Possession date of TULSI NISARG: 30 October 2027, moved from 30 June 2021 (76 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000005986, and currently active. 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about TULSI NISARG?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of TULSI NISARG has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT52000009708)

    Reason the builder gave MahaRERA: “Due to Covid-19 , non availability of workers and business stress.”
  3. 30 October 2027

    Extended at the builder's request

Source: TULSI NISARG’s extension records on MahaRERA (P52000005986), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on TULSI NISARG

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000005986
Status
Registered and active
Builder
PRISTINE GROUP
Location
neral, Raigarh · 410101
Project type
Others
Registered on
14 Aug 2017
Completion date at registration
June 2021
Latest completion date
October 2027
Delay so far
76 months
Homes
1
Sold or booked
0%
Towers
8
Complaints on MahaRERA
3
Court cases listed
0
Title report on file
Not found

Construction progress of TULSI NISARG, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING 1 WING A100%37%0%0%
BUILDING 1 WING B100%25%0%0%
BUILDIND 1 WING C100%0%0%0%
BUILDING 2 WING D70%0%0%0%
BUILDING NO 2 WING E50%0%0%0%
BUILDING NO 2 WING F0%0%0%0%
BUILDING NO 3 WING G0%0%0%0%
BUILDING NO 3 WING H0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on TULSI NISARG every month.

TULSI NISARG: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING 1 WING A (9 floors) · BUILDING 1 WING B (9 floors) · BUILDIND 1 WING C (9 floors) · BUILDING 2 WING D (9 floors) · BUILDING NO 2 WING E (9 floors) · BUILDING NO 2 WING F (9 floors) · BUILDING NO 3 WING G (6 floors) · BUILDING NO 3 WING H (6 floors)
  • Land: 14,320 sq m (about 3.5 acres) · sanctioned built-up 12,392 sq m · recreational space 1,153 sq m
  • Boundaries filed include: STATE HIGHWAY

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of TULSI NISARG →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

TULSI NISARG: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about TULSI NISARG

What is the possession date of TULSI NISARG?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for TULSI NISARG in neral, Raigarh is 30 October 2027 — 76 months later than 30 June 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for TULSI NISARG?

Builders and listing sites often quote an earlier "target" date for handover. The completion date TULSI NISARG's builder has filed on MahaRERA, the official one, is 30 October 2027, already 76 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of TULSI NISARG extended?

According to GharKundli's check of MahaRERA records (updated November 2026), TULSI NISARG's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2026, giving the reason "Due to Covid-19 , non availability of workers and business stress."; to 30 October 2027.

What is the RERA number of TULSI NISARG?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of TULSI NISARG in neral, Raigarh is P52000005986.

Is TULSI NISARG registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), TULSI NISARG is registered as P52000005986 and its status is "Registered and active".

What is the construction status of TULSI NISARG?

According to GharKundli's check of MahaRERA records (updated November 2026), TULSI NISARG's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 37% across 8 towers. GharKundli's full report compares construction progress with the deadline.

Does TULSI NISARG have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is TULSI NISARG safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), TULSI NISARG is registered on MahaRERA as P52000005986, its completion date has moved 76 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if TULSI NISARG's possession date changes?

The latest dates are on TULSI NISARG's MahaRERA page (P52000005986). GharKundli's Kundli Watch sends a free WhatsApp update on TULSI NISARG every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does TULSI NISARG have?

According to GharKundli's check of MahaRERA records (updated November 2026), TULSI NISARG has 8 buildings filed: BUILDING 1 WING A with 9 floors; BUILDING 1 WING B with 9 floors; BUILDIND 1 WING C with 9 floors; BUILDING 2 WING D with 9 floors; BUILDING NO 2 WING E with 9 floors; BUILDING NO 2 WING F with 9 floors; and 2 more.

How big is the land of TULSI NISARG?

According to GharKundli's check of MahaRERA records (updated November 2026), TULSI NISARG stands on 14,320 sq m of land (about 3.5 acres), with 12,392 sq m of sanctioned built-up area and 1,153 sq m of recreational open space.

Where can I read reviews of TULSI NISARG?

Google Maps has reviews of TULSI NISARG written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is TULSI NISARG?

TULSI NISARG by PRISTINE GROUP is in neral, Raigarh (pincode 410101), Maharashtra, and is registered on MahaRERA as P52000005986, per GharKundli's check of MahaRERA records. Its boundaries filed there include STATE HIGHWAY.

How many homes are in TULSI NISARG?

According to GharKundli's check of MahaRERA records (updated November 2026), TULSI NISARG has 1 home in 8 towers registered on MahaRERA, and 0% of them are sold or booked.

When was TULSI NISARG registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), TULSI NISARG was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on TULSI NISARG?

No court cases are listed for TULSI NISARG on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of TULSI NISARG?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PRISTINE GROUP.

All projects with possession due in 2027 in Raigad →

Other projects in pincode 410101

All 362 projects in Neral (410101) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.