by Shree Siddhivinayak Classic Construction Private Limited (Ruparel) · Nehru Nagar, MumbaiAlso near Kurla East, Kurla West, Bhandup West

Possession date of Ruparel Livia: 30 October 2026, moved from 30 June 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800026450, and currently active. Its completion date has moved from June 2024 to October 2026: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 9 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about Ruparel Livia?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Ruparel Livia has moved

  1. 30 June 2024

    Completion date given when the project was registered

  2. 30 June 2026

    Extended at the builder's request (MahaRERA application EXT51800024075)

    Reason the builder gave MahaRERA:
    “We, M/s. Shree Siddhivinayak Classic Construction Pvt. Ltd., the promoter of the project “Ruparel Livia,” kindly request an extension of the project completion date to 30th June 2026. The mahaRERA registration certificate issued on 24th Sep…” Read the full reason“We, M/s. Shree Siddhivinayak Classic Construction Pvt. Ltd., the promoter of the project “Ruparel Livia,” kindly request an extension of the project completion date to 30th June 2026. The mahaRERA registration certificate issued on 24th September 2020, is currently valid until 30th June 2024. Due to unforeseen and uncontrollable circumstances, including legal and pandemic-related challenges, the project has faced significant delays. We request this extension under Section 7(3) of the RERA Act. Key Reasons for Delay: Legal Proceedings for Tenant Eviction Legal actions against 15 commercial t…”
  3. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Ruparel Livia’s extension records on MahaRERA (P51800026450), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ruparel Livia

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 9 complaints, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800026450
Status
Registered and active
Builder
Shree Siddhivinayak Classic Construction Private Limited
Location
Nehru Nagar, Mumbai · 400024
Project type
Residential / Group Housing
Registered on
24 Sep 2020
Completion date at registration
June 2024
Latest completion date
October 2026
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
120
Sold or booked
43%
Towers
1
Complaints on MahaRERA
9
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Ruparel Livia, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Ruparel Livia100%100%95%0%

Commencement certificate (CC), as filed on MahaRERA

  • Ruparel Livia: covers This C.C. is further extended up to 14th upper floors, as per the last approved amended plans dated 24/01/2020

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ruparel Livia every month.

Ruparel Livia: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK301 – 368120
Shops23 – 22435

The builder’s record and reviews

Ruparel Infra & Realty (a group of 12 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 47 months); 13 still being built, 7 past the promised date (typically 28 months late); 10 lapsed. 856 complaints on MahaRERA across 19 projects.

Read Google reviews of Ruparel Livia →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ruparel Livia: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Ruparel Livia

What is the possession date of Ruparel Livia?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ruparel Livia in Nehru Nagar, Mumbai is 30 October 2026 — 24 months later than 30 June 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Ruparel Livia?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ruparel Livia's builder has filed on MahaRERA, the official one, is 30 October 2026, already 24 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Ruparel Livia extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Livia's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "We, M/s. Shree Siddhivinayak Classic Construction Pvt. Ltd., the promoter of the project “Ruparel Livia,” kindly request an extension of the project completion date to 30th June 2026. The mahaRERA registration certificate issued on 24th September 2020, is currently valid until 30th June 2024. Due to unforeseen and uncontrollable circumstances, including legal and pandemic-related challenges, the project has faced significant delays. We request this extension under Section 7(3) of the RERA Act. Key Reasons for Delay: Legal Proceedings for Tenant Eviction Legal actions against 15 commercial t…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Ruparel Livia?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ruparel Livia in Nehru Nagar, Mumbai is P51800026450.

Is Ruparel Livia registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Livia is registered as P51800026450 and its status is "Registered and active".

What is the construction status of Ruparel Livia?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Livia's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Ruparel Livia is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does Ruparel Livia have complaints on MahaRERA?

9 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Ruparel Livia safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Livia is registered on MahaRERA as P51800026450, its completion date has moved 24 months since registration and 9 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Ruparel Livia's possession date changes?

The latest dates are on Ruparel Livia's MahaRERA page (P51800026450). GharKundli's Kundli Watch sends a free WhatsApp update on Ruparel Livia every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ruparel Livia have?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Livia has one building filed: Ruparel Livia with 19 floors and 155 units.

What are the flat sizes (carpet area) in Ruparel Livia?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Ruparel Livia: 1 BHK: 301 to 368 sq ft carpet (120 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Ruparel Livia?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Livia stands on 1,222 sq m of land (about 0.3 acres), with 5,037 sq m of sanctioned built-up area.

What is the track record of Ruparel Livia's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Infra & Realty (a group of 12 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 47 months); 13 still being built, 7 past the promised date (typically 28 months late); 10 lapsed. 856 complaints on MahaRERA across 19 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Ruparel Livia?

Google Maps has reviews of Ruparel Livia written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 9 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Ruparel Livia?

Ruparel Livia by Shree Siddhivinayak Classic Construction Private Limited (Ruparel) is in Nehru Nagar, Mumbai (pincode 400024), near Kurla East, Kurla West, Bhandup West, Maharashtra, and is registered on MahaRERA as P51800026450, per GharKundli's check of MahaRERA records.

How many homes are in Ruparel Livia?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Livia has 120 homes in 1 tower registered on MahaRERA, and 43% of them are sold or booked.

When was Ruparel Livia registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Livia was registered on MahaRERA on 24 September 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on Ruparel Livia?

No court cases are listed for Ruparel Livia on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Ruparel Livia?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shree Siddhivinayak Classic Construction Private Limited, the company Ruparel files this project under, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in pincode 400024

All 85 projects in Kurla East (400024) →

Other projects by Shree Siddhivinayak Classic Construction Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.