Swastik Epitome Building 2 Phase III 15 to 21 floors
by MAHAVIR HOMES · Behind D Mart Virar East, PalgharAlso near Virar West
Possession date of Swastik Epitome Building 2 Phase III 15 to 21 floors: 31 July 2027, moved from 30 December 2021 (63 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000005964, and currently active. Its completion date has moved from December 2021 to July 2027: 63 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Swastik Epitome Building 2 Phase III 15 to 21 floors?
How the possession date of Swastik Epitome Building 2 Phase III 15 to 21 floors has moved
30 December 2021
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EXT99000013554)
Reason the builder gave MahaRERA: “The project is delayed due to worldwide Pandemic situation which led to financial crisis. Also, due to unforseen circumstances i.e on- availabilty of labour , materials and lack of customer demand occurred during the Pandemic period.”
31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Swastik Epitome Building 2 Phase III 15 to 21 floors’s extension records on MahaRERA (P99000005964), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Swastik Epitome Building 2 Phase III 15 to 21 floors
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Swastik Epitome Building 1 Phase III 15 to 21 floorsP99000008299 · possession 31 Jul 2028
- MahaRERA registration
- P99000005964
- Status
- Registered and active
- Builder
- MAHAVIR HOMES
- Location
- Behind D Mart Virar East, Palghar · 401305
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- December 2021
- Latest completion date
- July 2027
- Delay so far
- 63 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 177
- Sold or booked
- 43%
- Towers
- 5
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of Swastik Epitome Building 2 Phase III 15 to 21 floors, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| C WING | 100% | 100% | 95% | 95% |
| D WING | 100% | 100% | 95% | 95% |
| E WING | 100% | 100% | 75% | 70% |
| F WING | 100% | 100% | 75% | 70% |
| G WING | 100% | 100% | 75% | 70% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Swastik Epitome Building 2 Phase III 15 to 21 floors every month.
Swastik Epitome Building 2 Phase III 15 to 21 floors: buildings, flats and land, as filed on MahaRERA
- Buildings: C WING (9 floors) · D WING (9 floors) · E WING (9 floors) · F WING (9 floors) · G WING (9 floors)
- Land: 3,421 sq m (about 0.8 acres) · sanctioned built-up 7,957 sq m · recreational space 2,827 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Mahavir Homes has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 4 still being built, 4 past the promised date (typically 42 months late). No complaints on MahaRERA.
Read Google reviews of Swastik Epitome Building 2 Phase III 15 to 21 floors →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Swastik Epitome Building 2 Phase III 15 to 21 floors: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Swastik Epitome Building 2 Phase III 15 to 21 floors
What is the possession date of Swastik Epitome Building 2 Phase III 15 to 21 floors?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Swastik Epitome Building 2 Phase III 15 to 21 floors in Behind D Mart Virar East, Palghar is 31 July 2027 — 63 months later than 30 December 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Swastik Epitome Building 2 Phase III 15 to 21 floors?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Swastik Epitome Building 2 Phase III 15 to 21 floors's builder has filed on MahaRERA, the official one, is 31 July 2027, already 63 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Swastik Epitome Building 2 Phase III 15 to 21 floors extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Swastik Epitome Building 2 Phase III 15 to 21 floors's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "The project is delayed due to worldwide Pandemic situation which led to financial crisis. Also, due to unforseen circumstances i.e on- availabilty of labour , materials and lack of customer demand occurred during the Pandemic period.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Swastik Epitome Building 2 Phase III 15 to 21 floors?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Swastik Epitome Building 2 Phase III 15 to 21 floors in Behind D Mart Virar East, Palghar is P99000005964.
Is Swastik Epitome Building 2 Phase III 15 to 21 floors registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Swastik Epitome Building 2 Phase III 15 to 21 floors is registered as P99000005964 and its status is "Registered and active".
What is the construction status of Swastik Epitome Building 2 Phase III 15 to 21 floors?
According to GharKundli's check of MahaRERA records (updated November 2026), Swastik Epitome Building 2 Phase III 15 to 21 floors's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does Swastik Epitome Building 2 Phase III 15 to 21 floors have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Swastik Epitome Building 2 Phase III 15 to 21 floors safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Swastik Epitome Building 2 Phase III 15 to 21 floors is registered on MahaRERA as P99000005964, its completion date has moved 63 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Swastik Epitome Building 2 Phase III 15 to 21 floors have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Swastik Epitome Building 1 Phase III 15 to 21 floors (P99000008299, possession 31 Jul 2028). Check that your agreement names the registration of your own wing.
How can I get updates if Swastik Epitome Building 2 Phase III 15 to 21 floors's possession date changes?
The latest dates are on Swastik Epitome Building 2 Phase III 15 to 21 floors's MahaRERA page (P99000005964). GharKundli's Kundli Watch sends a free WhatsApp update on Swastik Epitome Building 2 Phase III 15 to 21 floors every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Swastik Epitome Building 2 Phase III 15 to 21 floors have?
According to GharKundli's check of MahaRERA records (updated November 2026), Swastik Epitome Building 2 Phase III 15 to 21 floors has 5 buildings filed: C WING with 9 floors; D WING with 9 floors; E WING with 9 floors; F WING with 9 floors; G WING with 9 floors.
How big is the land of Swastik Epitome Building 2 Phase III 15 to 21 floors?
According to GharKundli's check of MahaRERA records (updated November 2026), Swastik Epitome Building 2 Phase III 15 to 21 floors stands on 3,421 sq m of land (about 0.8 acres), with 7,957 sq m of sanctioned built-up area and 2,827 sq m of recreational open space.
What is the track record of Swastik Epitome Building 2 Phase III 15 to 21 floors's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahavir Homes has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 4 still being built, 4 past the promised date (typically 42 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Swastik Epitome Building 2 Phase III 15 to 21 floors?
Google Maps has reviews of Swastik Epitome Building 2 Phase III 15 to 21 floors written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Swastik Epitome Building 2 Phase III 15 to 21 floors?
Swastik Epitome Building 2 Phase III 15 to 21 floors by MAHAVIR HOMES is in Behind D Mart Virar East, Palghar (pincode 401305), near Virar West, Maharashtra, and is registered on MahaRERA as P99000005964, per GharKundli's check of MahaRERA records.
How many homes are in Swastik Epitome Building 2 Phase III 15 to 21 floors?
According to GharKundli's check of MahaRERA records (updated November 2026), Swastik Epitome Building 2 Phase III 15 to 21 floors has 177 homes in 5 towers registered on MahaRERA, and 43% of them are sold or booked.
When was Swastik Epitome Building 2 Phase III 15 to 21 floors registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Swastik Epitome Building 2 Phase III 15 to 21 floors was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Swastik Epitome Building 2 Phase III 15 to 21 floors?
No court cases are listed for Swastik Epitome Building 2 Phase III 15 to 21 floors on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Swastik Epitome Building 2 Phase III 15 to 21 floors?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MAHAVIR HOMES, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Swastik Epitome Building 2 Phase III 15 to 21 floors
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Palghar →
Other projects in pincode 401305
- Swastik Epitome Building 2 Phase I Ground to 7 floors
- Swastik Epitome Building 2 Phase II 8 to 14 floors
- SIDDHIVINAYAK CROWN
- GIRDHARI HEIGHTS
- VIRAT CO-OP HOUSING SOCIETY
- NANA HEIGHTS
- SHREE SWAMI SAMARTH NX
- SHIVNERI
Other projects by MAHAVIR HOMES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.