Concord Legacy Vrindavan

by Concord Enterprises · Gundge, Next To Gundge Municipal School, Raigarh 400075Registered on MahaRERA as “Legacy Vrindavan”

What’s in the report? →

Possession date of Concord Legacy Vrindavan (MahaRERA P52000012969): 30 April 2028, moved from 31 December 2018 (108 months later). It has 98 homes, 15% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000012969, and currently active. Its completion date has moved from December 2018 to April 2028: 108 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P52000012969, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Concord Legacy Vrindavan?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Concord Legacy Vrindavan has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EXT52000019221)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 71.43% allottees for purpose of extension of RERA registration period of the said project.”
  3. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Concord Legacy Vrindavan’s extension records on MahaRERA (P52000012969), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Concord Legacy Vrindavan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000012969
Status
Registered and active
Builder
Concord Enterprises
Location
Gundge, Next To Gundge Municipal School, Raigarh · 400075
Project type
Residential / Group Housing
Registered on
7 Sep 2017
Completion date at registration
December 2018
Latest completion date
April 2028
Delay so far
108 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
98
Sold or booked
15%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Concord Legacy Vrindavan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A Wing70%100%100%100%
B wing70%100%40%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Concord Legacy Vrindavan every 1–2 months.

Concord Legacy Vrindavan: buildings, flats and land, as filed on MahaRERA

  • Buildings: A Wing (9 floors) · B wing (9 floors)
  • Land: 7,860 sq m (about 1.9 acres) · sanctioned built-up 10,665 sq m · recreational space 750 sq m
  • Land, as filed: 17/1/A/3/A/2/B, 18/3/A/1 tO 10, 18/1/A, 18/1/B, 18/1/C
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Concord Legacy Vrindavan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Concord Legacy Vrindavan: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Concord Legacy Vrindavan

What is the possession date of Concord Legacy Vrindavan?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Concord Legacy Vrindavan in Gundge, Next To Gundge Municipal School, Raigarh is 30 April 2028 — 108 months later than 31 December 2018, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 108 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Concord Legacy Vrindavan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Concord Legacy Vrindavan's builder has filed on MahaRERA, the official one, is 30 April 2028, already 108 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Concord Legacy Vrindavan extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Concord Legacy Vrindavan's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 71.43% allottees for purpose of extension of RERA registration period of the said project.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Concord Legacy Vrindavan?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Concord Legacy Vrindavan in Gundge, Next To Gundge Municipal School, Raigarh is P52000012969.

Is Concord Legacy Vrindavan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Concord Legacy Vrindavan is registered as P52000012969 and its status is "Registered and active".

What is the current construction status of Concord Legacy Vrindavan? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Concord Legacy Vrindavan's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Concord Legacy Vrindavan have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Concord Legacy Vrindavan safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Concord Legacy Vrindavan is registered on MahaRERA as P52000012969, its completion date has moved 108 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Concord Legacy Vrindavan?

Concord Legacy Vrindavan is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Concord Legacy Vrindavan?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Concord Legacy Vrindavan: gharkundli.com/tools/property-cost-calculator

Has Concord Legacy Vrindavan received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Concord Legacy Vrindavan is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Concord Legacy Vrindavan uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Concord Legacy Vrindavan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Concord Legacy Vrindavan's possession date changes?

The latest dates are on Concord Legacy Vrindavan's MahaRERA page (P52000012969). GharKundli's Kundli Watch sends a free WhatsApp update on Concord Legacy Vrindavan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Concord Legacy Vrindavan have?

According to GharKundli's check of MahaRERA records (updated October 2026), Concord Legacy Vrindavan has 2 buildings filed: A Wing with 9 floors; B wing with 9 floors.

How big is the land of Concord Legacy Vrindavan?

According to GharKundli's check of MahaRERA records (updated October 2026), Concord Legacy Vrindavan stands on 7,860 sq m of land (about 1.9 acres), with 10,665 sq m of sanctioned built-up area and 750 sq m of recreational open space.

What are the reviews of Concord Legacy Vrindavan?

Google Maps has reviews of Concord Legacy Vrindavan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Concord Legacy Vrindavan?

Concord Legacy Vrindavan by Concord Enterprises is in Gundge, Next To Gundge Municipal School, Raigarh, pincode 400075, Maharashtra, and is registered on MahaRERA as P52000012969, per GharKundli's check of MahaRERA records. Its land is filed as 17/1/A/3/A/2/B, 18/3/A/1 tO 10, 18/1/A, 18/1/B, 18/1/C. GharKundli lists all 133 MahaRERA projects in Ghatkopar East (400075).

How many flats are in Concord Legacy Vrindavan, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Concord Legacy Vrindavan has 98 homes in 2 towers registered on MahaRERA, and 15% of them are sold or booked.

When was Concord Legacy Vrindavan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Concord Legacy Vrindavan was registered on MahaRERA on 7 September 2017. GharKundli did not find a title report on the land on file there.

Does Concord Legacy Vrindavan have any legal issues or court cases?

No court cases are listed for Concord Legacy Vrindavan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Concord Legacy Vrindavan?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Concord Enterprises.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Karjat

All 133 projects in Ghatkopar East (400075) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.