Possession date of Park Mansion 48: 30 April 2029, moved from 31 December 2018 (120 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500004854, and currently active. Its completion date has moved from December 2018 to April 2029: 120 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Park Mansion 48?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Park Mansion 48 has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT50500017146)

    Reason the builder gave MahaRERA:
    “Due to the fact that a new 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications were successfully rec…” Read the full reason“Due to the fact that a new 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications were successfully received on the same.”
  3. 30 November 2025

    Extended at the builder's request (MahaRERA application EXT50500027092)

    Reason the builder gave MahaRERA: “This project is a single Villa with a single Allottee. Due to design changes required by customer and change in approval authority, there has been delay in procuring sanctioned plans and also in completion of the project.”
  4. 31 December 2028

    Extended at the builder's request (MahaRERA application EA15052620985)

    Reason the builder gave MahaRERA:
    “We, LUXORA INFRASTRUCTURE PRIVATE LIMITED, Promoter of the real estate project “Park Mansion 48”, bearing MahaRERA Registration No. P50500004854, hereby submit this application seeking an extension up to 31/12/2028 for completion of the sai…” Read the full reason“We, LUXORA INFRASTRUCTURE PRIVATE LIMITED, Promoter of the real estate project “Park Mansion 48”, bearing MahaRERA Registration No. P50500004854, hereby submit this application seeking an extension up to 31/12/2028 for completion of the said project. We respectfully submit that the delay in completion of the project has occurred due to prolonged and cumulative circumstances beyond the control of the promoter. The project has been affected by delays in obtaining statutory approvals, revalidations, and permissions from competent authorities, along with a sustained slowdown in the real estate…”
  5. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Park Mansion 48’s extension records on MahaRERA (P50500004854), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Park Mansion 48

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P50500004854
Status
Registered and active
Builder
Luxora Infrastructure Private Limited
Location
Mauza, Nagpur · 440034
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
December 2018
Latest completion date
April 2029
Delay so far
120 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
1
Sold or booked
100%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
22

Construction progress of Park Mansion 48, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Park Mansion 48100%43%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Park Mansion 48: covers 2 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Park Mansion 48 every month.

Park Mansion 48: buildings, flats and land, as filed on MahaRERA

  • Buildings: Park Mansion 48 (2 floors, 1 units)
  • Car parking: 1 covered
  • Land: 697 sq m (about 0.2 acres) · sanctioned built-up 303 sq m

The builder’s record and reviews

Luxora Infrastructure (a group of 2 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 57 months); 12 still being built, 8 past the promised date (typically 78 months late); 2 lapsed. 17 complaints on MahaRERA across 6 projects.

Read Google reviews of Park Mansion 48 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Park Mansion 48: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Park Mansion 48

What is the possession date of Park Mansion 48?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Park Mansion 48 in Mauza, Nagpur is 30 April 2029 — 120 months later than 31 December 2018, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Park Mansion 48?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Park Mansion 48's builder has filed on MahaRERA, the official one, is 30 April 2029, already 120 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Park Mansion 48 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Park Mansion 48's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2024, giving the reason "Due to the fact that a new 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications were successfully received on the same."; to 30 November 2025, giving the reason "This project is a single Villa with a single Allottee. Due to design changes required by customer and change in approval authority, there has been delay in procuring sanctioned plans and also in completion of the project."; to 31 December 2028, giving the reason "We, LUXORA INFRASTRUCTURE PRIVATE LIMITED, Promoter of the real estate project “Park Mansion 48”, bearing MahaRERA Registration No. P50500004854, hereby submit this application seeking an extension up to 31/12/2028 for completion of the said project. We respectfully submit that the delay in completion of the project has occurred due to prolonged and cumulative circumstances beyond the control of the promoter. The project has been affected by delays in obtaining statutory approvals, revalidations, and permissions from competent authorities, along with a sustained slowdown in the real estate…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Park Mansion 48?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Park Mansion 48 in Mauza, Nagpur is P50500004854.

Is Park Mansion 48 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Park Mansion 48 is registered as P50500004854 and its status is "Registered and active".

What is the construction status of Park Mansion 48?

According to GharKundli's check of MahaRERA records (updated October 2026), Park Mansion 48's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Park Mansion 48 is 43% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Park Mansion 48 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Park Mansion 48 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Park Mansion 48 is registered on MahaRERA as P50500004854, its completion date has moved 120 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Park Mansion 48 have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Park Mansion 52 (P50500019484, possession 31 Dec 2026); Park Mansion 54 (P50500010626, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.

How can I get updates if Park Mansion 48's possession date changes?

The latest dates are on Park Mansion 48's MahaRERA page (P50500004854). GharKundli's Kundli Watch sends a free WhatsApp update on Park Mansion 48 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Park Mansion 48 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Park Mansion 48 has one building filed: Park Mansion 48 with 2 floors and 1 units.

How much parking does Park Mansion 48 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for Park Mansion 48.

How big is the land of Park Mansion 48?

According to GharKundli's check of MahaRERA records (updated October 2026), Park Mansion 48 stands on 697 sq m of land (about 0.2 acres), with 303 sq m of sanctioned built-up area.

What is the track record of Park Mansion 48's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Luxora Infrastructure (a group of 2 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 57 months); 12 still being built, 8 past the promised date (typically 78 months late); 2 lapsed. 17 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Park Mansion 48?

Google Maps has reviews of Park Mansion 48 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Park Mansion 48?

Park Mansion 48 by Luxora Infrastructure Private Limited is in Mauza, Nagpur (pincode 440034), Maharashtra, and is registered on MahaRERA as P50500004854, per GharKundli's check of MahaRERA records.

How many homes are in Park Mansion 48?

According to GharKundli's check of MahaRERA records (updated October 2026), Park Mansion 48 has 1 home in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was Park Mansion 48 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Park Mansion 48 was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Park Mansion 48?

No court cases are listed for Park Mansion 48 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Park Mansion 48?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Luxora Infrastructure Private Limited, which has 22 other projects registered on MahaRERA.

All projects with possession due in 2029 in Nagpur →

Other projects in Mauza

All 122 projects in Mhalginagar (440034) →

Other projects by Luxora Infrastructure Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.