SHREE VALLABH AANGAN

by Hansa Nalin Patel · karjat, Raigarh

Possession date of SHREE VALLABH AANGAN: 30 April 2028, moved from 30 December 2022 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000003436, and currently active. Its completion date has moved from December 2022 to April 2028: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHREE VALLABH AANGAN?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on SHREE VALLABH AANGAN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000003436
Status
Registered and active
Builder
Hansa Nalin Patel
Location
karjat, Raigarh · 410201
Project type
Residential / Group Housing
Registered on
5 Aug 2017
Completion date at registration
December 2022
Latest completion date
April 2028
Delay so far
60 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
180
Towers
8
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found

Construction progress of SHREE VALLABH AANGAN, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING NO 1 WING A100%100%100%100%
BUILDING NO 1 WING B100%100%100%100%
BUILDING NO 1 WING C100%100%100%100%
BUILDING NO 1 WING D100%100%100%100%
BUILDING NO 1 WING E100%100%100%100%
BUILDING NO 2 WING F100%0%0%0%
BUILDING NO 2 WING G100%0%0%0%
BUILDING NO 2 WING H100%100%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREE VALLABH AANGAN every month.

SHREE VALLABH AANGAN: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING NO 1 WING A (5 floors) · BUILDING NO 1 WING B (5 floors) · BUILDING NO 1 WING C (5 floors) · BUILDING NO 1 WING D (5 floors) · BUILDING NO 1 WING E (5 floors) · BUILDING NO 2 WING F (5 floors) · BUILDING NO 2 WING G (5 floors) · BUILDING NO 2 WING H (5 floors)
  • Land: 5,660 sq m (about 1.4 acres) · sanctioned built-up 5,656 sq m · recreational space 839 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHREE VALLABH AANGAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHREE VALLABH AANGAN: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHREE VALLABH AANGAN

What is the possession date of SHREE VALLABH AANGAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHREE VALLABH AANGAN in karjat, Raigarh is 30 April 2028 — 60 months later than 30 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SHREE VALLABH AANGAN?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREE VALLABH AANGAN's builder has filed on MahaRERA, the official one, is 30 April 2028, already 60 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of SHREE VALLABH AANGAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHREE VALLABH AANGAN in karjat, Raigarh is P52000003436.

Is SHREE VALLABH AANGAN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE VALLABH AANGAN is registered as P52000003436 and its status is "Registered and active".

What is the construction status of SHREE VALLABH AANGAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE VALLABH AANGAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 8 towers. GharKundli's full report compares construction progress with the deadline.

Does SHREE VALLABH AANGAN have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SHREE VALLABH AANGAN safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE VALLABH AANGAN is registered on MahaRERA as P52000003436, its completion date has moved 60 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHREE VALLABH AANGAN's possession date changes?

The latest dates are on SHREE VALLABH AANGAN's MahaRERA page (P52000003436). GharKundli's Kundli Watch sends a free WhatsApp update on SHREE VALLABH AANGAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHREE VALLABH AANGAN have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE VALLABH AANGAN has 8 buildings filed: BUILDING NO 1 WING A with 5 floors; BUILDING NO 1 WING B with 5 floors; BUILDING NO 1 WING C with 5 floors; BUILDING NO 1 WING D with 5 floors; BUILDING NO 1 WING E with 5 floors; BUILDING NO 2 WING F with 5 floors; and 2 more.

How big is the land of SHREE VALLABH AANGAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE VALLABH AANGAN stands on 5,660 sq m of land (about 1.4 acres), with 5,656 sq m of sanctioned built-up area and 839 sq m of recreational open space.

Where can I read reviews of SHREE VALLABH AANGAN?

Google Maps has reviews of SHREE VALLABH AANGAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHREE VALLABH AANGAN?

SHREE VALLABH AANGAN by Hansa Nalin Patel is in karjat, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000003436, per GharKundli's check of MahaRERA records.

How many homes are in SHREE VALLABH AANGAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE VALLABH AANGAN has 180 homes in 8 towers registered on MahaRERA.

When was SHREE VALLABH AANGAN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE VALLABH AANGAN was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SHREE VALLABH AANGAN?

No court cases are listed for SHREE VALLABH AANGAN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SHREE VALLABH AANGAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Hansa Nalin Patel.

All projects with possession due in 2028 in Raigad →

Other projects in pincode 410201

All 310 projects in Karjat (410201) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.