Possession date of CENTRONA NOVA B: 30 October 2027, moved from 30 December 2026 (6 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800004566, and currently active. Its completion date has moved from December 2026 to October 2027: 6 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about CENTRONA NOVA B?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of CENTRONA NOVA B has moved

  1. 30 December 2026

    Completion date given when the project was registered

  2. 30 June 2027

    Extended at the builder's request (MahaRERA application EXT51800017579)

    Reason the builder gave MahaRERA: “Change in layout plan”
  3. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: CENTRONA NOVA B’s extension records on MahaRERA (P51800004566), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on CENTRONA NOVA B

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800004566
Status
Registered and active
Builder
ELEVATED AVENUE REALTY LLP
Location
Ghatkopar East, Mumbai · 400077
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
December 2026
Latest completion date
October 2027
Delay so far
6 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
228
Sold or booked
100%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
7

Construction progress of CENTRONA NOVA B, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Orchid D100%69%30%0%

Commencement certificate (CC), as filed on MahaRERA

  • Orchid D: covers Plinth

Want to know when this changes? Kundli Watch sends a free WhatsApp update on CENTRONA NOVA B every month.

CENTRONA NOVA B: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of CENTRONA NOVA B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

CENTRONA NOVA B: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about CENTRONA NOVA B

What is the possession date of CENTRONA NOVA B?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for CENTRONA NOVA B in Ghatkopar East, Mumbai is 30 October 2027 — 6 months later than 30 December 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for CENTRONA NOVA B?

Builders and listing sites often quote an earlier "target" date for handover. The completion date CENTRONA NOVA B's builder has filed on MahaRERA, the official one, is 30 October 2027, already 6 months later than the 30 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of CENTRONA NOVA B extended?

According to GharKundli's check of MahaRERA records (updated November 2026), CENTRONA NOVA B's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "Change in layout plan". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of CENTRONA NOVA B?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of CENTRONA NOVA B in Ghatkopar East, Mumbai is P51800004566.

Is CENTRONA NOVA B registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), CENTRONA NOVA B is registered as P51800004566 and its status is "Registered and active".

What is the construction status of CENTRONA NOVA B?

According to GharKundli's check of MahaRERA records (updated November 2026), CENTRONA NOVA B's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Orchid D is 69% done and internal work 30%. GharKundli's full report compares construction progress with the deadline.

Does CENTRONA NOVA B have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is CENTRONA NOVA B safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), CENTRONA NOVA B is registered on MahaRERA as P51800004566, its completion date has moved 6 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does CENTRONA NOVA B have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: CENTRONA NOVA-A (P51800005456, possession 30 Oct 2027). Check that your agreement names the registration of your own wing.

How can I get updates if CENTRONA NOVA B's possession date changes?

The latest dates are on CENTRONA NOVA B's MahaRERA page (P51800004566). GharKundli's Kundli Watch sends a free WhatsApp update on CENTRONA NOVA B every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does CENTRONA NOVA B have?

According to GharKundli's check of MahaRERA records (updated November 2026), CENTRONA NOVA B has one building filed: Orchid D with 35 floors and 228 units.

How big is the land of CENTRONA NOVA B?

According to GharKundli's check of MahaRERA records (updated November 2026), CENTRONA NOVA B stands on 793 sq m of land (about 0.2 acres), with 12,557 sq m of sanctioned built-up area.

Where can I read reviews of CENTRONA NOVA B?

Google Maps has reviews of CENTRONA NOVA B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is CENTRONA NOVA B?

CENTRONA NOVA B by ELEVATED AVENUE REALTY LLP is in Ghatkopar East, Mumbai (pincode 400077), near Ghatkopar Kirol, Chembur, Rajawadi, Maharashtra, and is registered on MahaRERA as P51800004566, per GharKundli's check of MahaRERA records. Its boundaries filed there include Eastern Express Highway.

How many homes are in CENTRONA NOVA B?

According to GharKundli's check of MahaRERA records (updated November 2026), CENTRONA NOVA B has 228 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was CENTRONA NOVA B registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), CENTRONA NOVA B was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on CENTRONA NOVA B?

No court cases are listed for CENTRONA NOVA B on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of CENTRONA NOVA B?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ELEVATED AVENUE REALTY LLP, which has 7 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Ghatkopar East

All 228 projects in Ghatkopar East (400077) →

Other projects by ELEVATED AVENUE REALTY LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.