by Luxora Infrastructure Private Limited · Mauza, Nagpur
Possession date of Vista 3B: 30 April 2027, moved from 30 December 2021 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500003509, and currently active. Its completion date has moved from December 2021 to April 2027: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Vista 3B?
How the possession date of Vista 3B has moved
30 December 2021
Completion date given when the project was registered
30 December 2022
Extended at the builder's request (MahaRERA application EXT50500011818)
Reason the builder gave MahaRERA:
“Due to the fact that a new 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications were successfully rec…” Read the full reason
“Due to the fact that a new 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications were successfully received on the same.”31 December 2026
Extended at the builder's request (MahaRERA application EXT50500017716)
Reason the builder gave MahaRERA:
“Due to the fact that an 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications and amendments were rece…” Read the full reason
“Due to the fact that an 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications and amendments were received on the same.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Vista 3B’s extension records on MahaRERA (P50500003509), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vista 3B
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- MahaRERA registration
- P50500003509
- Status
- Registered and active
- Builder
- Luxora Infrastructure Private Limited
- Location
- Mauza, Nagpur · 440034
- Project type
- Residential / Group Housing
- Registered on
- 5 Aug 2017
- Completion date at registration
- December 2021
- Latest completion date
- April 2027
- Delay so far
- 60 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 84
- Sold or booked
- 5%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 22
Construction progress of Vista 3B, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Vista 3B | 57% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Vista 3B: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vista 3B every month.
Vista 3B: buildings, flats and land, as filed on MahaRERA
- Buildings: Vista 3B (8 floors, 84 units)
- Car parking: 6 covered
- Land: 3,558 sq m (about 0.9 acres) · sanctioned built-up 7,693 sq m
The builder’s record and reviews
Luxora Infrastructure (a group of 2 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 57 months); 12 still being built, 8 past the promised date (typically 78 months late); 2 lapsed. 17 complaints on MahaRERA across 6 projects.
Read Google reviews of Vista 3B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vista 3B: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Vista 3B
What is the possession date of Vista 3B?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vista 3B in Mauza, Nagpur is 30 April 2027 — 60 months later than 30 December 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Vista 3B?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vista 3B's builder has filed on MahaRERA, the official one, is 30 April 2027, already 60 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vista 3B extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Vista 3B's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2022, giving the reason "Due to the fact that a new 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications were successfully received on the same."; to 31 December 2026, giving the reason "Due to the fact that an 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications and amendments were received on the same.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Vista 3B?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vista 3B in Mauza, Nagpur is P50500003509.
Is Vista 3B registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vista 3B is registered as P50500003509 and its status is "Registered and active".
What is the construction status of Vista 3B?
According to GharKundli's check of MahaRERA records (updated October 2026), Vista 3B's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Vista 3B is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Vista 3B have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Vista 3B safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vista 3B is registered on MahaRERA as P50500003509, its completion date has moved 60 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Vista 3B have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Vista 3A (P50500032662, possession 31 Dec 2025); Vista 3C (P50500007884, possession 30 Jun 2024). Check that your agreement names the registration of your own wing.
How can I get updates if Vista 3B's possession date changes?
The latest dates are on Vista 3B's MahaRERA page (P50500003509). GharKundli's Kundli Watch sends a free WhatsApp update on Vista 3B every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vista 3B have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vista 3B has one building filed: Vista 3B with 8 floors and 84 units.
How much parking does Vista 3B have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 6 covered car parking spaces for Vista 3B.
How big is the land of Vista 3B?
According to GharKundli's check of MahaRERA records (updated October 2026), Vista 3B stands on 3,558 sq m of land (about 0.9 acres), with 7,693 sq m of sanctioned built-up area.
What is the track record of Vista 3B's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Luxora Infrastructure (a group of 2 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 57 months); 12 still being built, 8 past the promised date (typically 78 months late); 2 lapsed. 17 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Vista 3B?
Google Maps has reviews of Vista 3B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Vista 3B?
Vista 3B by Luxora Infrastructure Private Limited is in Mauza, Nagpur (pincode 440034), Maharashtra, and is registered on MahaRERA as P50500003509, per GharKundli's check of MahaRERA records.
How many homes are in Vista 3B?
According to GharKundli's check of MahaRERA records (updated October 2026), Vista 3B has 84 homes in 1 tower registered on MahaRERA, and 5% of them are sold or booked.
When was Vista 3B registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vista 3B was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Vista 3B?
No court cases are listed for Vista 3B on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Vista 3B?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Luxora Infrastructure Private Limited, which has 22 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Vista 3B
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nagpur →
Other projects in Mauza
- Park House Tranquil
- Park Mansion 54
- Park Mansion 52
- Treeline 6
- Park Mansion 48
- Park House Holistic
- Springfield
- Diamondleaf
Other projects by Luxora Infrastructure Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.