by Luxora Infrastructure Private Limited · Mauza, NagpurAlso near Pipla
Possession date of Park House Holistic: 30 April 2027, moved from 31 December 2019 (84 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500011398, and currently active. Its completion date has moved from December 2019 to April 2027: 84 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Park House Holistic?
How the possession date of Park House Holistic has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT50500005658)
Reason the builder gave MahaRERA:
“Due to the fact that a new 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications were successfully rec…” Read the full reason
“Due to the fact that a new 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications were successfully received on the same.”31 December 2025
Extended at the builder's request (MahaRERA application EXT50500016746)
Reason the builder gave MahaRERA:
“Due to the fact that a new 18 m wide DP road was proposed by NMC in the regional plan which directly affected the project after the start of the construction, construction was delayed until clarifications were succesfully received on the sa…” Read the full reason
“Due to the fact that a new 18 m wide DP road was proposed by NMC in the regional plan which directly affected the project after the start of the construction, construction was delayed until clarifications were succesfully received on the same. The new project completion date will be 31st Dec 2025 as we would like to apply via section 7(3) with customer consent.”30 December 2026
Extended at the builder's request (MahaRERA application EA04032620078)
Reason the builder gave MahaRERA:
“We, LUXORA INFRASTRUCTURE PRIVATE LIMITED, Promoter of the real estate project “PARK HOUSE HOLISTIC”, bearing MahaRERA Registration No. P50500011398, hereby submit this application seeking an extension of Twelve (12) months for completion o…” Read the full reason
“We, LUXORA INFRASTRUCTURE PRIVATE LIMITED, Promoter of the real estate project “PARK HOUSE HOLISTIC”, bearing MahaRERA Registration No. P50500011398, hereby submit this application seeking an extension of Twelve (12) months for completion of the said project. We respectfully submit that the delay in completion of the project has occurred due to circumstances beyond the control of the promoter. The progress of the project was impacted due to delays in obtaining statutory approvals and revalidations, fluctuations in the real estate market affecting sales and cash flow, and delay in developmen…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Park House Holistic’s extension records on MahaRERA (P50500011398), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Park House Holistic
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500011398
- Status
- Registered and active
- Builder
- Luxora Infrastructure Private Limited
- Location
- Mauza, Nagpur · 440034
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- April 2027
- Delay so far
- 84 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 16
- Sold or booked
- 75%
- Towers
- 16
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 22
Construction progress of Park House Holistic, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Park House Holistic Row House No. 13 | 100% | 100% | 49% | 93% |
| Park House Holistic Row House No. 14 | 100% | 100% | 49% | 93% |
| Park House Holistic Row House No. 15 | 100% | 100% | 100% | 100% |
| Park House Holistic Row House No. 16 | 100% | 100% | 49% | 93% |
| Park House Holistic Row House No. 17 | 100% | 100% | 100% | 100% |
| Park House Holistic Row House No. 18 | 100% | 100% | 100% | 100% |
| Park House Holistic Row House No. 19 | 100% | 100% | 100% | 100% |
| Park House Holistic Row House No. 20 | 100% | 100% | 100% | 100% |
| Park House Holistic Row House No. 21 | 100% | 100% | 100% | 100% |
| Park House Holistic Row House No. 22 | 100% | 100% | 100% | 100% |
| Park House Holistic Row House No. 23 | 100% | 100% | 100% | 100% |
| Park House Holistic Row House No. 24 | 100% | 100% | 100% | 100% |
| Park House Holistic Row House No. 25 | 100% | 100% | 100% | 100% |
| Park House Holistic Row House No. 26 | 100% | 100% | 49% | 93% |
| Park House Holistic Row House No. 27 | 100% | 100% | 49% | 93% |
| Park House Holistic Row House No 12 | 100% | 100% | 49% | 93% |
Commencement certificate (CC), as filed on MahaRERA
- Park House Holistic Row House No. 13: covers 2 floors
- Park House Holistic Row House No. 14: covers 2 floors
- Park House Holistic Row House No. 15: covers 2 floors
- Park House Holistic Row House No. 16: covers 2 floors
- Park House Holistic Row House No. 17: covers 2 floors
- Park House Holistic Row House No. 18: covers 2 floors
- Park House Holistic Row House No. 19: covers 2 floors
- Park House Holistic Row House No. 20: covers 2 floors
- Park House Holistic Row House No. 21: covers 2 floors
- Park House Holistic Row House No. 22: covers 2 floors
- Park House Holistic Row House No. 23: covers 2 floors
- Park House Holistic Row House No. 24: covers 2 floors
- Park House Holistic Row House No. 25: covers 2 floors
- Park House Holistic Row House No. 26: covers 2 floors
- Park House Holistic Row House No. 27: covers 2 floors
- Park House Holistic Row House No 12: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Park House Holistic every month.
Park House Holistic: buildings, flats and land, as filed on MahaRERA
- Buildings: Park House Holistic Row House No. 13 (2 floors, 1 units) · Park House Holistic Row House No. 14 (2 floors, 1 units) · Park House Holistic Row House No. 15 (2 floors, 1 units) · Park House Holistic Row House No. 16 (2 floors, 1 units) · Park House Holistic Row House No. 17 (2 floors, 1 units) · Park House Holistic Row House No. 18 (2 floors, 1 units) · Park House Holistic Row House No. 19 (2 floors, 1 units) · Park House Holistic Row House No. 20 (2 floors, 1 units) · and 8 more
- Land: 5,324 sq m (about 1.3 acres) · sanctioned built-up 3,347 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Luxora Infrastructure (a group of 2 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 57 months); 12 still being built, 8 past the promised date (typically 78 months late); 2 lapsed. 17 complaints on MahaRERA across 6 projects.
Read Google reviews of Park House Holistic →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Park House Holistic: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Park House Holistic
What is the possession date of Park House Holistic?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Park House Holistic in Mauza, Nagpur is 30 April 2027 — 84 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Park House Holistic?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Park House Holistic's builder has filed on MahaRERA, the official one, is 30 April 2027, already 84 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Park House Holistic extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Park House Holistic's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2020, giving the reason "Due to the fact that a new 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications were successfully received on the same."; to 31 December 2025, giving the reason "Due to the fact that a new 18 m wide DP road was proposed by NMC in the regional plan which directly affected the project after the start of the construction, construction was delayed until clarifications were succesfully received on the same. The new project completion date will be 31st Dec 2025 as we would like to apply via section 7(3) with customer consent."; to 30 December 2026, giving the reason "We, LUXORA INFRASTRUCTURE PRIVATE LIMITED, Promoter of the real estate project “PARK HOUSE HOLISTIC”, bearing MahaRERA Registration No. P50500011398, hereby submit this application seeking an extension of Twelve (12) months for completion of the said project. We respectfully submit that the delay in completion of the project has occurred due to circumstances beyond the control of the promoter. The progress of the project was impacted due to delays in obtaining statutory approvals and revalidations, fluctuations in the real estate market affecting sales and cash flow, and delay in developmen…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Park House Holistic?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Park House Holistic in Mauza, Nagpur is P50500011398.
Is Park House Holistic registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Park House Holistic is registered as P50500011398 and its status is "Registered and active".
What is the construction status of Park House Holistic?
According to GharKundli's check of MahaRERA records (updated October 2026), Park House Holistic's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 16 towers. GharKundli's full report compares construction progress with the deadline.
Does Park House Holistic have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Park House Holistic safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Park House Holistic is registered on MahaRERA as P50500011398, its completion date has moved 84 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Park House Holistic's possession date changes?
The latest dates are on Park House Holistic's MahaRERA page (P50500011398). GharKundli's Kundli Watch sends a free WhatsApp update on Park House Holistic every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Park House Holistic have?
According to GharKundli's check of MahaRERA records (updated October 2026), Park House Holistic has 16 buildings filed: Park House Holistic Row House No. 13 with 2 floors and 1 units; Park House Holistic Row House No. 14 with 2 floors and 1 units; Park House Holistic Row House No. 15 with 2 floors and 1 units; Park House Holistic Row House No. 16 with 2 floors and 1 units; Park House Holistic Row House No. 17 with 2 floors and 1 units; Park House Holistic Row House No. 18 with 2 floors and 1 units; and 10 more.
How big is the land of Park House Holistic?
According to GharKundli's check of MahaRERA records (updated October 2026), Park House Holistic stands on 5,324 sq m of land (about 1.3 acres), with 3,347 sq m of sanctioned built-up area.
What is the track record of Park House Holistic's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Luxora Infrastructure (a group of 2 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 57 months); 12 still being built, 8 past the promised date (typically 78 months late); 2 lapsed. 17 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Park House Holistic?
Google Maps has reviews of Park House Holistic written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Park House Holistic?
Park House Holistic by Luxora Infrastructure Private Limited is in Mauza, Nagpur (pincode 440034), near Pipla, Maharashtra, and is registered on MahaRERA as P50500011398, per GharKundli's check of MahaRERA records.
How many homes are in Park House Holistic?
According to GharKundli's check of MahaRERA records (updated October 2026), Park House Holistic has 16 homes in 16 towers registered on MahaRERA, and 75% of them are sold or booked.
When was Park House Holistic registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Park House Holistic was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Park House Holistic?
No court cases are listed for Park House Holistic on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Park House Holistic?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Luxora Infrastructure Private Limited, which has 22 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Park House Holistic
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nagpur →
Other projects in Mauza
- Park House Tranquil
- Park Mansion 52
- Park Mansion 54
- Park Mansion 48
- Treeline 6
- Springfield
- Diamondleaf
- Vista 3B
Other projects by Luxora Infrastructure Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.