CENTRONA ZEN-A
by ELEVATED AVENUE REALTY LLP · Ghatkopar East, MumbaiAlso near Ghatkopar Kirol, Chembur, Rajawadi
Possession date of CENTRONA ZEN-A: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800006239, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about CENTRONA ZEN-A?
How the possession date of CENTRONA ZEN-A has moved
30 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: CENTRONA ZEN-A’s extension records on MahaRERA (P51800006239), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on CENTRONA ZEN-A
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- CENTRONA ZEN-BP51800006139 · possession 30 Apr 2027
- MahaRERA registration
- P51800006239
- Status
- Registered and active
- Builder
- ELEVATED AVENUE REALTY LLP
- Location
- Ghatkopar East, Mumbai · 400077
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 376
- Sold or booked
- 99%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 7
Construction progress of CENTRONA ZEN-A, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Ivy A | 100% | 100% | 100% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- Ivy A: covers Plinth
Want to know when this changes? Kundli Watch sends a free WhatsApp update on CENTRONA ZEN-A every month.
CENTRONA ZEN-A: buildings, flats and land, as filed on MahaRERA
- Buildings: Ivy A (27 floors, 376 units)
- Land: 564 sq m (about 0.1 acres) · sanctioned built-up 9,996 sq m
- Boundaries filed include: Eastern Express Highway
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of CENTRONA ZEN-A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
CENTRONA ZEN-A: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about CENTRONA ZEN-A
What is the possession date of CENTRONA ZEN-A?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for CENTRONA ZEN-A in Ghatkopar East, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for CENTRONA ZEN-A?
Builders and listing sites often quote an earlier "target" date for handover. The completion date CENTRONA ZEN-A's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of CENTRONA ZEN-A?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of CENTRONA ZEN-A in Ghatkopar East, Mumbai is P51800006239.
Is CENTRONA ZEN-A registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), CENTRONA ZEN-A is registered as P51800006239 and its status is "Registered and active".
What is the construction status of CENTRONA ZEN-A?
According to GharKundli's check of MahaRERA records (updated November 2026), CENTRONA ZEN-A's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Ivy A is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does CENTRONA ZEN-A have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is CENTRONA ZEN-A safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), CENTRONA ZEN-A is registered on MahaRERA as P51800006239, its completion date has not been moved by the builder and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does CENTRONA ZEN-A have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: CENTRONA ZEN-B (P51800006139, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.
How can I get updates if CENTRONA ZEN-A's possession date changes?
The latest dates are on CENTRONA ZEN-A's MahaRERA page (P51800006239). GharKundli's Kundli Watch sends a free WhatsApp update on CENTRONA ZEN-A every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does CENTRONA ZEN-A have?
According to GharKundli's check of MahaRERA records (updated November 2026), CENTRONA ZEN-A has one building filed: Ivy A with 27 floors and 376 units.
How big is the land of CENTRONA ZEN-A?
According to GharKundli's check of MahaRERA records (updated November 2026), CENTRONA ZEN-A stands on 564 sq m of land (about 0.1 acres), with 9,996 sq m of sanctioned built-up area.
Where can I read reviews of CENTRONA ZEN-A?
Google Maps has reviews of CENTRONA ZEN-A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is CENTRONA ZEN-A?
CENTRONA ZEN-A by ELEVATED AVENUE REALTY LLP is in Ghatkopar East, Mumbai (pincode 400077), near Ghatkopar Kirol, Chembur, Rajawadi, Maharashtra, and is registered on MahaRERA as P51800006239, per GharKundli's check of MahaRERA records. Its boundaries filed there include Eastern Express Highway.
How many homes are in CENTRONA ZEN-A?
According to GharKundli's check of MahaRERA records (updated November 2026), CENTRONA ZEN-A has 376 homes in 1 tower registered on MahaRERA, and 99% of them are sold or booked.
When was CENTRONA ZEN-A registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), CENTRONA ZEN-A was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on CENTRONA ZEN-A?
No court cases are listed for CENTRONA ZEN-A on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of CENTRONA ZEN-A?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ELEVATED AVENUE REALTY LLP, which has 7 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of CENTRONA ZEN-A
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Ghatkopar East
- Jai Arihant
- Terraform Dwarka - Wing D
- Avis Residency
- Omkaar Pride
- Damji Shamji Corporate Square - Wing C
- Manhattan Residency (A4) - upto 14th Floor
- North Sea Heights (A1) - upto 14th floor
- Om Shreepal
Other projects by ELEVATED AVENUE REALTY LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.