Sheth Cnergy Malad
by Sheth Developers Private Limited · Dindoshi - Malad, Mumbai 400097Also near Malad East, Goregaon East
What’s in the report? →Possession date of Sheth Cnergy Malad (MahaRERA P51800027269): 28 March 2028, moved from 30 June 2023 (53 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800027269, and currently active. Its completion date has moved from June 2023 to March 2028: 53 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project.
Source: MahaRERA website — records for P51800027269, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Sheth Cnergy Malad?
6 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sheth Cnergy Malad has moved
30 June 2023
Completion date given when the project was registered
29 June 2024
Extended at the builder's request (MahaRERA application EXT51800016799)
Reason the builder gave MahaRERA:
“The reason for construction of the Project being at halt and unlikely to be completed by 30.06.2023: 1. The applicant has submitted an application for CC revalidation vide its architect letter dated 15.11.2022, which was duly granted on 13.…” Read the full reason
“The reason for construction of the Project being at halt and unlikely to be completed by 30.06.2023: 1. The applicant has submitted an application for CC revalidation vide its architect letter dated 15.11.2022, which was duly granted on 13.12.2022. Hereto annexed and marked as Annexure - B is copy of the CC revalidation approval granted by Municipal Corporation of Greater Mumbai. 2. The applicant has also submitted amended plan of the proposed project building to the Municipal Corporation of Greater Mumbai on 01.12.2022. The sub engineer (B.P) P3 and Executive Engineer (B.P) (P Ward), have…”28 November 2027
Extended at the builder's request (MahaRERA application EXT51800024130)
Reason the builder gave MahaRERA:
“a) The Applicant submits that due to reasons beyond the control of Applicant and as elaborately mentioned hereinafter, the said Project is unlikely to be completed by 29.06.2024. Hence, in the said circumstances, the Applicant is constraine…” Read the full reason
“a) The Applicant submits that due to reasons beyond the control of Applicant and as elaborately mentioned hereinafter, the said Project is unlikely to be completed by 29.06.2024. Hence, in the said circumstances, the Applicant is constrained to make this Application and seek extension of the registration of project for 42 months i.e. till 28.11.2027. b) The applicant has submitted an application online for CC revalidation on 21.11.2023, which was duly granted on 13.12.2023. c) The applicant has also submitted amended plan of the proposed project building to the Municipal Corporation of Grea…”28 March 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sheth Cnergy Malad’s extension records on MahaRERA (P51800027269), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sheth Cnergy Malad
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 6 court cases, and how it ended
- Construction pace against the March 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800027269
- Status
- Registered and active
- Builder
- Sheth Developers Private Limited
- Location
- Dindoshi - Malad, Mumbai · 400097
- Project type
- Commercial
- Registered on
- 28 Nov 2020
- Completion date at registration
- June 2023
- Latest completion date
- March 2028
- Delay so far
- 53 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 64%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 6
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 9
Construction progress of Sheth Cnergy Malad, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHETH CNERGY | 95% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SHETH CNERGY: covers 0 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sheth Cnergy Malad every 1–2 months.
Sheth Cnergy Malad: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 431 – 504 | 45 |
- Buildings: SHETH CNERGY (10 floors, 45 units)
- Car parking: 37 covered
- Land: 680 sq m (about 0.2 acres)
- Land, as filed: PART OF CTS NO 104/B OF VILLAGE DINDOSHI
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Sheth Developers (a group of 5 linked companies) has 17 projects on MahaRERA since 2017, this one included. Of the 17 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 27 months); 12 still being built, 8 past the promised date (typically 18 months late). 321 complaints on MahaRERA across 15 projects.
Read Google reviews of Sheth Cnergy Malad →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sheth Cnergy Malad: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sheth Cnergy Malad
What is the possession date of Sheth Cnergy Malad?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sheth Cnergy Malad in Dindoshi - Malad, Mumbai is 28 March 2028 — 53 months later than 30 June 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 53 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Sheth Cnergy Malad?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sheth Cnergy Malad's builder has filed on MahaRERA, the official one, is 28 March 2028, already 53 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sheth Cnergy Malad extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Cnergy Malad's builder applied to MahaRERA to extend the completion date 2 times: to 29 June 2024, giving the reason "The reason for construction of the Project being at halt and unlikely to be completed by 30.06.2023: 1. The applicant has submitted an application for CC revalidation vide its architect letter dated 15.11.2022, which was duly granted on 13.12.2022. Hereto annexed and marked as Annexure - B is copy of the CC revalidation approval granted by Municipal Corporation of Greater Mumbai. 2. The applicant has also submitted amended plan of the proposed project building to the Municipal Corporation of Greater Mumbai on 01.12.2022. The sub engineer (B.P) P3 and Executive Engineer (B.P) (P Ward), have…"; to 28 November 2027, giving the reason "a) The Applicant submits that due to reasons beyond the control of Applicant and as elaborately mentioned hereinafter, the said Project is unlikely to be completed by 29.06.2024. Hence, in the said circumstances, the Applicant is constrained to make this Application and seek extension of the registration of project for 42 months i.e. till 28.11.2027. b) The applicant has submitted an application online for CC revalidation on 21.11.2023, which was duly granted on 13.12.2023. c) The applicant has also submitted amended plan of the proposed project building to the Municipal Corporation of Grea…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sheth Cnergy Malad?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sheth Cnergy Malad in Dindoshi - Malad, Mumbai is P51800027269.
Is Sheth Cnergy Malad registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Cnergy Malad is registered as P51800027269 and its status is "Registered and active".
What is the current construction status of Sheth Cnergy Malad? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Cnergy Malad's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHETH CNERGY is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Sheth Cnergy Malad have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sheth Cnergy Malad safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Cnergy Malad is registered on MahaRERA as P51800027269, its completion date has moved 53 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sheth Cnergy Malad?
Sheth Cnergy Malad is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sheth Cnergy Malad?
For a flat in Sheth Cnergy Malad (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Sheth Cnergy Malad received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Cnergy Malad is still under construction, with 28 March 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Sheth Cnergy Malad uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sheth Cnergy Malad was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Sheth Cnergy Malad's possession date changes?
The latest dates are on Sheth Cnergy Malad's MahaRERA page (P51800027269). GharKundli's Kundli Watch sends a free WhatsApp update on Sheth Cnergy Malad every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sheth Cnergy Malad have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Cnergy Malad has one building filed: SHETH CNERGY with 10 floors and 45 units.
How much parking does Sheth Cnergy Malad have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 37 covered car parking spaces for Sheth Cnergy Malad.
How big is the land of Sheth Cnergy Malad?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Cnergy Malad stands on 680 sq m of land (about 0.2 acres).
What is the track record of Sheth Cnergy Malad's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Developers (a group of 5 linked companies) has 17 projects on MahaRERA since 2017, this one included. Of the 17 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 27 months); 12 still being built, 8 past the promised date (typically 18 months late). 321 complaints on MahaRERA across 15 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Sheth Cnergy Malad?
Google Maps has reviews of Sheth Cnergy Malad written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sheth Cnergy Malad?
Sheth Cnergy Malad by Sheth Developers Private Limited is in Dindoshi - Malad, Mumbai, pincode 400097 (near Malad East, Goregaon East), Maharashtra, and is registered on MahaRERA as P51800027269, per GharKundli's check of MahaRERA records. Its land is filed as PART OF CTS NO 104/B OF VILLAGE DINDOSHI. GharKundli lists all 195 MahaRERA projects in Malad East (400097).
How many flats are in Sheth Cnergy Malad, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Cnergy Malad has 0 homes in 1 tower registered on MahaRERA, and 64% of them are sold or booked.
When was Sheth Cnergy Malad registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Cnergy Malad was registered on MahaRERA on 28 November 2020. GharKundli did not find a title report on the land on file there.
Does Sheth Cnergy Malad have any legal issues or court cases?
6 court cases are listed for Sheth Cnergy Malad on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Sheth Cnergy Malad?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sheth Developers Private Limited, which has 9 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sheth Cnergy Malad
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Borivali
- Saffronwoods CHSL
- L&T Realty Ahana Tower A
- Avirahi Elegance
- L&T Realty Ahana Tower B
- Parshuram Heights
- Maru Mansion
- LA SERENA Tower 5, Tower 6 and Tower 7
- Shraddha Skyline
Other projects by Sheth Developers Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.