Sheth Avalon - Phase 2
by Sheth Developers Private Limited · Majiwada, Thane 400601Also near Village Panchpakhadi, Thane West, Balkum
What’s in the report? →Possession date of Sheth Avalon - Phase 2 (MahaRERA P51700015517): 30 April 2028, moved from 30 December 2025 (24 months later). It has 232 homes, 65% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700015517, and currently active. Its completion date has moved from December 2025 to April 2028: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700015517, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Sheth Avalon - Phase 2?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sheth Avalon - Phase 2 has moved
30 December 2025
Completion date given when the project was registered
30 December 2027
Extended at the builder's request (MahaRERA application EA30092517987)
Reason the builder gave MahaRERA: “As per order of the Hon'ble Chairman (MahaRERA) Dated 12/12/2025 we request you kindly to grant us extension till 30/12/2027”
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sheth Avalon - Phase 2’s extension records on MahaRERA (P51700015517), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sheth Avalon - Phase 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- SHETH AVALON - PHASE 1P51700001729 · possession 30 Dec 2021
- MahaRERA registration
- P51700015517
- Status
- Registered and active
- Builder
- Sheth Developers Private Limited
- Location
- Majiwada, Thane · 400601
- Project type
- Residential / Group Housing
- Registered on
- 7 Mar 2018
- Completion date at registration
- December 2025
- Latest completion date
- April 2028
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 232
- Sold or booked
- 65%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 9
Construction progress of Sheth Avalon - Phase 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| TOWER A | 100% | 80% | 37% | 0% |
| TOWER B | 100% | 80% | 37% | 0% |
| TOWER C | 100% | 100% | 95% | 70% |
Commencement certificate (CC), as filed on MahaRERA
- TOWER A: covers 44 floors
- TOWER B: covers 44 floors
- TOWER C: covers 28 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sheth Avalon - Phase 2 every 1–2 months.
Sheth Avalon - Phase 2: buildings, flats and land, as filed on MahaRERA
- Buildings: TOWER A (50 floors, 93 units) · TOWER B (49 floors, 92 units) · TOWER C (33 floors, 56 units)
- Car parking: 506 covered
- Land: 6,147 sq m (about 1.5 acres) · sanctioned built-up 6,214 sq m · recreational space 1,272 sq m
- Boundaries filed include: 15 MTR WIDE SERVICE ROAD
- Land, as filed: OUT OF SURVEY NO48/1P,2,3,4,5P, 49/2P,4,73/1,2,3,4,5,6,74P,526P
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Sheth Developers (a group of 5 linked companies) has 17 projects on MahaRERA since 2017, this one included. Of the 17 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 27 months); 12 still being built, 8 past the promised date (typically 18 months late). 321 complaints on MahaRERA across 15 projects.
Read Google reviews of Sheth Avalon - Phase 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sheth Avalon - Phase 2: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sheth Avalon - Phase 2
What is the possession date of Sheth Avalon - Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sheth Avalon - Phase 2 in Majiwada, Thane is 30 April 2028 — 24 months later than 30 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Sheth Avalon - Phase 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sheth Avalon - Phase 2's builder has filed on MahaRERA, the official one, is 30 April 2028, already 24 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sheth Avalon - Phase 2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Avalon - Phase 2's builder applied to MahaRERA to extend the completion date once: to 30 December 2027, giving the reason "As per order of the Hon'ble Chairman (MahaRERA) Dated 12/12/2025 we request you kindly to grant us extension till 30/12/2027". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sheth Avalon - Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sheth Avalon - Phase 2 in Majiwada, Thane is P51700015517.
Is Sheth Avalon - Phase 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Avalon - Phase 2 is registered as P51700015517 and its status is "Registered and active".
What is the current construction status of Sheth Avalon - Phase 2? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Avalon - Phase 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 80% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Sheth Avalon - Phase 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sheth Avalon - Phase 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Avalon - Phase 2 is registered on MahaRERA as P51700015517, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sheth Avalon - Phase 2?
Sheth Avalon - Phase 2 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sheth Avalon - Phase 2?
For a flat in Sheth Avalon - Phase 2 (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Sheth Avalon - Phase 2 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Avalon - Phase 2 is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Sheth Avalon - Phase 2 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sheth Avalon - Phase 2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Sheth Avalon - Phase 2 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: SHETH AVALON - PHASE 1 (P51700001729, possession 30 Dec 2021). Check that your agreement names the registration of your own wing.
How can I get updates if Sheth Avalon - Phase 2's possession date changes?
The latest dates are on Sheth Avalon - Phase 2's MahaRERA page (P51700015517). GharKundli's Kundli Watch sends a free WhatsApp update on Sheth Avalon - Phase 2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sheth Avalon - Phase 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Avalon - Phase 2 has 3 buildings filed: TOWER A with 50 floors and 93 units; TOWER B with 49 floors and 92 units; TOWER C with 33 floors and 56 units.
How much parking does Sheth Avalon - Phase 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 506 covered car parking spaces for Sheth Avalon - Phase 2.
How big is the land of Sheth Avalon - Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Avalon - Phase 2 stands on 6,147 sq m of land (about 1.5 acres), with 6,214 sq m of sanctioned built-up area and 1,272 sq m of recreational open space.
What is the track record of Sheth Avalon - Phase 2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Developers (a group of 5 linked companies) has 17 projects on MahaRERA since 2017, this one included. Of the 17 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 27 months); 12 still being built, 8 past the promised date (typically 18 months late). 321 complaints on MahaRERA across 15 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Sheth Avalon - Phase 2?
Google Maps has reviews of Sheth Avalon - Phase 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sheth Avalon - Phase 2?
Sheth Avalon - Phase 2 by Sheth Developers Private Limited is in Majiwada, Thane, pincode 400601 (near Village Panchpakhadi, Thane West, Balkum), Maharashtra, and is registered on MahaRERA as P51700015517, per GharKundli's check of MahaRERA records. Its boundaries filed there include 15 MTR WIDE SERVICE ROAD. Its land is filed as OUT OF SURVEY NO48/1P,2,3,4,5P, 49/2P,4,73/1,2,3,4,5,6,74P,526P. GharKundli lists all 178 MahaRERA projects in Thane (400601).
How many flats are in Sheth Avalon - Phase 2, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Avalon - Phase 2 has 232 homes in 3 towers registered on MahaRERA, and 65% of them are sold or booked.
When was Sheth Avalon - Phase 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Avalon - Phase 2 was registered on MahaRERA on 7 March 2018. GharKundli did not find a title report on the land on file there.
Does Sheth Avalon - Phase 2 have any legal issues or court cases?
No court cases are listed for Sheth Avalon - Phase 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Sheth Avalon - Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sheth Developers Private Limited, which has 9 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sheth Avalon - Phase 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Thane (400601)
- Sheth Vasant Lawns
- Miraya Trinity - Serenity
- Sheth Avalon - Phase 1
- Ashar Pulse
- Madhu Milind Residency
- Riddhi Siddhi Complex
- Neelkanth Heights
Other projects by Sheth Developers Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.