VICTORY DIVINE
by YASHODANAND REALTORS · Borivali West, MumbaiAlso near Malad West, Malad East, Goregaon West
Possession date of VICTORY DIVINE: 30 April 2027, moved from 30 September 2020 (75 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800008313, and currently active. Its completion date has moved from September 2020 to April 2027: 75 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about VICTORY DIVINE?
How the possession date of VICTORY DIVINE has moved
30 September 2020
Completion date given when the project was registered
31 October 2024
Extended at the builder's request (MahaRERA application EXT51800012937)
Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/10/2024”
31 December 2026
Extended at the builder's request (MahaRERA application EXT51800025193)
Reason the builder gave MahaRERA:
“This is to inform you that our project name Victory Divine located at TSP, N. B. Cross Road, Malad (W), Somwari Bazar, Mumbai 400 064 Bearing Rera No P51800008313 is delayed due to some dispute with the society, they had filed case before t…” Read the full reason
“This is to inform you that our project name Victory Divine located at TSP, N. B. Cross Road, Malad (W), Somwari Bazar, Mumbai 400 064 Bearing Rera No P51800008313 is delayed due to some dispute with the society, they had filed case before the Hon'ble High Court and now all the disputed have been resolved and we are amicably moving forward to complete the project”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: VICTORY DIVINE’s extension records on MahaRERA (P51800008313), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VICTORY DIVINE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800008313
- Status
- Registered and active
- Builder
- YASHODANAND REALTORS
- Location
- Borivali West, Mumbai · 400064
- Project type
- Residential / Group Housing
- Registered on
- 18 Aug 2017
- Completion date at registration
- September 2020
- Latest completion date
- April 2027
- Delay so far
- 75 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 50
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of VICTORY DIVINE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MATANGI NIWAS | 100% | 35% | 4% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VICTORY DIVINE every month.
VICTORY DIVINE: buildings, flats and land, as filed on MahaRERA
- Buildings: MATANGI NIWAS (15 floors)
- Land: 843 sq m (about 0.2 acres) · sanctioned built-up 2,272 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of VICTORY DIVINE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VICTORY DIVINE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VICTORY DIVINE
What is the possession date of VICTORY DIVINE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VICTORY DIVINE in Borivali West, Mumbai is 30 April 2027 — 75 months later than 30 September 2020, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for VICTORY DIVINE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VICTORY DIVINE's builder has filed on MahaRERA, the official one, is 30 April 2027, already 75 months later than the 30 September 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of VICTORY DIVINE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), VICTORY DIVINE's builder applied to MahaRERA to extend the completion date 2 times: to 31 October 2024, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/10/2024"; to 31 December 2026, giving the reason "This is to inform you that our project name Victory Divine located at TSP, N. B. Cross Road, Malad (W), Somwari Bazar, Mumbai 400 064 Bearing Rera No P51800008313 is delayed due to some dispute with the society, they had filed case before the Hon'ble High Court and now all the disputed have been resolved and we are amicably moving forward to complete the project". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of VICTORY DIVINE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VICTORY DIVINE in Borivali West, Mumbai is P51800008313.
Is VICTORY DIVINE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VICTORY DIVINE is registered as P51800008313 and its status is "Registered and active".
What is the construction status of VICTORY DIVINE?
According to GharKundli's check of MahaRERA records (updated October 2026), VICTORY DIVINE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MATANGI NIWAS is 35% done and internal work 4%. GharKundli's full report compares construction progress with the deadline.
Does VICTORY DIVINE have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is VICTORY DIVINE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), VICTORY DIVINE is registered on MahaRERA as P51800008313, its completion date has moved 75 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VICTORY DIVINE's possession date changes?
The latest dates are on VICTORY DIVINE's MahaRERA page (P51800008313). GharKundli's Kundli Watch sends a free WhatsApp update on VICTORY DIVINE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VICTORY DIVINE have?
According to GharKundli's check of MahaRERA records (updated October 2026), VICTORY DIVINE has one building filed: MATANGI NIWAS with 15 floors.
How big is the land of VICTORY DIVINE?
According to GharKundli's check of MahaRERA records (updated October 2026), VICTORY DIVINE stands on 843 sq m of land (about 0.2 acres), with 2,272 sq m of sanctioned built-up area.
Where can I read reviews of VICTORY DIVINE?
Google Maps has reviews of VICTORY DIVINE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VICTORY DIVINE?
VICTORY DIVINE by YASHODANAND REALTORS is in Borivali West, Mumbai (pincode 400064), near Malad West, Malad East, Goregaon West, Maharashtra, and is registered on MahaRERA as P51800008313, per GharKundli's check of MahaRERA records.
How many homes are in VICTORY DIVINE?
According to GharKundli's check of MahaRERA records (updated October 2026), VICTORY DIVINE has 50 homes in 1 tower registered on MahaRERA.
When was VICTORY DIVINE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VICTORY DIVINE was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on VICTORY DIVINE?
No court cases are listed for VICTORY DIVINE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of VICTORY DIVINE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is YASHODANAND REALTORS.
Check it yourself on MahaRERA
- How to check the possession date of VICTORY DIVINE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Borivali West
- I SPACE URBAN VISTA
- LEGACY
- SKYLARK HEIGHTS
- RAJHANS
- AVYUKTA PARIJAT
- RITE DEVANGI
- GAUTAM PRABHU
- BORIVALI MADHUMAS CHSL
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.