Nidhi 86 Central A

by Sri Sai Nidhi Realtors Private Limited · Ghatkopar West, Mumbai 400086Also near Barve Nagar, Pant Nagar, VikhroliRegistered on MahaRERA as “86 CENTRAL A”

What’s in the report? →

Possession date of Nidhi 86 Central A (MahaRERA P51800021290): 30 December 2024, and it has already passed. It has 190 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800021290. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800021290, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2024) has passed.

What do you want to know about Nidhi 86 Central A?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Nidhi 86 Central A

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800021290
Status
Lapsed (registration period ended)
Builder
Sri Sai Nidhi Realtors Private Limited
Location
Ghatkopar West, Mumbai · 400086
Project type
Commercial
Registered on
21 Jun 2019
Completion date at registration
December 2024
Latest completion date
December 2024
Homes
190
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Nidhi 86 Central A, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
86 CENTRAL A100%100%100%30%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nidhi 86 Central A every 1–2 months.

Nidhi 86 Central A: buildings, flats and land, as filed on MahaRERA

  • Buildings: 86 CENTRAL A (16 floors)
  • Land: 399 sq m (about 0.1 acres) · sanctioned built-up 5,880 sq m
  • Boundaries filed include: LINK ROAD
  • Land, as filed: 2210A PT 2210 PT 2210C PT 2147TO 2177 2178 TO 2185
  • Map: Get directions

The builder’s record and reviews

Sri Sai Nidhi Realtors has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 2 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Nidhi 86 Central A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Nidhi 86 Central A: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Nidhi 86 Central A

What is the possession date of Nidhi 86 Central A?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Nidhi 86 Central A in Ghatkopar West, Mumbai is 30 December 2024. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Nidhi 86 Central A?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Nidhi 86 Central A's builder has filed on MahaRERA, the official one, is 30 December 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Nidhi 86 Central A?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Nidhi 86 Central A in Ghatkopar West, Mumbai is P51800021290.

Is Nidhi 86 Central A registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Nidhi 86 Central A is registered as P51800021290 and its status is "Lapsed (registration period ended)".

What is the current construction status of Nidhi 86 Central A? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Nidhi 86 Central A's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on 86 CENTRAL A is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Nidhi 86 Central A have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Nidhi 86 Central A safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Nidhi 86 Central A is registered on MahaRERA as P51800021290, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Nidhi 86 Central A?

Nidhi 86 Central A isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Nidhi 86 Central A?

For a flat in Nidhi 86 Central A (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Nidhi 86 Central A received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Nidhi 86 Central A isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Nidhi 86 Central A?

According to GharKundli's check of MahaRERA records (updated October 2026), Nidhi 86 Central A's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Nidhi 86 Central A uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Nidhi 86 Central A was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Nidhi 86 Central A's possession date changes?

The latest dates are on Nidhi 86 Central A's MahaRERA page (P51800021290). GharKundli's Kundli Watch sends a free WhatsApp update on Nidhi 86 Central A every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Nidhi 86 Central A have?

According to GharKundli's check of MahaRERA records (updated October 2026), Nidhi 86 Central A has one building filed: 86 CENTRAL A with 16 floors.

How big is the land of Nidhi 86 Central A?

According to GharKundli's check of MahaRERA records (updated October 2026), Nidhi 86 Central A stands on 399 sq m of land (about 0.1 acres), with 5,880 sq m of sanctioned built-up area.

What is the track record of Nidhi 86 Central A's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sri Sai Nidhi Realtors has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 2 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Nidhi 86 Central A?

Google Maps has reviews of Nidhi 86 Central A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Nidhi 86 Central A?

Nidhi 86 Central A by Sri Sai Nidhi Realtors Private Limited is in Ghatkopar West, Mumbai, pincode 400086 (near Barve Nagar, Pant Nagar, Vikhroli), Maharashtra, and is registered on MahaRERA as P51800021290, per GharKundli's check of MahaRERA records. Its boundaries filed there include LINK ROAD. Its land is filed as 2210A PT 2210 PT 2210C PT 2147TO 2177 2178 TO 2185. GharKundli lists all 83 MahaRERA projects in Ghatkopar West (400086).

How many flats are in Nidhi 86 Central A?

According to GharKundli's check of MahaRERA records (updated October 2026), Nidhi 86 Central A has 190 homes in 1 tower registered on MahaRERA.

When was Nidhi 86 Central A registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Nidhi 86 Central A was registered on MahaRERA on 21 June 2019. GharKundli did not find a title report on the land on file there.

Does Nidhi 86 Central A have any legal issues or court cases?

1 court case is listed for Nidhi 86 Central A on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Nidhi 86 Central A?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sri Sai Nidhi Realtors Private Limited, which has 2 other projects registered on MahaRERA.

Other projects in Ghatkopar West (400086)

All 83 projects in Ghatkopar West (400086) →

Other projects by Sri Sai Nidhi Realtors Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.