SHETH BLUE IVY
by Sheth Developers Private Limited · Dindoshi Malad, MumbaiAlso near Malad East, Goregaon East, Pathanwadi
Possession date of SHETH BLUE IVY: 28 March 2028, moved from 30 June 2023 (53 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800001407, and currently active. Its completion date has moved from June 2023 to March 2028: 53 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project. 19 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHETH BLUE IVY?
How the possession date of SHETH BLUE IVY has moved
30 June 2023
Completion date given when the project was registered
29 June 2024
Extended at the builder's request (MahaRERA application EXT51800015214)
Reason the builder gave MahaRERA:
“1) The said Project is part of the Layout Project being constructed in Larger Property. On the said Larger Layout, the Promoter has already constructed and developed Building No.1 (commercial building and known as “Sheth House”, Building No…” Read the full reason
“1) The said Project is part of the Layout Project being constructed in Larger Property. On the said Larger Layout, the Promoter has already constructed and developed Building No.1 (commercial building and known as “Sheth House”, Building No. 2 & 3 (having A & B wing) which is now known as Vasant Valley Aster Tower Co-Operative Housing Society Ltd. and Building No.3 (having A & B Wing) which is now known as Venus Vasant Valley Co-Operative Housing Society Ltd. The Promoter has subsequently proposed said Project i.e. Building No. 4 consisting of 34 stories by utilizing the balance FSI and TDR…”28 November 2027
Extended at the builder's request (MahaRERA application EXT51800024129)
Reason the builder gave MahaRERA:
“The said Project is part of the Layout Project being constructed in Larger Property. On the said Larger Layout, the Promoter has already constructed and developed Building No.1 (commercial building and known as “Sheth House”, Building No. 2…” Read the full reason
“The said Project is part of the Layout Project being constructed in Larger Property. On the said Larger Layout, the Promoter has already constructed and developed Building No.1 (commercial building and known as “Sheth House”, Building No. 2 & 3 (having A & B wing) which is now known as Vasant Valley Aster Tower Co-Operative Housing Society Ltd. and Building No.3 (having A & B Wing) which is now known as Venus Vasant Valley Co-Operative Housing Society Ltd. The Promoter has subsequently proposed said Project i.e. Building No. 4 consisting of 34 stories by utilizing the balance FSI and TDR av…”28 March 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SHETH BLUE IVY’s extension records on MahaRERA (P51800001407), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHETH BLUE IVY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 19 complaints and 3 court cases, and how it ended
- Construction pace against the March 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800001407
- Status
- Registered and active
- Builder
- Sheth Developers Private Limited
- Location
- Dindoshi Malad, Mumbai · 400097
- Project type
- Residential / Group Housing
- Registered on
- 28 Jul 2017
- Completion date at registration
- June 2023
- Latest completion date
- March 2028
- Delay so far
- 53 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 66
- Sold or booked
- 56%
- Towers
- 1
- Complaints on MahaRERA
- 19
- Court cases listed
- 3
- Appeals at the tribunal
- 17
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 9
Construction progress of SHETH BLUE IVY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BLUE IVY | 3% | 0% | 0% | 10% |
Commencement certificate (CC), as filed on MahaRERA
- BLUE IVY: covers 0 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHETH BLUE IVY every month.
SHETH BLUE IVY: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 4 BHK | 1,734 – 1,778 | 61 |
| 2 BHK | 1,058 | 4 |
| 3 BHK | 1,374 | 1 |
- Buildings: BLUE IVY (37 floors, 66 units)
- Car parking: 1 covered
- Land: 1,735 sq m (about 0.4 acres) · sanctioned built-up 694 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Sheth Developers (a group of 4 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 27 months); 9 still being built, 6 past the promised date (typically 21 months late). 295 complaints on MahaRERA across 11 projects.
Read Google reviews of SHETH BLUE IVY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHETH BLUE IVY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHETH BLUE IVY
What is the possession date of SHETH BLUE IVY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHETH BLUE IVY in Dindoshi Malad, Mumbai is 28 March 2028 — 53 months later than 30 June 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SHETH BLUE IVY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHETH BLUE IVY's builder has filed on MahaRERA, the official one, is 28 March 2028, already 53 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHETH BLUE IVY extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHETH BLUE IVY's builder applied to MahaRERA to extend the completion date 2 times: to 29 June 2024, giving the reason "1) The said Project is part of the Layout Project being constructed in Larger Property. On the said Larger Layout, the Promoter has already constructed and developed Building No.1 (commercial building and known as “Sheth House”, Building No. 2 & 3 (having A & B wing) which is now known as Vasant Valley Aster Tower Co-Operative Housing Society Ltd. and Building No.3 (having A & B Wing) which is now known as Venus Vasant Valley Co-Operative Housing Society Ltd. The Promoter has subsequently proposed said Project i.e. Building No. 4 consisting of 34 stories by utilizing the balance FSI and TDR…"; to 28 November 2027, giving the reason "The said Project is part of the Layout Project being constructed in Larger Property. On the said Larger Layout, the Promoter has already constructed and developed Building No.1 (commercial building and known as “Sheth House”, Building No. 2 & 3 (having A & B wing) which is now known as Vasant Valley Aster Tower Co-Operative Housing Society Ltd. and Building No.3 (having A & B Wing) which is now known as Venus Vasant Valley Co-Operative Housing Society Ltd. The Promoter has subsequently proposed said Project i.e. Building No. 4 consisting of 34 stories by utilizing the balance FSI and TDR av…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SHETH BLUE IVY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHETH BLUE IVY in Dindoshi Malad, Mumbai is P51800001407.
Is SHETH BLUE IVY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHETH BLUE IVY is registered as P51800001407 and its status is "Registered and active".
What is the construction status of SHETH BLUE IVY?
According to GharKundli's check of MahaRERA records (updated October 2026), SHETH BLUE IVY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BLUE IVY is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does SHETH BLUE IVY have complaints on MahaRERA?
19 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SHETH BLUE IVY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHETH BLUE IVY is registered on MahaRERA as P51800001407, its completion date has moved 53 months since registration and 19 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHETH BLUE IVY's possession date changes?
The latest dates are on SHETH BLUE IVY's MahaRERA page (P51800001407). GharKundli's Kundli Watch sends a free WhatsApp update on SHETH BLUE IVY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHETH BLUE IVY have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHETH BLUE IVY has one building filed: BLUE IVY with 37 floors and 66 units.
What are the flat sizes (carpet area) in SHETH BLUE IVY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SHETH BLUE IVY: 4 BHK: 1734 to 1778 sq ft carpet (61 homes); 2 BHK: 1058 sq ft carpet (4 homes); 3 BHK: 1374 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does SHETH BLUE IVY have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for SHETH BLUE IVY.
How big is the land of SHETH BLUE IVY?
According to GharKundli's check of MahaRERA records (updated October 2026), SHETH BLUE IVY stands on 1,735 sq m of land (about 0.4 acres), with 694 sq m of sanctioned built-up area.
What is the track record of SHETH BLUE IVY's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Developers (a group of 4 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 27 months); 9 still being built, 6 past the promised date (typically 21 months late). 295 complaints on MahaRERA across 11 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHETH BLUE IVY?
Google Maps has reviews of SHETH BLUE IVY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 19 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHETH BLUE IVY?
SHETH BLUE IVY by Sheth Developers Private Limited is in Dindoshi Malad, Mumbai (pincode 400097), near Malad East, Goregaon East, Pathanwadi, Maharashtra, and is registered on MahaRERA as P51800001407, per GharKundli's check of MahaRERA records.
How many homes are in SHETH BLUE IVY?
According to GharKundli's check of MahaRERA records (updated October 2026), SHETH BLUE IVY has 66 homes in 1 tower registered on MahaRERA, and 56% of them are sold or booked.
When was SHETH BLUE IVY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHETH BLUE IVY was registered on MahaRERA on 28 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SHETH BLUE IVY?
3 court cases are listed for SHETH BLUE IVY on MahaRERA, and 17 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SHETH BLUE IVY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sheth Developers Private Limited, which has 9 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SHETH BLUE IVY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Borivali
- SAFFRONWOODS CHSL
- L&T Realty Ahana Tower B
- PARSHURAM HEIGHTS
- L&T Realty Ahana Tower A
- AVIRAHI ELEGANCE
- RASHMI ICON
- MARU MANSION
- SHRADDHA SKYLINE
Other projects by Sheth Developers Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.