SHETH CNERGY MALAD
by Sheth Developers Private Limited · Dindoshi - Malad, Mumbai
Registered on MahaRERA under P51800027269, and currently active. Its completion date has moved from June 2023 to March 2028, 57 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on SHETH CNERGY MALAD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800027269
- Status
- Registered and active
- Builder
- Sheth Developers Private Limited
- Location
- Dindoshi - Malad, Mumbai · 400097
- Project type
- Commercial
- Registered on
- 28 Nov 2020
- Completion date at registration
- June 2023
- Latest completion date
- March 2028
- Delay so far
- 57 months
- Homes
- 0
- Sold or booked
- 64%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 6
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 9
Kundli Watch
SHETH CNERGY MALAD: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about SHETH CNERGY MALAD
Is SHETH CNERGY MALAD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHETH CNERGY MALAD is registered as P51800027269 and its status is "Registered and active".
Where is SHETH CNERGY MALAD?
SHETH CNERGY MALAD by Sheth Developers Private Limited is in Dindoshi - Malad, Mumbai (pincode 400097), Maharashtra, and is registered on MahaRERA as P51800027269, per GharKundli's check of MahaRERA records.
When is possession of SHETH CNERGY MALAD due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHETH CNERGY MALAD in Dindoshi - Malad, Mumbai is 28 March 2028 — 57 months later than 30 June 2023, the date given at registration.
Does SHETH CNERGY MALAD have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of SHETH CNERGY MALAD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sheth Developers Private Limited, which has 9 other projects registered on MahaRERA.
Other projects in pincode 400097
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.