SHETH CNERGY PH 1 - UPTO 11TH FLOOR
by Sheth Developers Private Limited · Panch Pakhadi, ThaneAlso near Naupada, Majiwada, Badlapur
Possession date of SHETH CNERGY PH 1 - UPTO 11TH FLOOR: 28 April 2028, moved from 30 December 2023 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700023047, and currently active. Its completion date has moved from December 2023 to April 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project. 6 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHETH CNERGY PH 1 - UPTO 11TH FLOOR?
How the possession date of SHETH CNERGY PH 1 - UPTO 11TH FLOOR has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EA27092401835)
Reason the builder gave MahaRERA:
“The applicant vide Development Agreement dated 01.10.2003 executed between Voltas Limited and the applicant, acquired rights to develop a land admeasuring aggregating to 1,15,018 sq. mtrs. The Applicant state out of the bigger property the…” Read the full reason
“The applicant vide Development Agreement dated 01.10.2003 executed between Voltas Limited and the applicant, acquired rights to develop a land admeasuring aggregating to 1,15,018 sq. mtrs. The Applicant state out of the bigger property the land bearing Survey No. 35/4A admeasuring 434 sq. mtrs., land bearing Survey No. 35/8 admeasuring 5236.17 sq. mtrs., and land bearing survey no. 35/9/A admeasuring 746.30 sq. mtrs., was affected by Fire Bridget Station and MTRS reservation as per the sanctioned Development Plan for the City of Thane. Thane Municipal Corporation permitted the applicant to…”28 December 2027
Extended at the builder's request (MahaRERA application EXT51700026018)
Reason the builder gave MahaRERA:
“The applicant vide Development Agreement dated 01.10.2003 executed between Voltas Limited and the applicant, registered at the office of sub-registrar Thane at Serial No. TNN1/06589/2003 on 03.10.2003 acquired rights to develop a land admea…” Read the full reason
“The applicant vide Development Agreement dated 01.10.2003 executed between Voltas Limited and the applicant, registered at the office of sub-registrar Thane at Serial No. TNN1/06589/2003 on 03.10.2003 acquired rights to develop a land admeasuring aggregating to 1,15,018 sq. mtrs. The Applicant state out of the bigger property the land bearing Survey No. 35/4A admeasuring 434 sq. mtrs., land bearing Survey No. 35/8 admeasuring 5236.17 sq. mtrs., and land bearing survey no. 35/9/A admeasuring 746.30 sq. mtrs., (Hereinafter referred to as “The entire property”) was affected by Fire Bridget Sta…”28 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SHETH CNERGY PH 1 - UPTO 11TH FLOOR’s extension records on MahaRERA (P51700023047), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHETH CNERGY PH 1 - UPTO 11TH FLOOR
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 6 complaints and 1 court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700023047
- Status
- Registered and active
- Builder
- Sheth Developers Private Limited
- Location
- Panch Pakhadi, Thane · 400601
- Project type
- Commercial
- Registered on
- 18 Nov 2019
- Completion date at registration
- December 2023
- Latest completion date
- April 2028
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 87%
- Towers
- 1
- Complaints on MahaRERA
- 6
- Court cases listed
- 1
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 9
Construction progress of SHETH CNERGY PH 1 - UPTO 11TH FLOOR, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHETH CNERGY | 100% | 52% | 5% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SHETH CNERGY: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHETH CNERGY PH 1 - UPTO 11TH FLOOR every month.
SHETH CNERGY PH 1 - UPTO 11TH FLOOR: buildings, flats and land, as filed on MahaRERA
- Buildings: SHETH CNERGY (7 floors, 173 units)
- Car parking: 353 covered
- Land: 6,416 sq m (about 1.6 acres) · sanctioned built-up 7,894 sq m · recreational space 1,283 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Sheth Developers (a group of 4 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 27 months); 9 still being built, 6 past the promised date (typically 21 months late). 295 complaints on MahaRERA across 11 projects.
Read Google reviews of SHETH CNERGY PH 1 - UPTO 11TH FLOOR →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHETH CNERGY PH 1 - UPTO 11TH FLOOR: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHETH CNERGY PH 1 - UPTO 11TH FLOOR
What is the possession date of SHETH CNERGY PH 1 - UPTO 11TH FLOOR?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHETH CNERGY PH 1 - UPTO 11TH FLOOR in Panch Pakhadi, Thane is 28 April 2028 — 48 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SHETH CNERGY PH 1 - UPTO 11TH FLOOR?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHETH CNERGY PH 1 - UPTO 11TH FLOOR's builder has filed on MahaRERA, the official one, is 28 April 2028, already 48 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHETH CNERGY PH 1 - UPTO 11TH FLOOR extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHETH CNERGY PH 1 - UPTO 11TH FLOOR's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2024, giving the reason "The applicant vide Development Agreement dated 01.10.2003 executed between Voltas Limited and the applicant, acquired rights to develop a land admeasuring aggregating to 1,15,018 sq. mtrs. The Applicant state out of the bigger property the land bearing Survey No. 35/4A admeasuring 434 sq. mtrs., land bearing Survey No. 35/8 admeasuring 5236.17 sq. mtrs., and land bearing survey no. 35/9/A admeasuring 746.30 sq. mtrs., was affected by Fire Bridget Station and MTRS reservation as per the sanctioned Development Plan for the City of Thane. Thane Municipal Corporation permitted the applicant to…"; to 28 December 2027, giving the reason "The applicant vide Development Agreement dated 01.10.2003 executed between Voltas Limited and the applicant, registered at the office of sub-registrar Thane at Serial No. TNN1/06589/2003 on 03.10.2003 acquired rights to develop a land admeasuring aggregating to 1,15,018 sq. mtrs. The Applicant state out of the bigger property the land bearing Survey No. 35/4A admeasuring 434 sq. mtrs., land bearing Survey No. 35/8 admeasuring 5236.17 sq. mtrs., and land bearing survey no. 35/9/A admeasuring 746.30 sq. mtrs., (Hereinafter referred to as “The entire property”) was affected by Fire Bridget Sta…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SHETH CNERGY PH 1 - UPTO 11TH FLOOR?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHETH CNERGY PH 1 - UPTO 11TH FLOOR in Panch Pakhadi, Thane is P51700023047.
Is SHETH CNERGY PH 1 - UPTO 11TH FLOOR registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHETH CNERGY PH 1 - UPTO 11TH FLOOR is registered as P51700023047 and its status is "Registered and active".
What is the construction status of SHETH CNERGY PH 1 - UPTO 11TH FLOOR?
According to GharKundli's check of MahaRERA records (updated October 2026), SHETH CNERGY PH 1 - UPTO 11TH FLOOR's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHETH CNERGY is 52% done and internal work 5%. GharKundli's full report compares construction progress with the deadline.
Does SHETH CNERGY PH 1 - UPTO 11TH FLOOR have complaints on MahaRERA?
6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SHETH CNERGY PH 1 - UPTO 11TH FLOOR safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHETH CNERGY PH 1 - UPTO 11TH FLOOR is registered on MahaRERA as P51700023047, its completion date has moved 48 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHETH CNERGY PH 1 - UPTO 11TH FLOOR's possession date changes?
The latest dates are on SHETH CNERGY PH 1 - UPTO 11TH FLOOR's MahaRERA page (P51700023047). GharKundli's Kundli Watch sends a free WhatsApp update on SHETH CNERGY PH 1 - UPTO 11TH FLOOR every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHETH CNERGY PH 1 - UPTO 11TH FLOOR have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHETH CNERGY PH 1 - UPTO 11TH FLOOR has one building filed: SHETH CNERGY with 7 floors and 173 units.
How much parking does SHETH CNERGY PH 1 - UPTO 11TH FLOOR have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 353 covered car parking spaces for SHETH CNERGY PH 1 - UPTO 11TH FLOOR.
How big is the land of SHETH CNERGY PH 1 - UPTO 11TH FLOOR?
According to GharKundli's check of MahaRERA records (updated October 2026), SHETH CNERGY PH 1 - UPTO 11TH FLOOR stands on 6,416 sq m of land (about 1.6 acres), with 7,894 sq m of sanctioned built-up area and 1,283 sq m of recreational open space.
What is the track record of SHETH CNERGY PH 1 - UPTO 11TH FLOOR's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sheth Developers (a group of 4 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 27 months); 9 still being built, 6 past the promised date (typically 21 months late). 295 complaints on MahaRERA across 11 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHETH CNERGY PH 1 - UPTO 11TH FLOOR?
Google Maps has reviews of SHETH CNERGY PH 1 - UPTO 11TH FLOOR written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHETH CNERGY PH 1 - UPTO 11TH FLOOR?
SHETH CNERGY PH 1 - UPTO 11TH FLOOR by Sheth Developers Private Limited is in Panch Pakhadi, Thane (pincode 400601), near Naupada, Majiwada, Badlapur, Maharashtra, and is registered on MahaRERA as P51700023047, per GharKundli's check of MahaRERA records.
How many homes are in SHETH CNERGY PH 1 - UPTO 11TH FLOOR?
According to GharKundli's check of MahaRERA records (updated October 2026), SHETH CNERGY PH 1 - UPTO 11TH FLOOR has 0 homes in 1 tower registered on MahaRERA, and 87% of them are sold or booked.
When was SHETH CNERGY PH 1 - UPTO 11TH FLOOR registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHETH CNERGY PH 1 - UPTO 11TH FLOOR was registered on MahaRERA on 18 November 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on SHETH CNERGY PH 1 - UPTO 11TH FLOOR?
1 court case is listed for SHETH CNERGY PH 1 - UPTO 11TH FLOOR on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SHETH CNERGY PH 1 - UPTO 11TH FLOOR?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sheth Developers Private Limited, which has 9 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SHETH CNERGY PH 1 - UPTO 11TH FLOOR
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Thane
- LARKINS 315 FIO-A
- Veer Square (Thane)
- RAJ TATTVA PHASE 1 COMMERCIAL
- MAULI KRUPA
- GURUKRUPA NITYAM
- Panache
- LOTUS
- ASAVARI CO OP HSG SOC LTD
Other projects by Sheth Developers Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.