SHRADDHA VARDAAN
by SHRADDHA LANDMARK PRIVATE LIMITED · Bhandup West, MumbaiAlso near Kanjurmarg East, Powai, Vikhroli East
Possession date of SHRADDHA VARDAAN: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800028936, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SHRADDHA VARDAAN?
How the possession date of SHRADDHA VARDAAN has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SHRADDHA VARDAAN’s extension records on MahaRERA (P51800028936), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHRADDHA VARDAAN
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 1 court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800028936
- Status
- Registered and active
- Builder
- SHRADDHA LANDMARK PRIVATE LIMITED
- Location
- Bhandup West, Mumbai · 400078
- Project type
- Residential / Group Housing
- Registered on
- 15 Apr 2021
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 723
- Sold or booked
- 94%
- Towers
- 3
- Complaints on MahaRERA
- 1
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 20
Construction progress of SHRADDHA VARDAAN, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 100% | 100% | 100% | 40% |
| WING B | 100% | 100% | 100% | 40% |
| WING C | 100% | 100% | 71.65% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- WING A: covers 40 floors
- WING B: covers 40 floors
- WING C: covers 40 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHRADDHA VARDAAN every month.
SHRADDHA VARDAAN: buildings, flats and land, as filed on MahaRERA
- Buildings: WING A (42 floors, 213 units) · WING B (42 floors, 293 units) · WING C (42 floors, 217 units)
- Land: 10,741 sq m (about 2.7 acres) · sanctioned built-up 24,333 sq m · recreational space 563 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Shraddha Landmark (a group of 8 linked companies) has 35 projects on MahaRERA since 2017, this one included. Of the 35 GharKundli has checked: 12 finished, 8 within the promised date and 4 needed more time (typically 8 months); 22 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 7 complaints on MahaRERA across 7 projects.
Read Google reviews of SHRADDHA VARDAAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHRADDHA VARDAAN: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHRADDHA VARDAAN
What is the possession date of SHRADDHA VARDAAN?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHRADDHA VARDAAN in Bhandup West, Mumbai is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SHRADDHA VARDAAN?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHRADDHA VARDAAN's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SHRADDHA VARDAAN?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHRADDHA VARDAAN in Bhandup West, Mumbai is P51800028936.
Is SHRADDHA VARDAAN registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHRADDHA VARDAAN is registered as P51800028936 and its status is "Registered and active".
What is the construction status of SHRADDHA VARDAAN?
According to GharKundli's check of MahaRERA records (updated November 2026), SHRADDHA VARDAAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does SHRADDHA VARDAAN have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SHRADDHA VARDAAN safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SHRADDHA VARDAAN is registered on MahaRERA as P51800028936, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHRADDHA VARDAAN's possession date changes?
The latest dates are on SHRADDHA VARDAAN's MahaRERA page (P51800028936). GharKundli's Kundli Watch sends a free WhatsApp update on SHRADDHA VARDAAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHRADDHA VARDAAN have?
According to GharKundli's check of MahaRERA records (updated November 2026), SHRADDHA VARDAAN has 3 buildings filed: WING A with 42 floors and 213 units; WING B with 42 floors and 293 units; WING C with 42 floors and 217 units.
How big is the land of SHRADDHA VARDAAN?
According to GharKundli's check of MahaRERA records (updated November 2026), SHRADDHA VARDAAN stands on 10,741 sq m of land (about 2.7 acres), with 24,333 sq m of sanctioned built-up area and 563 sq m of recreational open space.
What is the track record of SHRADDHA VARDAAN's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Shraddha Landmark (a group of 8 linked companies) has 35 projects on MahaRERA since 2017, this one included. Of the 35 GharKundli has checked: 12 finished, 8 within the promised date and 4 needed more time (typically 8 months); 22 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 7 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHRADDHA VARDAAN?
Google Maps has reviews of SHRADDHA VARDAAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHRADDHA VARDAAN?
SHRADDHA VARDAAN by SHRADDHA LANDMARK PRIVATE LIMITED is in Bhandup West, Mumbai (pincode 400078), near Kanjurmarg East, Powai, Vikhroli East, Maharashtra, and is registered on MahaRERA as P51800028936, per GharKundli's check of MahaRERA records.
How many homes are in SHRADDHA VARDAAN?
According to GharKundli's check of MahaRERA records (updated November 2026), SHRADDHA VARDAAN has 723 homes in 3 towers registered on MahaRERA, and 94% of them are sold or booked.
When was SHRADDHA VARDAAN registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHRADDHA VARDAAN was registered on MahaRERA on 15 April 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on SHRADDHA VARDAAN?
1 court case is listed for SHRADDHA VARDAAN on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SHRADDHA VARDAAN?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHRADDHA LANDMARK PRIVATE LIMITED, which has 20 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SHRADDHA VARDAAN
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in pincode 400078
- Runwal Forests Tower 9 - 11
- Horizon
- Valentina CHS
- Sugee Vaayu
- Godrej Nurture - Tower 2
- Godrej Nurture - Tower 3
- BHOOMI GREEN HILL
- Pandora by Shraddha
Other projects by SHRADDHA LANDMARK PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.