Skip to content
GharKundli

CASA UNICO PHASE - 1

by Landmark Real Estate Developers Limited · Karjat, Raigarh

Possession date of CASA UNICO PHASE - 1: 31 December 2026, moved from 30 December 2021 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000007113, and currently active. 12 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about CASA UNICO PHASE - 1?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of CASA UNICO PHASE - 1 has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 30 December 2022

    Extended at the builder's request (MahaRERA application EXT52000011217)

    Reason the builder gave MahaRERA:
    “1.) Stop work notice issued by the (Revenue and Forest Department), District Collector and District Magistrate, Raigad - Alibuag, dated 02.08.2018, due to which the actual work could not be carried on as per the sanctioned plan resulting in…” Read the full reason“1.) Stop work notice issued by the (Revenue and Forest Department), District Collector and District Magistrate, Raigad - Alibuag, dated 02.08.2018, due to which the actual work could not be carried on as per the sanctioned plan resulting in delay for a period of (5) Five months. 2. )Also, post the said stop work notice was lifted on 12/12/2018, the migratory labourers were not available at the site of the Builder / Promoter/ Developer for a quick kick start resulting in further delay of another (4) Four months; 3.) Due to the pre-pandemic situation Covid Phase - I and strict Lockdown situat…”
  3. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT52000013428)

    Reason the builder gave MahaRERA:
    “vi. Various reasons for the project to be stalled and delay in completion of the development works: a. Stop work notice issued by the (Revenue and Forest Department), District Collector and District Magistrate, Raigad - Alibuag, dated 02.08…” Read the full reason“vi. Various reasons for the project to be stalled and delay in completion of the development works: a. Stop work notice issued by the (Revenue and Forest Department), District Collector and District Magistrate, Raigad - Alibuag, dated 02.08.2018, due to which the actual work could not be carried on as per the sanctioned plan resulting in delay for a period of (5) Five months. Also, post the said stop work notice was lifted on 12/12/2018, the migratory labourers were not available at the site of the Builder / Promoter/ Developer for a quick kick start resulting in further delay of another (4…”
  4. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT52000018590)

    Reason the builder gave MahaRERA:
    “Various reasons for the project to be stalled and delay in completion of the development works: a. Stop work notice issued by the (Revenue and Forest Department), District Collector and District Magistrate, Raigad - Alibuag, dated 02.08.201…” Read the full reason“Various reasons for the project to be stalled and delay in completion of the development works: a. Stop work notice issued by the (Revenue and Forest Department), District Collector and District Magistrate, Raigad - Alibuag, dated 02.08.2018, due to which the actual work could not be carried on as per the sanctioned plan resulting in delay for a period of (5) Five months. Also, post the said stop work notice was lifted on 12/12/2018, the migratory labourers were not available at the site of the Builder / Promoter/ Developer for a quick kick start resulting in further delay of another (4) Fo…”
  5. 31 December 2026

    Extended at the builder's request (MahaRERA application EA22122518917)

    Reason the builder gave MahaRERA:
    “The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essentia…” Read the full reason“The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essential construction materials, including but not limited to cement, steel, copper, electrical components, plumbing materials, and paints. This escalation in material costs has resulted in severe financial strain, disrupting the supply chain and leading to delays in procurement and delivery of these materials to the project site. In particular, the delivery tim…”

Source: CASA UNICO PHASE - 1’s extension records on MahaRERA (P52000007113), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on CASA UNICO PHASE - 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 12 complaints and 3 court cases, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000007113
Status
Registered and active
Builder
Landmark Real Estate Developers Limited
Location
Karjat, Raigarh · 410201
Project type
Residential / Group Housing
Registered on
17 Aug 2017
Completion date at registration
December 2021
Latest completion date
December 2026
Delay so far
60 months
Homes
216
Sold or booked
94%
Towers
10
Complaints on MahaRERA
12
Court cases listed
3
Title report on file
Not found

Construction progress of CASA UNICO PHASE - 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ADONIA-1100%100%100%10%
ADONIA-2100%100%100%20%
ADONIA-3100%100%95%0%
ADONIA-4100%100%90%0%
GRANDE-1100%100%35%0%
GRANDE-2100%100%50%0%
GRANDE-3100%100%40%0%
GRANDE-4100%100%100%75%
STELLA-1100%100%100%90%
STELLA-30%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • ADONIA-1: covers 6 floors
  • ADONIA-2: covers 6 floors
  • ADONIA-3: covers 6 floors
  • ADONIA-4: covers 6 floors
  • GRANDE-1: covers 4 floors
  • GRANDE-2: covers 4 floors
  • GRANDE-3: covers 4 floors
  • GRANDE-4: covers 4 floors
  • STELLA-1: covers 4 floors
  • STELLA-3: covers 4 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on CASA UNICO PHASE - 1 every month.

CASA UNICO PHASE - 1: buildings, flats and land, as filed on MahaRERA

  • Buildings: ADONIA-1 (6 floors, 32 units) · ADONIA-2 (6 floors, 32 units) · ADONIA-3 (6 floors, 32 units) · ADONIA-4 (6 floors, 32 units) · GRANDE-1 (5 floors, 6 units) · GRANDE-2 (5 floors, 6 units) · GRANDE-3 (5 floors, 6 units) · GRANDE-4 (5 floors, 6 units) · and 2 more
  • Car parking: 116 covered
  • Land: 33,529 sq m (about 8.3 acres) · sanctioned built-up 11,870 sq m · recreational space 7,435 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of CASA UNICO PHASE - 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

CASA UNICO PHASE - 1: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about CASA UNICO PHASE - 1

What is the possession date of CASA UNICO PHASE - 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for CASA UNICO PHASE - 1 in Karjat, Raigarh is 31 December 2026 — 60 months later than 30 December 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for CASA UNICO PHASE - 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date CASA UNICO PHASE - 1's builder has filed on MahaRERA, the official one, is 31 December 2026, already 60 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of CASA UNICO PHASE - 1 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), CASA UNICO PHASE - 1's builder applied to MahaRERA to extend the completion date 4 times: to 30 December 2022, giving the reason "1.) Stop work notice issued by the (Revenue and Forest Department), District Collector and District Magistrate, Raigad - Alibuag, dated 02.08.2018, due to which the actual work could not be carried on as per the sanctioned plan resulting in delay for a period of (5) Five months. 2. )Also, post the said stop work notice was lifted on 12/12/2018, the migratory labourers were not available at the site of the Builder / Promoter/ Developer for a quick kick start resulting in further delay of another (4) Four months; 3.) Due to the pre-pandemic situation Covid Phase - I and strict Lockdown situat…"; to 31 December 2023, giving the reason "vi. Various reasons for the project to be stalled and delay in completion of the development works: a. Stop work notice issued by the (Revenue and Forest Department), District Collector and District Magistrate, Raigad - Alibuag, dated 02.08.2018, due to which the actual work could not be carried on as per the sanctioned plan resulting in delay for a period of (5) Five months. Also, post the said stop work notice was lifted on 12/12/2018, the migratory labourers were not available at the site of the Builder / Promoter/ Developer for a quick kick start resulting in further delay of another (4…"; to 31 December 2025, giving the reason "Various reasons for the project to be stalled and delay in completion of the development works: a. Stop work notice issued by the (Revenue and Forest Department), District Collector and District Magistrate, Raigad - Alibuag, dated 02.08.2018, due to which the actual work could not be carried on as per the sanctioned plan resulting in delay for a period of (5) Five months. Also, post the said stop work notice was lifted on 12/12/2018, the migratory labourers were not available at the site of the Builder / Promoter/ Developer for a quick kick start resulting in further delay of another (4) Fo…"; to 31 December 2026, giving the reason "The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essential construction materials, including but not limited to cement, steel, copper, electrical components, plumbing materials, and paints. This escalation in material costs has resulted in severe financial strain, disrupting the supply chain and leading to delays in procurement and delivery of these materials to the project site. In particular, the delivery tim…".

What is the RERA number of CASA UNICO PHASE - 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of CASA UNICO PHASE - 1 in Karjat, Raigarh is P52000007113.

Is CASA UNICO PHASE - 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), CASA UNICO PHASE - 1 is registered as P52000007113 and its status is "Registered and active".

What is the construction status of CASA UNICO PHASE - 1?

According to GharKundli's check of MahaRERA records (updated October 2026), CASA UNICO PHASE - 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 10 towers. GharKundli's full report compares construction progress with the deadline.

Does CASA UNICO PHASE - 1 have complaints on MahaRERA?

12 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is CASA UNICO PHASE - 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), CASA UNICO PHASE - 1 is registered on MahaRERA as P52000007113, its completion date has moved 60 months since registration and 12 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if CASA UNICO PHASE - 1's possession date changes?

The latest dates are on CASA UNICO PHASE - 1's MahaRERA page (P52000007113). GharKundli's Kundli Watch sends a free WhatsApp update on CASA UNICO PHASE - 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does CASA UNICO PHASE - 1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), CASA UNICO PHASE - 1 has 10 buildings filed: ADONIA-1 with 6 floors and 32 units; ADONIA-2 with 6 floors and 32 units; ADONIA-3 with 6 floors and 32 units; ADONIA-4 with 6 floors and 32 units; GRANDE-1 with 5 floors and 6 units; GRANDE-2 with 5 floors and 6 units; and 4 more.

How much parking does CASA UNICO PHASE - 1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 116 covered car parking spaces for CASA UNICO PHASE - 1.

How big is the land of CASA UNICO PHASE - 1?

According to GharKundli's check of MahaRERA records (updated October 2026), CASA UNICO PHASE - 1 stands on 33,529 sq m of land (about 8.3 acres), with 11,870 sq m of sanctioned built-up area and 7,435 sq m of recreational open space.

Where can I read reviews of CASA UNICO PHASE - 1?

Google Maps has reviews of CASA UNICO PHASE - 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 12 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is CASA UNICO PHASE - 1?

CASA UNICO PHASE - 1 by Landmark Real Estate Developers Limited is in Karjat, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000007113, per GharKundli's check of MahaRERA records.

How many homes are in CASA UNICO PHASE - 1?

According to GharKundli's check of MahaRERA records (updated October 2026), CASA UNICO PHASE - 1 has 216 homes in 10 towers registered on MahaRERA, and 94% of them are sold or booked.

When was CASA UNICO PHASE - 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), CASA UNICO PHASE - 1 was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on CASA UNICO PHASE - 1?

3 court cases are listed for CASA UNICO PHASE - 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of CASA UNICO PHASE - 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Landmark Real Estate Developers Limited.

All projects with possession due in 2026 in Raigad →

Other projects in pincode 410201

All 311 projects in Karjat (410201) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.