Olympeo Riverside - Phase 3

by Olympeo Riverside Projects LLP · Neral, Raigarh

Possession date of Olympeo Riverside - Phase 3: 30 April 2029, moved from 30 June 2022 (78 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000012184, and currently active. Its completion date has moved from June 2022 to April 2029: 78 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 5 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Olympeo Riverside - Phase 3?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Olympeo Riverside - Phase 3 has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT52000012207)

    Reason the builder gave MahaRERA: “The progress of project got hampered due to Pandemic and it has severely impacted the sales & collections. Because of prolonged liquidity constraints our construction timeline got impacted.”
  3. 29 June 2024

    Extended at the builder's request (MahaRERA application EXT52000016766)

    Reason the builder gave MahaRERA:
    “RCC and blockwork is complete in building C3 and finishing work is in progress. For building C4, we have completed 90% RCC and 50% blockwork. Project has been delayed due to impact of COVID19 on cashflows and interest obligation of lenders…” Read the full reason“RCC and blockwork is complete in building C3 and finishing work is in progress. For building C4, we have completed 90% RCC and 50% blockwork. Project has been delayed due to impact of COVID19 on cashflows and interest obligation of lenders along foreclosing construction loan. Also customers were unable to clear demand amount as per milestones.”
  4. 31 December 2028

    Extended at the builder's request (MahaRERA application EXT52000024812)

    Reason the builder gave MahaRERA: “Due to COVID, we are unable to complete our project. Therefore, we require a project extension until 31/12/2028.”
  5. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Olympeo Riverside - Phase 3’s extension records on MahaRERA (P52000012184), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Olympeo Riverside - Phase 3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 5 complaints, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52000012184
Status
Registered and active
Builder
Olympeo Riverside Projects LLP
Location
Neral, Raigarh · 410101
Project type
Residential / Group Housing
Registered on
1 Sep 2017
Completion date at registration
June 2022
Latest completion date
April 2029
Delay so far
78 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
360
Sold or booked
54%
Towers
7
Complaints on MahaRERA
5
Court cases listed
0
Appeals at the tribunal
2
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Olympeo Riverside - Phase 3, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
C3100%100%95%20%
C4100%86%25%0%
C541%0%0%0%
C60%0%0%0%
C80%0%0%0%
NA0%0%0%0%
C70%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • C3: covers 8 floors
  • C4: covers 8 floors
  • C5: covers 8 floors
  • C6: covers 8 floors
  • C8: covers 8 floors
  • NA: covers 0 floors
  • C7: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Olympeo Riverside - Phase 3 every month.

Olympeo Riverside - Phase 3: buildings, flats and land, as filed on MahaRERA

  • Buildings: C3 (8 floors, 60 units) · C4 (8 floors, 60 units) · C5 (8 floors, 60 units) · C6 (8 floors, 60 units) · C8 (8 floors, 60 units) · C7 (8 floors, 60 units)
  • Land: 1,265 sq m (about 0.3 acres) · sanctioned built-up 16,053 sq m · recreational space 9,913 sq m
  • Boundaries filed include: Ulhas River and Shelu Village

The builder’s record and reviews

Olympeo Riverside Projects (a group of 5 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 3 finished, all within the promised date; 4 still being built, 2 past the promised date (typically 33 months late). 11 complaints on MahaRERA across 2 projects.

Read Google reviews of Olympeo Riverside - Phase 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Olympeo Riverside - Phase 3: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Olympeo Riverside - Phase 3

What is the possession date of Olympeo Riverside - Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Olympeo Riverside - Phase 3 in Neral, Raigarh is 30 April 2029 — 78 months later than 30 June 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Olympeo Riverside - Phase 3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Olympeo Riverside - Phase 3's builder has filed on MahaRERA, the official one, is 30 April 2029, already 78 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Olympeo Riverside - Phase 3 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Olympeo Riverside - Phase 3's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2023, giving the reason "The progress of project got hampered due to Pandemic and it has severely impacted the sales & collections. Because of prolonged liquidity constraints our construction timeline got impacted."; to 29 June 2024, giving the reason "RCC and blockwork is complete in building C3 and finishing work is in progress. For building C4, we have completed 90% RCC and 50% blockwork. Project has been delayed due to impact of COVID19 on cashflows and interest obligation of lenders along foreclosing construction loan. Also customers were unable to clear demand amount as per milestones."; to 31 December 2028, giving the reason "Due to COVID, we are unable to complete our project. Therefore, we require a project extension until 31/12/2028.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Olympeo Riverside - Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Olympeo Riverside - Phase 3 in Neral, Raigarh is P52000012184.

Is Olympeo Riverside - Phase 3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Olympeo Riverside - Phase 3 is registered as P52000012184 and its status is "Registered and active".

What is the construction status of Olympeo Riverside - Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), Olympeo Riverside - Phase 3's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 7 towers. GharKundli's full report compares construction progress with the deadline.

Does Olympeo Riverside - Phase 3 have complaints on MahaRERA?

5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Olympeo Riverside - Phase 3 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Olympeo Riverside - Phase 3 is registered on MahaRERA as P52000012184, its completion date has moved 78 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Olympeo Riverside - Phase 3 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Olympeo Riverside - Phase 1 (P52000002351, possession 30 Jun 2018). Check that your agreement names the registration of your own wing.

How can I get updates if Olympeo Riverside - Phase 3's possession date changes?

The latest dates are on Olympeo Riverside - Phase 3's MahaRERA page (P52000012184). GharKundli's Kundli Watch sends a free WhatsApp update on Olympeo Riverside - Phase 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Olympeo Riverside - Phase 3 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Olympeo Riverside - Phase 3 has 6 buildings filed: C3 with 8 floors and 60 units; C4 with 8 floors and 60 units; C5 with 8 floors and 60 units; C6 with 8 floors and 60 units; C8 with 8 floors and 60 units; C7 with 8 floors and 60 units.

How big is the land of Olympeo Riverside - Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), Olympeo Riverside - Phase 3 stands on 1,265 sq m of land (about 0.3 acres), with 16,053 sq m of sanctioned built-up area and 9,913 sq m of recreational open space.

What is the track record of Olympeo Riverside - Phase 3's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Olympeo Riverside Projects (a group of 5 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 3 finished, all within the promised date; 4 still being built, 2 past the promised date (typically 33 months late). 11 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Olympeo Riverside - Phase 3?

Google Maps has reviews of Olympeo Riverside - Phase 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Olympeo Riverside - Phase 3?

Olympeo Riverside - Phase 3 by Olympeo Riverside Projects LLP is in Neral, Raigarh (pincode 410101), Maharashtra, and is registered on MahaRERA as P52000012184, per GharKundli's check of MahaRERA records. Its boundaries filed there include Ulhas River and Shelu Village.

How many homes are in Olympeo Riverside - Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), Olympeo Riverside - Phase 3 has 360 homes in 7 towers registered on MahaRERA, and 54% of them are sold or booked.

When was Olympeo Riverside - Phase 3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Olympeo Riverside - Phase 3 was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Olympeo Riverside - Phase 3?

No court cases are listed for Olympeo Riverside - Phase 3 on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Olympeo Riverside - Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Olympeo Riverside Projects LLP, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2029 in Raigad →

Other projects in pincode 410101

All 362 projects in Neral (410101) →

Other projects by Olympeo Riverside Projects LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.