METRO PARK 5
by RITESH SAXENA · Dongargaon, Nagpur
Possession date of METRO PARK 5: 31 July 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500049389, and currently active. Its completion date is now July 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about METRO PARK 5?
How the possession date of METRO PARK 5 has moved
31 March 2027
Completion date given when the project was registered
31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: METRO PARK 5’s extension records on MahaRERA (P50500049389), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on METRO PARK 5
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- METRO PARK 12P50500049304 · possession 31 Jul 2027
- METRO PARK 13P50500049674 · possession 31 Jul 2027
- Metro Park 21P50500080630
- MahaRERA registration
- P50500049389
- Status
- Registered and active
- Builder
- RITESH SAXENA
- Location
- Dongargaon, Nagpur · 441108
- Project type
- Plotted
- Registered on
- 7 Feb 2023
- Completion date at registration
- March 2027
- Latest completion date
- July 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
METRO PARK 5: buildings, flats and land, as filed on MahaRERA
- Land: 14,835 sq m (about 3.7 acres) · sanctioned built-up 14,049 sq m · recreational space 1,781 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Ritesh Kailashprasad Saxena has 7 projects on MahaRERA since 2023, this one included. Of the 6 GharKundli has checked: 6 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of METRO PARK 5 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
METRO PARK 5: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about METRO PARK 5
What is the possession date of METRO PARK 5?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for METRO PARK 5 in Dongargaon, Nagpur is 31 July 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for METRO PARK 5?
Builders and listing sites often quote an earlier "target" date for handover. The completion date METRO PARK 5's builder has filed on MahaRERA, the official one, is 31 July 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of METRO PARK 5?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of METRO PARK 5 in Dongargaon, Nagpur is P50500049389.
Is METRO PARK 5 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), METRO PARK 5 is registered as P50500049389 and its status is "Registered and active".
What is the construction status of METRO PARK 5?
According to GharKundli's check of MahaRERA records (updated November 2026), METRO PARK 5's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.
Does METRO PARK 5 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is METRO PARK 5 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), METRO PARK 5 is registered on MahaRERA as P50500049389, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does METRO PARK 5 have other wings or phases?
Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: METRO PARK 12 (P50500049304, possession 31 Jul 2027); METRO PARK 13 (P50500049674, possession 31 Jul 2027); Metro Park 21 (P50500080630). Check that your agreement names the registration of your own wing.
How can I get updates if METRO PARK 5's possession date changes?
The latest dates are on METRO PARK 5's MahaRERA page (P50500049389). GharKundli's Kundli Watch sends a free WhatsApp update on METRO PARK 5 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How big is the land of METRO PARK 5?
According to GharKundli's check of MahaRERA records (updated November 2026), METRO PARK 5 stands on 14,835 sq m of land (about 3.7 acres), with 14,049 sq m of sanctioned built-up area and 1,781 sq m of recreational open space.
What is the track record of METRO PARK 5's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Ritesh Kailashprasad Saxena has 7 projects on MahaRERA since 2023, this one included. Of the 6 GharKundli has checked: 6 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of METRO PARK 5?
Google Maps has reviews of METRO PARK 5 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is METRO PARK 5?
METRO PARK 5 by RITESH SAXENA is in Dongargaon, Nagpur (pincode 441108), Maharashtra, and is registered on MahaRERA as P50500049389, per GharKundli's check of MahaRERA records.
When was METRO PARK 5 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), METRO PARK 5 was registered on MahaRERA on 7 February 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on METRO PARK 5?
No court cases are listed for METRO PARK 5 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of METRO PARK 5?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RITESH SAXENA, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of METRO PARK 5
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nagpur →
Other projects in pincode 441108
- CENTRAL COST CITY
- Nivaasa Retreat
- Happy Galaxy
- PEAK ORCHARD ESTATE
- SHREE LAXMI VISION CITY
- SWASTIK IMPERIAL
- MAHALAXMI NAGAR 51 ANAYA
- DEV BHUMI
Other projects by RITESH SAXENA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.