What’s in the report? →Possession date of Asmi Shimmers (MahaRERA P51800029561): 31 December 2025, moved from 31 December 2022 (36 months later), and it has already passed. It has 42 homes (1 BHK, 2 BHK and 3 BHK, 442–1090 sq ft carpet), 74% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800029561. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800029561, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Asmi Shimmers?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Asmi Shimmers has moved
31 December 2022
Completion date given when the project was registered
31 December 2023
Extended at the builder's request (MahaRERA application EXT51800012967)
Reason the builder gave MahaRERA:
“The project is delayed because of technical issues from due to that competent authority is pending. We require another one year to complete the project which is from 31st December, 2022 to 31st December, 2023 for doing all compliance of com…” Read the full reason
“The project is delayed because of technical issues from due to that competent authority is pending. We require another one year to complete the project which is from 31st December, 2022 to 31st December, 2023 for doing all compliance of competent authority.”31 December 2025
Extended at the builder's request (MahaRERA application EXT51800018982)
Reason the builder gave MahaRERA: “government compliance”
Source: Asmi Shimmers’s extension records on MahaRERA (P51800029561), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Asmi Shimmers
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 court cases, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800029561
- Status
- Lapsed (registration period ended)
- Builder
- AJAY DEDHIA
- Location
- Goregaon East, Mumbai · 400063
- Project type
- Residential / Group Housing
- Registered on
- 4 Jun 2021
- Completion date at registration
- December 2022
- Latest completion date
- December 2025
- Delay so far
- 36 months
- Homes
- 42
- Sold or booked
- 74%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 2
- Title report on file
- Not found
Construction progress of Asmi Shimmers, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Udayachal CHS LTD | 100% | 100% | 95% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- Udayachal CHS LTD: covers 15 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Asmi Shimmers every 1–2 months.
Asmi Shimmers: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 442 – 563 | 31 |
| 2 BHK | 678 – 752 | 6 |
| 3 BHK | 1,090 | 5 |
| Shops | 662 | 1 |
- Buildings: Udayachal CHS LTD (15 floors, 43 units)
- Car parking: 32 covered
- Land: 949 sq m (about 0.2 acres) · sanctioned built-up 2,172 sq m
- Land, as filed: 281,92
- Map: Get directions
The builder’s record and reviews
Ajay Malshi Dedhia has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 2 months); 2 lapsed. No complaints on MahaRERA.
Read Google reviews of Asmi Shimmers →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Asmi Shimmers: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Asmi Shimmers
What is the possession date of Asmi Shimmers?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Asmi Shimmers in Goregaon East, Mumbai is 31 December 2025 — 36 months later than 31 December 2022, the date given at registration. That date has already passed.
The date has already moved 36 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Asmi Shimmers?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Asmi Shimmers's builder has filed on MahaRERA, the official one, is 31 December 2025, already 36 months later than the 31 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Asmi Shimmers extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Shimmers's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2023, giving the reason "The project is delayed because of technical issues from due to that competent authority is pending. We require another one year to complete the project which is from 31st December, 2022 to 31st December, 2023 for doing all compliance of competent authority."; to 31 December 2025, giving the reason "government compliance".
What is the RERA number of Asmi Shimmers?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Asmi Shimmers in Goregaon East, Mumbai is P51800029561.
Is Asmi Shimmers registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Shimmers is registered as P51800029561 and its status is "Lapsed (registration period ended)".
What is the current construction status of Asmi Shimmers? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Shimmers's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Udayachal CHS LTD is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does Asmi Shimmers have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Asmi Shimmers safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Shimmers is registered on MahaRERA as P51800029561, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Asmi Shimmers?
Asmi Shimmers isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Asmi Shimmers are 442 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Asmi Shimmers?
For a flat in Asmi Shimmers (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Asmi Shimmers received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Shimmers isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Asmi Shimmers?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Shimmers's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Is Asmi Shimmers a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Shimmers is a redevelopment: 16 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Asmi Shimmers uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Asmi Shimmers was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Asmi Shimmers's possession date changes?
The latest dates are on Asmi Shimmers's MahaRERA page (P51800029561). GharKundli's Kundli Watch sends a free WhatsApp update on Asmi Shimmers every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Asmi Shimmers have?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Shimmers has one building filed: Udayachal CHS LTD with 15 floors and 43 units.
What are the flat sizes (carpet area) in Asmi Shimmers?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Asmi Shimmers: 1 BHK: 442 to 563 sq ft carpet (31 homes); 2 BHK: 678 to 752 sq ft carpet (6 homes); 3 BHK: 1090 sq ft carpet (5 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Asmi Shimmers have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 32 covered car parking spaces for Asmi Shimmers.
How big is the land of Asmi Shimmers?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Shimmers stands on 949 sq m of land (about 0.2 acres), with 2,172 sq m of sanctioned built-up area.
What is the track record of Asmi Shimmers's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Ajay Malshi Dedhia has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 2 months); 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Asmi Shimmers?
Google Maps has reviews of Asmi Shimmers written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Asmi Shimmers?
Asmi Shimmers by AJAY DEDHIA is in Goregaon East, Mumbai, pincode 400063 (near Jogeshwari West), Maharashtra, and is registered on MahaRERA as P51800029561, per GharKundli's check of MahaRERA records. Its land is filed as 281,92. GharKundli lists all 151 MahaRERA projects in Goregaon East (400063).
How many flats are in Asmi Shimmers, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Shimmers has 42 homes in 1 tower registered on MahaRERA, and 74% of them are sold or booked.
When was Asmi Shimmers registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Shimmers was registered on MahaRERA on 4 June 2021. GharKundli did not find a title report on the land on file there.
Does Asmi Shimmers have any legal issues or court cases?
2 court cases are listed for Asmi Shimmers on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Asmi Shimmers?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AJAY DEDHIA.
Check it yourself on MahaRERA
- How to check the possession date of Asmi Shimmers
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Goregaon East (400063)
- 104 East
- Sheetal Sangam
- Astoria Tower B
- Avant Hillway
- Avant Hillway
- Satellite Elegance
- Sejal Square
- S-city-r2
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.