Park Mansion 54
by Luxora Infrastructure Private Limited · Mauza, NagpurAlso near Besa, Pipla
Possession date of Park Mansion 54: 30 April 2027, moved from 31 March 2018 (105 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500010626, and currently active. Its completion date has moved from March 2018 to April 2027: 105 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Park Mansion 54?
How the possession date of Park Mansion 54 has moved
31 March 2018
Completion date given when the project was registered
30 June 2023
Extended at the builder's request (MahaRERA application EXT50500000745)
Reason the builder gave MahaRERA:
“Due to the fact that a new 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications were successfully rec…” Read the full reason
“Due to the fact that a new 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications were successfully received on the same.”30 June 2024
Extended at the builder's request (MahaRERA application EXT50500018214)
Reason the builder gave MahaRERA:
“Due to the fact that a new 18 m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications and amendments were…” Read the full reason
“Due to the fact that a new 18 m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications and amendments were successfully received on the same.”30 November 2025
Extended at the builder's request (MahaRERA application EXT50500025415)
Reason the builder gave MahaRERA: “This is a single customized villa and due to design changes required by the customer, the sanction plans had to be revised and have been submitted for approval. Hence there is delay in completion of this project.”
31 December 2026
Extended at the builder's request (MahaRERA application EA13052620950)
Reason the builder gave MahaRERA:
“Respected Sir/Madam, We, LUXORA INFRASTRUCTURE PRIVATE LIMITED, Promoter of the real estate project “Park Mansion 54”, bearing MahaRERA Registration No. P50500010626, hereby submit this application seeking an extension up to 31/12/2026 for…” Read the full reason
“Respected Sir/Madam, We, LUXORA INFRASTRUCTURE PRIVATE LIMITED, Promoter of the real estate project “Park Mansion 54”, bearing MahaRERA Registration No. P50500010626, hereby submit this application seeking an extension up to 31/12/2026 for completion of the said project. We respectfully submit that the delay in completion of the project has occurred due to prolonged and cumulative circumstances beyond the control of the promoter. The project has been affected by delays in obtaining statutory approvals, revalidations, and permissions from competent authorities, along with a sustained slowdow…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Park Mansion 54’s extension records on MahaRERA (P50500010626), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Park Mansion 54
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Park Mansion 48P50500004854 · possession 30 Apr 2029
- Park Mansion 52P50500019484 · possession 31 Dec 2026
- MahaRERA registration
- P50500010626
- Status
- Registered and active
- Builder
- Luxora Infrastructure Private Limited
- Location
- Mauza, Nagpur · 440034
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- March 2018
- Latest completion date
- April 2027
- Delay so far
- 105 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 1
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 22
Construction progress of Park Mansion 54, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Park Mansion 54 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Park Mansion 54: covers 2 floors
Latest CC order on MahaRERA: dated 08/04/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Park Mansion 54 every month.
Park Mansion 54: buildings, flats and land, as filed on MahaRERA
- Buildings: Park Mansion 54 (2 floors, 1 units)
- Car parking: 1 covered, 1 open
- Land: 650 sq m (about 0.2 acres) · sanctioned built-up 313 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Luxora Infrastructure (a group of 2 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 57 months); 12 still being built, 8 past the promised date (typically 78 months late); 2 lapsed. 17 complaints on MahaRERA across 6 projects.
Read Google reviews of Park Mansion 54 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Park Mansion 54: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Park Mansion 54
What is the possession date of Park Mansion 54?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Park Mansion 54 in Mauza, Nagpur is 30 April 2027 — 105 months later than 31 March 2018, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Park Mansion 54?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Park Mansion 54's builder has filed on MahaRERA, the official one, is 30 April 2027, already 105 months later than the 31 March 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Park Mansion 54 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Park Mansion 54's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2023, giving the reason "Due to the fact that a new 18m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications were successfully received on the same."; to 30 June 2024, giving the reason "Due to the fact that a new 18 m wide DP road was proposed by NMC in the Regional Plan which directly affected the project after the start of its construction, construction of the project was delayed until clarifications and amendments were successfully received on the same."; to 30 November 2025, giving the reason "This is a single customized villa and due to design changes required by the customer, the sanction plans had to be revised and have been submitted for approval. Hence there is delay in completion of this project."; to 31 December 2026, giving the reason "Respected Sir/Madam, We, LUXORA INFRASTRUCTURE PRIVATE LIMITED, Promoter of the real estate project “Park Mansion 54”, bearing MahaRERA Registration No. P50500010626, hereby submit this application seeking an extension up to 31/12/2026 for completion of the said project. We respectfully submit that the delay in completion of the project has occurred due to prolonged and cumulative circumstances beyond the control of the promoter. The project has been affected by delays in obtaining statutory approvals, revalidations, and permissions from competent authorities, along with a sustained slowdow…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Park Mansion 54?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Park Mansion 54 in Mauza, Nagpur is P50500010626.
Is Park Mansion 54 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Park Mansion 54 is registered as P50500010626 and its status is "Registered and active".
What is the construction status of Park Mansion 54?
According to GharKundli's check of MahaRERA records (updated October 2026), Park Mansion 54's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Park Mansion 54 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Park Mansion 54 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Park Mansion 54 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Park Mansion 54 is registered on MahaRERA as P50500010626, its completion date has moved 105 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Park Mansion 54 have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Park Mansion 48 (P50500004854, possession 30 Apr 2029); Park Mansion 52 (P50500019484, possession 31 Dec 2026). Check that your agreement names the registration of your own wing.
How can I get updates if Park Mansion 54's possession date changes?
The latest dates are on Park Mansion 54's MahaRERA page (P50500010626). GharKundli's Kundli Watch sends a free WhatsApp update on Park Mansion 54 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Park Mansion 54 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Park Mansion 54 has one building filed: Park Mansion 54 with 2 floors and 1 units.
How much parking does Park Mansion 54 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered and 1 open car parking spaces for Park Mansion 54.
How big is the land of Park Mansion 54?
According to GharKundli's check of MahaRERA records (updated October 2026), Park Mansion 54 stands on 650 sq m of land (about 0.2 acres), with 313 sq m of sanctioned built-up area.
What is the track record of Park Mansion 54's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Luxora Infrastructure (a group of 2 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 57 months); 12 still being built, 8 past the promised date (typically 78 months late); 2 lapsed. 17 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Park Mansion 54?
Google Maps has reviews of Park Mansion 54 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Park Mansion 54?
Park Mansion 54 by Luxora Infrastructure Private Limited is in Mauza, Nagpur (pincode 440034), near Besa, Pipla, Maharashtra, and is registered on MahaRERA as P50500010626, per GharKundli's check of MahaRERA records.
How many homes are in Park Mansion 54?
According to GharKundli's check of MahaRERA records (updated October 2026), Park Mansion 54 has 1 home in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was Park Mansion 54 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Park Mansion 54 was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Park Mansion 54?
No court cases are listed for Park Mansion 54 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Park Mansion 54?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Luxora Infrastructure Private Limited, which has 22 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Park Mansion 54
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nagpur →
Other projects in Mauza
- Park House Tranquil
- Park Mansion 52
- Treeline 6
- Park Mansion 48
- Park House Holistic
- Springfield
- Diamondleaf
- Vista 3B
Other projects by Luxora Infrastructure Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.