SHETH ZURI

by Sheth Developers Private Limited · Near Viviana Mall, ThaneAlso near Thane west, Majiwada, Village Panchpakhadi

Possession date of SHETH ZURI: 29 April 2027, moved from 30 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700007274, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project. 66 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHETH ZURI?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHETH ZURI has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 29 December 2026

    Extended at the builder's request (MahaRERA application EXT51700024847)

    Reason the builder gave MahaRERA:
    “1. Stop Work Notice by Labor Department (delayed period January 21, 2020, to July 2020): On January 21, 2020, the Labor Department issued a letter (Inward No. 3457) addressed to the Thane Municipal Corporation, resulting in a Notice on Febr…” Read the full reason“1. Stop Work Notice by Labor Department (delayed period January 21, 2020, to July 2020): On January 21, 2020, the Labor Department issued a letter (Inward No. 3457) addressed to the Thane Municipal Corporation, resulting in a Notice on February 20, 2020. This effectively halted all construction activities on the Zuri Project. A copy of the Notice dated February 20, 2020 is annexed herewith as Annexure I. 2. Cheating by TDR Seller (delayed period November 05, 2020, to May 04, 2023): Sheth Developers Pvt. Ltd. entered into a TDR Purchase Agreement with Krishna Developers Pvt. Ltd. on November…”
  3. 29 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SHETH ZURI’s extension records on MahaRERA (P51700007274), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHETH ZURI

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 66 complaints, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700007274
Status
Registered and active
Builder
Sheth Developers Private Limited
Location
Near Viviana Mall, Thane · 400601
Project type
Residential / Group Housing
Registered on
17 Aug 2017
Completion date at registration
December 2024
Latest completion date
April 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
709
Sold or booked
98%
Towers
3
Complaints on MahaRERA
66
Court cases listed
0
Appeals at the tribunal
14
MahaRERA regulatory orders
1
Title report on file
Not found
Builder's other MahaRERA projects
9

Construction progress of SHETH ZURI, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
TOWER 1100%100%100%75%
TOWER 2100%100%100%100%
TOWER 3100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • TOWER 1: covers 28 floors
  • TOWER 2: covers 28 floors
  • TOWER 3: covers 28 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHETH ZURI every month.

SHETH ZURI: buildings, flats and land, as filed on MahaRERA

  • Buildings: TOWER 1 (35 floors, 241 units) · TOWER 2 (35 floors, 238 units) · TOWER 3 (35 floors, 238 units)
  • Car parking: 906 covered
  • Land: 9,099 sq m (about 2.2 acres) · sanctioned built-up 21,341 sq m · recreational space 1,559 sq m
  • Boundaries filed include: EASTER EXPRESS HIGHWAY, SUBHASH NAGAR SLUM
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Sheth Developers (a group of 4 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 27 months); 9 still being built, 6 past the promised date (typically 21 months late). 295 complaints on MahaRERA across 11 projects.

Read Google reviews of SHETH ZURI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHETH ZURI: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHETH ZURI

What is the possession date of SHETH ZURI?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHETH ZURI in Near Viviana Mall, Thane is 29 April 2027 — 24 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SHETH ZURI?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHETH ZURI's builder has filed on MahaRERA, the official one, is 29 April 2027, already 24 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHETH ZURI extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SHETH ZURI's builder applied to MahaRERA to extend the completion date once: to 29 December 2026, giving the reason "1. Stop Work Notice by Labor Department (delayed period January 21, 2020, to July 2020): On January 21, 2020, the Labor Department issued a letter (Inward No. 3457) addressed to the Thane Municipal Corporation, resulting in a Notice on February 20, 2020. This effectively halted all construction activities on the Zuri Project. A copy of the Notice dated February 20, 2020 is annexed herewith as Annexure I. 2. Cheating by TDR Seller (delayed period November 05, 2020, to May 04, 2023): Sheth Developers Pvt. Ltd. entered into a TDR Purchase Agreement with Krishna Developers Pvt. Ltd. on November…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SHETH ZURI?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHETH ZURI in Near Viviana Mall, Thane is P51700007274.

Is SHETH ZURI registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHETH ZURI is registered as P51700007274 and its status is "Registered and active".

What is the construction status of SHETH ZURI?

According to GharKundli's check of MahaRERA records (updated October 2026), SHETH ZURI's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does SHETH ZURI have complaints on MahaRERA?

66 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SHETH ZURI safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHETH ZURI is registered on MahaRERA as P51700007274, its completion date has moved 24 months since registration and 66 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHETH ZURI's possession date changes?

The latest dates are on SHETH ZURI's MahaRERA page (P51700007274). GharKundli's Kundli Watch sends a free WhatsApp update on SHETH ZURI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHETH ZURI have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHETH ZURI has 3 buildings filed: TOWER 1 with 35 floors and 241 units; TOWER 2 with 35 floors and 238 units; TOWER 3 with 35 floors and 238 units.

How much parking does SHETH ZURI have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 906 covered car parking spaces for SHETH ZURI.

How big is the land of SHETH ZURI?

According to GharKundli's check of MahaRERA records (updated October 2026), SHETH ZURI stands on 9,099 sq m of land (about 2.2 acres), with 21,341 sq m of sanctioned built-up area and 1,559 sq m of recreational open space.

What is the track record of SHETH ZURI's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Developers (a group of 4 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 27 months); 9 still being built, 6 past the promised date (typically 21 months late). 295 complaints on MahaRERA across 11 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SHETH ZURI?

Google Maps has reviews of SHETH ZURI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 66 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHETH ZURI?

SHETH ZURI by Sheth Developers Private Limited is in Near Viviana Mall, Thane (pincode 400601), near Thane west, Majiwada, Village Panchpakhadi, Maharashtra, and is registered on MahaRERA as P51700007274, per GharKundli's check of MahaRERA records. Its boundaries filed there include EASTER EXPRESS HIGHWAY, SUBHASH NAGAR SLUM.

How many homes are in SHETH ZURI?

According to GharKundli's check of MahaRERA records (updated October 2026), SHETH ZURI has 709 homes in 3 towers registered on MahaRERA, and 98% of them are sold or booked.

When was SHETH ZURI registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHETH ZURI was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SHETH ZURI?

No court cases are listed for SHETH ZURI on MahaRERA, and 14 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SHETH ZURI?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sheth Developers Private Limited, which has 9 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Thane

All 178 projects in Thane (400601) →

Other projects by Sheth Developers Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.