SWAGAT VILLAGE

by NAYAN INFRASTRUCTURE · Karjat, Raigarh

Possession date of SWAGAT VILLAGE: 29 October 2027, moved from 30 June 2023 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000005559, and currently active. Its completion date has moved from June 2023 to October 2027: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SWAGAT VILLAGE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SWAGAT VILLAGE has moved

  1. 30 June 2023

    Completion date given when the project was registered

  2. 29 June 2024

    Extended at the builder's request (MahaRERA application EXT52000016851)

    Reason the builder gave MahaRERA:
    “1. Continuous delay in disbursement of Housing loan of customers from Banks/NBFC, because of this there was a shortage of working capital funds and 2. There was heavy rain during monsoon which results into flood and water logged many times…” Read the full reason“1. Continuous delay in disbursement of Housing loan of customers from Banks/NBFC, because of this there was a shortage of working capital funds and 2. There was heavy rain during monsoon which results into flood and water logged many times surrounding the project due to which the construction work(External Plasters, Paints etc.) was disturbed several times through out the period of 5 to 6 months.”
  3. 29 June 2027

    Extended at the builder's request (MahaRERA application EXT52000023027)

    Reason the builder gave MahaRERA: “I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P52000005559. We have received order from RERA for the same.”
  4. 29 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SWAGAT VILLAGE’s extension records on MahaRERA (P52000005559), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SWAGAT VILLAGE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000005559
Status
Registered and active
Builder
NAYAN INFRASTRUCTURE
Location
Karjat, Raigarh · 410101
Project type
Residential / Group Housing
Registered on
11 Aug 2017
Completion date at registration
June 2023
Latest completion date
October 2027
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
494
Towers
9
Complaints on MahaRERA
1
Court cases listed
0
MahaRERA regulatory orders
1
Title report on file
Not found

Construction progress of SWAGAT VILLAGE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A0%0%0%0%
WING B100%100%100%100%
WING C100%100%100%100%
WING D100%100%100%100%
WING E100%100%100%80%
WING F100%80%60%0%
WING G100%100%100%100%
WING H100%100%100%60%
WING I50%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SWAGAT VILLAGE every month.

SWAGAT VILLAGE: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING A (9 floors) · WING B (9 floors) · WING C (9 floors) · WING D (9 floors) · WING E (9 floors) · WING F (9 floors) · WING G (9 floors) · WING H (9 floors) · and 1 more
  • Land: 9,184 sq m (about 2.3 acres) · sanctioned built-up 16,280 sq m · recreational space 1,177 sq m

The builder’s record and reviews

Nayan Infrastructure (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 24 months late). 2 complaints on MahaRERA across 2 projects.

Read Google reviews of SWAGAT VILLAGE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SWAGAT VILLAGE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SWAGAT VILLAGE

What is the possession date of SWAGAT VILLAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SWAGAT VILLAGE in Karjat, Raigarh is 29 October 2027 — 48 months later than 30 June 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SWAGAT VILLAGE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SWAGAT VILLAGE's builder has filed on MahaRERA, the official one, is 29 October 2027, already 48 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SWAGAT VILLAGE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SWAGAT VILLAGE's builder applied to MahaRERA to extend the completion date 2 times: to 29 June 2024, giving the reason "1. Continuous delay in disbursement of Housing loan of customers from Banks/NBFC, because of this there was a shortage of working capital funds and 2. There was heavy rain during monsoon which results into flood and water logged many times surrounding the project due to which the construction work(External Plasters, Paints etc.) was disturbed several times through out the period of 5 to 6 months."; to 29 June 2027, giving the reason "I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P52000005559. We have received order from RERA for the same.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SWAGAT VILLAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SWAGAT VILLAGE in Karjat, Raigarh is P52000005559.

Is SWAGAT VILLAGE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SWAGAT VILLAGE is registered as P52000005559 and its status is "Registered and active".

What is the construction status of SWAGAT VILLAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), SWAGAT VILLAGE's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 9 towers. GharKundli's full report compares construction progress with the deadline.

Does SWAGAT VILLAGE have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SWAGAT VILLAGE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SWAGAT VILLAGE is registered on MahaRERA as P52000005559, its completion date has moved 48 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SWAGAT VILLAGE's possession date changes?

The latest dates are on SWAGAT VILLAGE's MahaRERA page (P52000005559). GharKundli's Kundli Watch sends a free WhatsApp update on SWAGAT VILLAGE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SWAGAT VILLAGE have?

According to GharKundli's check of MahaRERA records (updated October 2026), SWAGAT VILLAGE has 9 buildings filed: WING A with 9 floors; WING B with 9 floors; WING C with 9 floors; WING D with 9 floors; WING E with 9 floors; WING F with 9 floors; and 3 more.

How big is the land of SWAGAT VILLAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), SWAGAT VILLAGE stands on 9,184 sq m of land (about 2.3 acres), with 16,280 sq m of sanctioned built-up area and 1,177 sq m of recreational open space.

What is the track record of SWAGAT VILLAGE's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Nayan Infrastructure (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 24 months late). 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SWAGAT VILLAGE?

Google Maps has reviews of SWAGAT VILLAGE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SWAGAT VILLAGE?

SWAGAT VILLAGE by NAYAN INFRASTRUCTURE is in Karjat, Raigarh (pincode 410101), Maharashtra, and is registered on MahaRERA as P52000005559, per GharKundli's check of MahaRERA records.

How many homes are in SWAGAT VILLAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), SWAGAT VILLAGE has 494 homes in 9 towers registered on MahaRERA.

When was SWAGAT VILLAGE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SWAGAT VILLAGE was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SWAGAT VILLAGE?

No court cases are listed for SWAGAT VILLAGE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SWAGAT VILLAGE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NAYAN INFRASTRUCTURE.

All projects with possession due in 2027 in Raigad →

Other projects in Karjat

All 362 projects in Neral (410101) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.