2026
- Completion date at registration
- November 2030
- Latest completion date
- March 2031
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 95
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of Aditya Rosewood Residency Building No. 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| 02 (ROSEWOOD RESIDENCY) | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- 02 (ROSEWOOD RESIDENCY): covers 9 floors
Latest CC order on MahaRERA: dated 09/04/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aditya Rosewood Residency Building No. 2 every 1–2 months.
Aditya Rosewood Residency Building No. 2: buildings, flats and land, as filed on MahaRERA
- Buildings: 02 (ROSEWOOD RESIDENCY) (9 floors, 95 units)
- Car parking: 116 covered
- Land: 5,900 sq m (about 1.5 acres) · sanctioned built-up 4,896 sq m · recreational space 520 sq m
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Aditya Aanandi Associates (a group of 2 linked companies) has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 3 months late). No complaints on MahaRERA.
Read Google reviews of Aditya Rosewood Residency Building No. 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Aditya Rosewood Residency Building No. 2: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Aditya Rosewood Residency Building No. 2
What is the possession date of Aditya Rosewood Residency Building No. 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Aditya Rosewood Residency Building No. 2 in Village:Chikloli, Thane is 30 March 2031, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Aditya Rosewood Residency Building No. 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Aditya Rosewood Residency Building No. 2's builder has filed on MahaRERA, the official one, is 30 March 2031, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Aditya Rosewood Residency Building No. 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Aditya Rosewood Residency Building No. 2 in Village:Chikloli, Thane is PR1331012600015.
Is Aditya Rosewood Residency Building No. 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Aditya Rosewood Residency Building No. 2 is registered as PR1331012600015 and its status is "Registered and active".
What is the current construction status of Aditya Rosewood Residency Building No. 2? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Aditya Rosewood Residency Building No. 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on 02 (ROSEWOOD RESIDENCY) is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Aditya Rosewood Residency Building No. 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Aditya Rosewood Residency Building No. 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Aditya Rosewood Residency Building No. 2 is registered on MahaRERA as PR1331012600015, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Aditya Rosewood Residency Building No. 2?
Aditya Rosewood Residency Building No. 2 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Aditya Rosewood Residency Building No. 2?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Aditya Rosewood Residency Building No. 2: gharkundli.com/tools/property-cost-calculator
Has Aditya Rosewood Residency Building No. 2 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Aditya Rosewood Residency Building No. 2 is still under construction, with 30 March 2031 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Aditya Rosewood Residency Building No. 2 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Aditya Rosewood Residency Building No. 2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Aditya Rosewood Residency Building No. 2's possession date changes?
The latest dates are on Aditya Rosewood Residency Building No. 2's MahaRERA page (PR1331012600015). GharKundli's Kundli Watch sends a free WhatsApp update on Aditya Rosewood Residency Building No. 2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Aditya Rosewood Residency Building No. 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Aditya Rosewood Residency Building No. 2 has one building filed: 02 (ROSEWOOD RESIDENCY) with 9 floors and 95 units.
How much parking does Aditya Rosewood Residency Building No. 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 116 covered car parking spaces for Aditya Rosewood Residency Building No. 2.
How big is the land of Aditya Rosewood Residency Building No. 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Aditya Rosewood Residency Building No. 2 stands on 5,900 sq m of land (about 1.5 acres), with 4,896 sq m of sanctioned built-up area and 520 sq m of recreational open space.
What is the track record of Aditya Rosewood Residency Building No. 2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Aditya Aanandi Associates (a group of 2 linked companies) has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 3 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Aditya Rosewood Residency Building No. 2?
Google Maps has reviews of Aditya Rosewood Residency Building No. 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Aditya Rosewood Residency Building No. 2?
Aditya Rosewood Residency Building No. 2 by ADITYA AANANDI ASSOCIATES is in Village:Chikloli, Thane, pincode 421501 (near Ambernath, Badlapur East, Mharal), Maharashtra, and is registered on MahaRERA as PR1331012600015, per GharKundli's check of MahaRERA records. GharKundli lists all 486 MahaRERA projects in Ambernath (421501).
How many flats are in Aditya Rosewood Residency Building No. 2, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Aditya Rosewood Residency Building No. 2 has 95 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Aditya Rosewood Residency Building No. 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Aditya Rosewood Residency Building No. 2 was registered on MahaRERA on 6 April 2026. GharKundli did not find a title report on the land on file there.
Does Aditya Rosewood Residency Building No. 2 have any legal issues or court cases?
1 court case is listed for Aditya Rosewood Residency Building No. 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Aditya Rosewood Residency Building No. 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ADITYA AANANDI ASSOCIATES.
Check it yourself on MahaRERA
- How to check the possession date of Aditya Rosewood Residency Building No. 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2031 in Thane →
Other projects in Ambarnath
- Nature Vista Building - 1
- Midtown B and C Wing
- Mery Villa CHSL
- Sai Universe
- Dattatray Residency
- Mahadev Heights
- Chadha Residency
- New Neelgagan CHS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.