SAI MORESHWAR
by SPACE LAND DEVELOPERS · Neral East Talika- Karjat Dist Raigad, Raigarh
Possession date of SAI MORESHWAR: 31 December 2027, moved from 31 December 2019 (96 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000007338, and currently active. 6 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SAI MORESHWAR?
How the possession date of SAI MORESHWAR has moved
31 December 2019
Completion date given when the project was registered
31 December 2020
Extended at the builder's request (MahaRERA application EXT52000005743)
Reason the builder gave MahaRERA:
“WITH DUE RESPONSIBILTY WE INTEND TO COMPLETE THE WORK ON TIME.BUT, DUE TO HEAVY RAIN FALL IN THE MONTH OF JUNE,JULY, AUGUST, SEPTEMBER, OCTOBER, NOVEMBER IN THE YEAR 2019 AND NON AVAILABILITY OF CONSTRUCTION MATERIAL, SPECIALLY SAND AND AGG…” Read the full reason
“WITH DUE RESPONSIBILTY WE INTEND TO COMPLETE THE WORK ON TIME.BUT, DUE TO HEAVY RAIN FALL IN THE MONTH OF JUNE,JULY, AUGUST, SEPTEMBER, OCTOBER, NOVEMBER IN THE YEAR 2019 AND NON AVAILABILITY OF CONSTRUCTION MATERIAL, SPECIALLY SAND AND AGGREGATES THE PROJECT IS DELAYED. WE REGRET FOR THE SAME. WE REQUEST YOU TO PROVIDE EXTENSION TO OUR PROJECT. WE WILL COMPLETE THE PROJECT BEFORE EXTENDED COMPLETION DATE 30 DEC 2020.”30 June 2022
Extended at the builder's request (MahaRERA application EXT52000010240)
Reason the builder gave MahaRERA:
“Covid pendamic has effected economy of the whole world including our Country. Maharashtra state is worsly effected due to Covid Pandemic. Which has resulted financial and resource crisis in the market. We hereby submit that we could not com…” Read the full reason
“Covid pendamic has effected economy of the whole world including our Country. Maharashtra state is worsly effected due to Covid Pandemic. Which has resulted financial and resource crisis in the market. We hereby submit that we could not complete the project in the given completion time due: 1. Non availability of labours 2. Non availability of material 3. Force meajure - Covid Pandamic 4. Force meajure - Cyclone Nisarg and Tauktae. Which are not under our control. Kindly consider this declration and provide us extension.”31 December 2025
Extended at the builder's request (MahaRERA application EXT52000013144)
Reason the builder gave MahaRERA:
“Respected Sir, We highly regret to submit this declaration. We have tried our best to complete our ongoing project SAI MORESHWAR COMPLEX bearing MahaRERA registration number P52000007338 located atOld S.no.66/2 and New S.no.15/2, Village- V…” Read the full reason
“Respected Sir, We highly regret to submit this declaration. We have tried our best to complete our ongoing project SAI MORESHWAR COMPLEX bearing MahaRERA registration number P52000007338 located atOld S.no.66/2 and New S.no.15/2, Village- Vanjarpada, Taluka- Karjat, Dist- Raigad -410101, within given completion date. After covid pandemic has affected economy of the whole world including our Country. We hereby submit that we could not complete the project in the given completion time due to: 1. Non availability of construction material. 2. Non availability of labours. We continued to work on…”31 December 2027
Extended at the builder's request (MahaRERA application EA08122518575)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31/12/2027 to complete the project and fulfil all regulatory requirements.”
Source: SAI MORESHWAR’s extension records on MahaRERA (P52000007338), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAI MORESHWAR
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 6 complaints, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000007338
- Status
- Registered and active
- Builder
- SPACE LAND DEVELOPERS
- Location
- Neral East Talika- Karjat Dist Raigad, Raigarh · 410101
- Project type
- Residential / Group Housing
- Registered on
- 17 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2027
- Delay so far
- 96 months
- Homes
- 296
- Sold or booked
- 83%
- Towers
- 16
- Complaints on MahaRERA
- 6
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of SAI MORESHWAR, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO B2 | 100% | 90% | 90% | 90% |
| BUILDING NO B1 | 100% | 90% | 90% | 90% |
| BUILDING NO B3 | 100% | 90% | 90% | 90% |
| BUILDING NO B4 | 0% | 100% | 90% | 90% |
| BUILDING NO B5 | 100% | 90% | 90% | 90% |
| BUILDING NO B6 | 100% | 90% | 90% | 90% |
| BUILDING NO B7 | 100% | 90% | 90% | 90% |
| BUILDING NO B8 | 100% | 90% | 90% | 90% |
| BUILDING NO B9 | 100% | 90% | 90% | 90% |
| BUILDING B10 A WING | 100% | 97% | 97% | 97% |
| BUILDING NO B10 B WING | 100% | 97% | 97% | 97% |
| BUILDING NO B10 C WING | 100% | 97% | 97% | 97% |
| BUILDING NO B10 D WING | 100% | 97% | 97% | 97% |
| BUILDING NO B10 E WING | 100% | 97% | 97% | 97% |
| BUILDING NO B10 F WING | 100% | 97% | 97% | 97% |
| BUILDING NO B10 G WING | 100% | 97% | 97% | 97% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO B2: covers 4 floors
- BUILDING NO B1: covers 4 floors
- BUILDING NO B3: covers 4 floors
- BUILDING NO B4: covers 4 floors
- BUILDING NO B5: covers 4 floors
- BUILDING NO B6: covers 4 floors
- BUILDING NO B7: covers 4 floors
- BUILDING NO B8: covers 4 floors
- BUILDING NO B9: covers 4 floors
- BUILDING B10 A WING: covers 4 floors
- BUILDING NO B10 B WING: covers 4 floors
- BUILDING NO B10 C WING: covers 4 floors
- BUILDING NO B10 D WING: covers 4 floors
- BUILDING NO B10 E WING: covers 4 floors
- BUILDING NO B10 F WING: covers 4 floors
- BUILDING NO B10 G WING: covers 4 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI MORESHWAR every month.
SAI MORESHWAR: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO B2 (6 floors, 16 units) · BUILDING NO B1 (6 floors, 16 units) · BUILDING NO B3 (6 floors, 20 units) · BUILDING NO B4 (6 floors, 20 units) · BUILDING NO B5 (6 floors, 16 units) · BUILDING NO B6 (6 floors, 20 units) · BUILDING NO B7 (6 floors, 16 units) · BUILDING NO B8 (6 floors, 20 units) · and 8 more
- Car parking: 16 covered
- Land: 13,200 sq m (about 3.3 acres) · sanctioned built-up 8,579 sq m · recreational space 1,320 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SAI MORESHWAR →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAI MORESHWAR: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAI MORESHWAR
What is the possession date of SAI MORESHWAR?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAI MORESHWAR in Neral East Talika- Karjat Dist Raigad, Raigarh is 31 December 2027 — 96 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SAI MORESHWAR?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI MORESHWAR's builder has filed on MahaRERA, the official one, is 31 December 2027, already 96 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAI MORESHWAR extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI MORESHWAR's builder applied to MahaRERA to extend the completion date 4 times: to 31 December 2020, giving the reason "WITH DUE RESPONSIBILTY WE INTEND TO COMPLETE THE WORK ON TIME.BUT, DUE TO HEAVY RAIN FALL IN THE MONTH OF JUNE,JULY, AUGUST, SEPTEMBER, OCTOBER, NOVEMBER IN THE YEAR 2019 AND NON AVAILABILITY OF CONSTRUCTION MATERIAL, SPECIALLY SAND AND AGGREGATES THE PROJECT IS DELAYED. WE REGRET FOR THE SAME. WE REQUEST YOU TO PROVIDE EXTENSION TO OUR PROJECT. WE WILL COMPLETE THE PROJECT BEFORE EXTENDED COMPLETION DATE 30 DEC 2020."; to 30 June 2022, giving the reason "Covid pendamic has effected economy of the whole world including our Country. Maharashtra state is worsly effected due to Covid Pandemic. Which has resulted financial and resource crisis in the market. We hereby submit that we could not complete the project in the given completion time due: 1. Non availability of labours 2. Non availability of material 3. Force meajure - Covid Pandamic 4. Force meajure - Cyclone Nisarg and Tauktae. Which are not under our control. Kindly consider this declration and provide us extension."; to 31 December 2025, giving the reason "Respected Sir, We highly regret to submit this declaration. We have tried our best to complete our ongoing project SAI MORESHWAR COMPLEX bearing MahaRERA registration number P52000007338 located atOld S.no.66/2 and New S.no.15/2, Village- Vanjarpada, Taluka- Karjat, Dist- Raigad -410101, within given completion date. After covid pandemic has affected economy of the whole world including our Country. We hereby submit that we could not complete the project in the given completion time due to: 1. Non availability of construction material. 2. Non availability of labours. We continued to work on…"; to 31 December 2027, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31/12/2027 to complete the project and fulfil all regulatory requirements.".
What is the RERA number of SAI MORESHWAR?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAI MORESHWAR in Neral East Talika- Karjat Dist Raigad, Raigarh is P52000007338.
Is SAI MORESHWAR registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI MORESHWAR is registered as P52000007338 and its status is "Registered and active".
What is the construction status of SAI MORESHWAR?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI MORESHWAR's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 90% to 100% across 16 towers. GharKundli's full report compares construction progress with the deadline.
Does SAI MORESHWAR have complaints on MahaRERA?
6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SAI MORESHWAR safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI MORESHWAR is registered on MahaRERA as P52000007338, its completion date has moved 96 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAI MORESHWAR's possession date changes?
The latest dates are on SAI MORESHWAR's MahaRERA page (P52000007338). GharKundli's Kundli Watch sends a free WhatsApp update on SAI MORESHWAR every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAI MORESHWAR have?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI MORESHWAR has 16 buildings filed: BUILDING NO B2 with 6 floors and 16 units; BUILDING NO B1 with 6 floors and 16 units; BUILDING NO B3 with 6 floors and 20 units; BUILDING NO B4 with 6 floors and 20 units; BUILDING NO B5 with 6 floors and 16 units; BUILDING NO B6 with 6 floors and 20 units; and 10 more.
How much parking does SAI MORESHWAR have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 16 covered car parking spaces for SAI MORESHWAR.
How big is the land of SAI MORESHWAR?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI MORESHWAR stands on 13,200 sq m of land (about 3.3 acres), with 8,579 sq m of sanctioned built-up area and 1,320 sq m of recreational open space.
Where can I read reviews of SAI MORESHWAR?
Google Maps has reviews of SAI MORESHWAR written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAI MORESHWAR?
SAI MORESHWAR by SPACE LAND DEVELOPERS is in Neral East Talika- Karjat Dist Raigad, Raigarh (pincode 410101), Maharashtra, and is registered on MahaRERA as P52000007338, per GharKundli's check of MahaRERA records.
How many homes are in SAI MORESHWAR?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI MORESHWAR has 296 homes in 16 towers registered on MahaRERA, and 83% of them are sold or booked.
When was SAI MORESHWAR registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI MORESHWAR was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SAI MORESHWAR?
No court cases are listed for SAI MORESHWAR on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SAI MORESHWAR?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SPACE LAND DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of SAI MORESHWAR
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Raigad →
Other projects in pincode 410101
- A Z LANDMARK
- VANSH HEIGHTS
- SWAMI AASHRAY
- MIRA RESIDENCY
- SIGNATURE PHASE 1
- ARYA RESIDENCY P1
- ARENA ONE
- MECCA AVENUE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.