Skip to content
GharKundli

Treeline 6

by Luxora Infrastructure Private Limited · Mauza, NagpurAlso near Pipla

Possession date of Treeline 6: 30 April 2032, moved from 31 December 2019 (144 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500011412, and currently active. Its completion date has moved from December 2019 to April 2032: 144 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Treeline 6?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Treeline 6 has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 September 2024

    Extended at the builder's request (MahaRERA application EXT50500008901)

    Reason the builder gave MahaRERA:
    “Due to the fact that a new 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications were successfully rec…” Read the full reason“Due to the fact that a new 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications were successfully received on the same.”
  3. 31 December 2031

    Extended at the builder's request (MahaRERA application EA07052620870)

    Reason the builder gave MahaRERA:
    “Sir/Madam, We, LUXORA INFRASTRUCTURE PRIVATE LIMITED, Promoter of the real estate project “TREELINE 6”, bearing MahaRERA Registration No. P50500011412, hereby submit this application seeking an extension up to 31/12/2031 for completion of t…” Read the full reason“Sir/Madam, We, LUXORA INFRASTRUCTURE PRIVATE LIMITED, Promoter of the real estate project “TREELINE 6”, bearing MahaRERA Registration No. P50500011412, hereby submit this application seeking an extension up to 31/12/2031 for completion of the said project. The delay in completion has occurred due to prolonged and unavoidable factors beyond the control of the Promoter, including delay in statutory approvals and revalidations, market slowdown and financial constraints, delay in development of external infrastructure, escalation in construction costs, labour shortages, regulatory changes requi…”
  4. 30 April 2032

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Treeline 6’s extension records on MahaRERA (P50500011412), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Treeline 6

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2032 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P50500011412
Status
Registered and active
Builder
Luxora Infrastructure Private Limited
Location
Mauza, Nagpur · 440034
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
December 2019
Latest completion date
April 2032
Delay so far
144 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
48
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
22

Construction progress of Treeline 6, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Treeline 6100%59%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Treeline 6: covers 5 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Treeline 6 every month.

Treeline 6: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Luxora Infrastructure (a group of 2 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 57 months); 12 still being built, 8 past the promised date (typically 78 months late); 2 lapsed. 17 complaints on MahaRERA across 6 projects.

Read Google reviews of Treeline 6 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Treeline 6: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Treeline 6

What is the possession date of Treeline 6?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Treeline 6 in Mauza, Nagpur is 30 April 2032 — 144 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Treeline 6?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Treeline 6's builder has filed on MahaRERA, the official one, is 30 April 2032, already 144 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Treeline 6 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Treeline 6's builder applied to MahaRERA to extend the completion date 2 times: to 30 September 2024, giving the reason "Due to the fact that a new 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications were successfully received on the same."; to 31 December 2031, giving the reason "Sir/Madam, We, LUXORA INFRASTRUCTURE PRIVATE LIMITED, Promoter of the real estate project “TREELINE 6”, bearing MahaRERA Registration No. P50500011412, hereby submit this application seeking an extension up to 31/12/2031 for completion of the said project. The delay in completion has occurred due to prolonged and unavoidable factors beyond the control of the Promoter, including delay in statutory approvals and revalidations, market slowdown and financial constraints, delay in development of external infrastructure, escalation in construction costs, labour shortages, regulatory changes requi…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Treeline 6?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Treeline 6 in Mauza, Nagpur is P50500011412.

Is Treeline 6 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Treeline 6 is registered as P50500011412 and its status is "Registered and active".

What is the construction status of Treeline 6?

According to GharKundli's check of MahaRERA records (updated October 2026), Treeline 6's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Treeline 6 is 59% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Treeline 6 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Treeline 6 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Treeline 6 is registered on MahaRERA as P50500011412, its completion date has moved 144 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Treeline 6 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Treeline 5 (P50500002936). Check that your agreement names the registration of your own wing.

How can I get updates if Treeline 6's possession date changes?

The latest dates are on Treeline 6's MahaRERA page (P50500011412). GharKundli's Kundli Watch sends a free WhatsApp update on Treeline 6 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Treeline 6 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Treeline 6 has one building filed: Treeline 6 with 5 floors and 48 units.

How much parking does Treeline 6 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 54 covered car parking spaces for Treeline 6.

How big is the land of Treeline 6?

According to GharKundli's check of MahaRERA records (updated October 2026), Treeline 6 stands on 6,105 sq m of land (about 1.5 acres), with 7,096 sq m of sanctioned built-up area.

What is the track record of Treeline 6's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Luxora Infrastructure (a group of 2 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 57 months); 12 still being built, 8 past the promised date (typically 78 months late); 2 lapsed. 17 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Treeline 6?

Google Maps has reviews of Treeline 6 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Treeline 6?

Treeline 6 by Luxora Infrastructure Private Limited is in Mauza, Nagpur (pincode 440034), near Pipla, Maharashtra, and is registered on MahaRERA as P50500011412, per GharKundli's check of MahaRERA records.

How many homes are in Treeline 6?

According to GharKundli's check of MahaRERA records (updated October 2026), Treeline 6 has 48 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Treeline 6 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Treeline 6 was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Treeline 6?

No court cases are listed for Treeline 6 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Treeline 6?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Luxora Infrastructure Private Limited, which has 22 other projects registered on MahaRERA.

Other projects in Mauza

All 122 projects in Mhalginagar (440034) →

Other projects by Luxora Infrastructure Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.