by Shreeram Builders (Amrut) · Pahadi Goregaon East, Mumbai 400063Also near Jogeshwari West

What’s in the report? →

Possession date of Onyx (MahaRERA P51800032011): 30 March 2027. It has 34 homes (1 BHK and 2 BHK, 405–709 sq ft carpet), 68% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800032011, and currently active. Its completion date is now March 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800032011, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Onyx?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Onyx has moved

  1. 30 November 2026

    Completion date given when the project was registered

  2. 30 March 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Onyx’s extension records on MahaRERA (P51800032011), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Onyx

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800032011
Status
Registered and active
Builder
Shreeram Builders
Location
Pahadi Goregaon East, Mumbai · 400063
Project type
Others
Registered on
3 Dec 2021
Completion date at registration
November 2026
Latest completion date
March 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
34
Sold or booked
68%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Onyx, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A100%75%30%0%
Wing B100%75%30%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Onyx every 1–2 months.

Onyx: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK405 – 47721
2 BHK585 – 70913
Shops239 – 5976
Office Space604 – 3,7894
  • Buildings: Wing A (26 floors) · Wing B (26 floors)
  • Land: 1,742 sq m (about 0.4 acres) · sanctioned built-up 4,642 sq m
  • Boundaries filed include: Jayprakash Road No - 1
  • Land, as filed: CTS No. 379, 379 1 to 13
  • Map: Get directions

The builder’s record and reviews

Shreeram Builders (a group of 6 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 13 finished, all within the promised date; 9 still being built, none past the promised date yet; 1 lapsed. 9 complaints on MahaRERA across 2 projects.

Read Google reviews of Onyx →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Onyx: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Onyx

What is the possession date of Onyx?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Onyx in Pahadi Goregaon East, Mumbai is 30 March 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Onyx?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Onyx's builder has filed on MahaRERA, the official one, is 30 March 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Onyx?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Onyx in Pahadi Goregaon East, Mumbai is P51800032011.

Is Onyx registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Onyx is registered as P51800032011 and its status is "Registered and active".

What is the current construction status of Onyx? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Onyx's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 75% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Onyx have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Onyx safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Onyx is registered on MahaRERA as P51800032011, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Onyx?

Onyx is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Onyx are 405 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Onyx?

For a flat in Onyx (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Onyx received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Onyx is still under construction, with 30 March 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Onyx uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Onyx was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Onyx's possession date changes?

The latest dates are on Onyx's MahaRERA page (P51800032011). GharKundli's Kundli Watch sends a free WhatsApp update on Onyx every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Onyx have?

According to GharKundli's check of MahaRERA records (updated October 2026), Onyx has 2 buildings filed: Wing A with 26 floors; Wing B with 26 floors.

What are the flat sizes (carpet area) in Onyx?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Onyx: 1 BHK: 405 to 477 sq ft carpet (21 homes); 2 BHK: 585 to 709 sq ft carpet (13 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Onyx?

According to GharKundli's check of MahaRERA records (updated October 2026), Onyx stands on 1,742 sq m of land (about 0.4 acres), with 4,642 sq m of sanctioned built-up area.

What is the track record of Onyx's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreeram Builders (a group of 6 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 13 finished, all within the promised date; 9 still being built, none past the promised date yet; 1 lapsed. 9 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Onyx?

Google Maps has reviews of Onyx written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Onyx?

Onyx by Shreeram Builders (Amrut) is in Pahadi Goregaon East, Mumbai, pincode 400063 (near Jogeshwari West), Maharashtra, and is registered on MahaRERA as P51800032011, per GharKundli's check of MahaRERA records. Its boundaries filed there include Jayprakash Road No - 1. Its land is filed as CTS No. 379, 379 1 to 13. GharKundli lists all 151 MahaRERA projects in Goregaon East (400063).

How many flats are in Onyx, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Onyx has 34 homes in 2 towers registered on MahaRERA, and 68% of them are sold or booked.

When was Onyx registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Onyx was registered on MahaRERA on 3 December 2021. GharKundli did not find a title report on the land on file there.

Does Onyx have any legal issues or court cases?

No court cases are listed for Onyx on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Onyx?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shreeram Builders, the company Amrut files this project under, which has 5 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Goregaon East (400063)

All 151 projects in Goregaon East (400063) →

Other projects by Shreeram Builders

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.