MADHAV BAUG

by RAJYOG PROJECTS · Borivali West, MumbaiAlso near Babhai Naka

Possession date of MADHAV BAUG: 30 April 2030, moved from 30 December 2023 (72 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800009337, and currently active. Its completion date has moved from December 2023 to April 2030: 72 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about MADHAV BAUG?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on MADHAV BAUG

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints and 3 court cases, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800009337
Status
Registered and active
Builder
RAJYOG PROJECTS
Location
Borivali West, Mumbai · 400092
Project type
Others
Registered on
22 Aug 2017
Completion date at registration
December 2023
Latest completion date
April 2030
Delay so far
72 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
30
Sold or booked
0%
Towers
1
Complaints on MahaRERA
2
Court cases listed
3
Title report on file
Not found

Construction progress of MADHAV BAUG, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MADHAV BAUG0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MADHAV BAUG every month.

MADHAV BAUG: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Shops95 – 2,29934
2 BHK78430
Office Space294 – 1,7829

The builder’s record and reviews

Ssavai Smart Abodes (a group of 5 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 2 still being built, 1 past the promised date (typically 18 months late); 2 lapsed. 22 complaints on MahaRERA across 3 projects.

Read Google reviews of MADHAV BAUG →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MADHAV BAUG: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MADHAV BAUG

What is the possession date of MADHAV BAUG?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MADHAV BAUG in Borivali West, Mumbai is 30 April 2030 — 72 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for MADHAV BAUG?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MADHAV BAUG's builder has filed on MahaRERA, the official one, is 30 April 2030, already 72 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of MADHAV BAUG?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MADHAV BAUG in Borivali West, Mumbai is P51800009337.

Is MADHAV BAUG registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MADHAV BAUG is registered as P51800009337 and its status is "Registered and active".

What is the construction status of MADHAV BAUG?

According to GharKundli's check of MahaRERA records (updated October 2026), MADHAV BAUG's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MADHAV BAUG is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does MADHAV BAUG have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is MADHAV BAUG safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MADHAV BAUG is registered on MahaRERA as P51800009337, its completion date has moved 72 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MADHAV BAUG's possession date changes?

The latest dates are on MADHAV BAUG's MahaRERA page (P51800009337). GharKundli's Kundli Watch sends a free WhatsApp update on MADHAV BAUG every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MADHAV BAUG have?

According to GharKundli's check of MahaRERA records (updated October 2026), MADHAV BAUG has one building filed: MADHAV BAUG with 31 floors.

What are the flat sizes (carpet area) in MADHAV BAUG?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for MADHAV BAUG: 2 BHK: 784 sq ft carpet (30 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of MADHAV BAUG?

According to GharKundli's check of MahaRERA records (updated October 2026), MADHAV BAUG stands on 5,171 sq m of land (about 1.3 acres), with 13,190 sq m of sanctioned built-up area.

What is the track record of MADHAV BAUG's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ssavai Smart Abodes (a group of 5 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 2 still being built, 1 past the promised date (typically 18 months late); 2 lapsed. 22 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of MADHAV BAUG?

Google Maps has reviews of MADHAV BAUG written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MADHAV BAUG?

MADHAV BAUG by RAJYOG PROJECTS is in Borivali West, Mumbai (pincode 400092), near Babhai Naka, Maharashtra, and is registered on MahaRERA as P51800009337, per GharKundli's check of MahaRERA records. Its boundaries filed there include 67TH ROAD TO THE NORTH.

How many homes are in MADHAV BAUG?

According to GharKundli's check of MahaRERA records (updated October 2026), MADHAV BAUG has 30 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was MADHAV BAUG registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MADHAV BAUG was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on MADHAV BAUG?

3 court cases are listed for MADHAV BAUG on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of MADHAV BAUG?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAJYOG PROJECTS.

All projects with possession due in 2030 in Mumbai Suburban →

Other projects in pincode 400092

All 362 projects in Borivali West (400092) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.