Vrundavan Sra CHS LTD Lotus Tower

by SHREE VARADKRUPA TOWERS LLP · Ghatkopar West Bhatwadi, Mumbai 400086Also near Ghatkopar East, Vile Parle West, Dahisar East

What’s in the report? →

Possession date of Vrundavan Sra CHS LTD Lotus Tower (MahaRERA P51800045859): 31 July 2026, moved from 31 March 2024 (24 months later), and it has already passed. It has 52 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800045859. Status: Lapsed (registration period ended). Its completion date has moved from March 2024 to July 2026: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800045859, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (July 2026) has passed.

What do you want to know about Vrundavan Sra CHS LTD Lotus Tower?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Vrundavan Sra CHS LTD Lotus Tower has moved

  1. 31 March 2024

    Completion date given when the project was registered

  2. 31 March 2026

    Extended at the builder's request (MahaRERA application EXT51800019306)

    Reason the builder gave MahaRERA:
    “Request for Extension of Building Completion date by 2 years to 31-03-2026  After receipt of IOA on 28-06-2021 residential structures were vacated after distributing rent. CC for the SRA project was received on 23-02-2022.  RERA filing wa…” Read the full reason“Request for Extension of Building Completion date by 2 years to 31-03-2026  After receipt of IOA on 28-06-2021 residential structures were vacated after distributing rent. CC for the SRA project was received on 23-02-2022.  RERA filing was immediately undertaken on 15-06-2022.  Since a 10 storied building was to be constructed completion of the project was anticipated to be 31-03-2024.  For construction material to be taken inside the plot, all commercial occupants were required to accord consent and shift.  Commercial occupants had not consented since all shops could not be planned on…”
  3. 31 July 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Vrundavan Sra CHS LTD Lotus Tower’s extension records on MahaRERA (P51800045859), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Vrundavan Sra CHS LTD Lotus Tower

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800045859
Status
Lapsed (registration period ended)
Builder
SHREE VARADKRUPA TOWERS LLP
Location
Ghatkopar West Bhatwadi, Mumbai · 400086
Project type
Residential / Group Housing
Registered on
15 Jun 2022
Completion date at registration
March 2024
Latest completion date
July 2026
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
52
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Vrundavan Sra CHS LTD Lotus Tower, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
LOTUS TOWER100%100%55%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vrundavan Sra CHS LTD Lotus Tower every 1–2 months.

Vrundavan Sra CHS LTD Lotus Tower: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Vrundavan Sra CHS LTD Lotus Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vrundavan Sra CHS LTD Lotus Tower: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Vrundavan Sra CHS LTD Lotus Tower

What is the possession date of Vrundavan Sra CHS LTD Lotus Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vrundavan Sra CHS LTD Lotus Tower in Ghatkopar West Bhatwadi, Mumbai is 31 July 2026 — 24 months later than 31 March 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Vrundavan Sra CHS LTD Lotus Tower?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vrundavan Sra CHS LTD Lotus Tower's builder has filed on MahaRERA, the official one, is 31 July 2026, already 24 months later than the 31 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Vrundavan Sra CHS LTD Lotus Tower extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Sra CHS LTD Lotus Tower's builder applied to MahaRERA to extend the completion date once: to 31 March 2026, giving the reason "Request for Extension of Building Completion date by 2 years to 31-03-2026  After receipt of IOA on 28-06-2021 residential structures were vacated after distributing rent. CC for the SRA project was received on 23-02-2022.  RERA filing was immediately undertaken on 15-06-2022.  Since a 10 storied building was to be constructed completion of the project was anticipated to be 31-03-2024.  For construction material to be taken inside the plot, all commercial occupants were required to accord consent and shift.  Commercial occupants had not consented since all shops could not be planned on…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Vrundavan Sra CHS LTD Lotus Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vrundavan Sra CHS LTD Lotus Tower in Ghatkopar West Bhatwadi, Mumbai is P51800045859.

Is Vrundavan Sra CHS LTD Lotus Tower registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Sra CHS LTD Lotus Tower is registered as P51800045859 and its status is "Lapsed (registration period ended)".

What is the current construction status of Vrundavan Sra CHS LTD Lotus Tower? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Sra CHS LTD Lotus Tower's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on LOTUS TOWER is 100% done and internal work 55%. GharKundli's full report compares construction progress with the deadline.

Does Vrundavan Sra CHS LTD Lotus Tower have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Vrundavan Sra CHS LTD Lotus Tower safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Sra CHS LTD Lotus Tower is registered on MahaRERA as P51800045859, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Vrundavan Sra CHS LTD Lotus Tower?

Vrundavan Sra CHS LTD Lotus Tower isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Vrundavan Sra CHS LTD Lotus Tower?

For a flat in Vrundavan Sra CHS LTD Lotus Tower (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Vrundavan Sra CHS LTD Lotus Tower received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Sra CHS LTD Lotus Tower isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 July 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Vrundavan Sra CHS LTD Lotus Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Sra CHS LTD Lotus Tower's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 July 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Vrundavan Sra CHS LTD Lotus Tower uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vrundavan Sra CHS LTD Lotus Tower was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Vrundavan Sra CHS LTD Lotus Tower's possession date changes?

The latest dates are on Vrundavan Sra CHS LTD Lotus Tower's MahaRERA page (P51800045859). GharKundli's Kundli Watch sends a free WhatsApp update on Vrundavan Sra CHS LTD Lotus Tower every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vrundavan Sra CHS LTD Lotus Tower have?

According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Sra CHS LTD Lotus Tower has one building filed: LOTUS TOWER with 11 floors.

How big is the land of Vrundavan Sra CHS LTD Lotus Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Sra CHS LTD Lotus Tower stands on 650 sq m of land (about 0.2 acres), with 2,577 sq m of sanctioned built-up area.

What are the reviews of Vrundavan Sra CHS LTD Lotus Tower?

Google Maps has reviews of Vrundavan Sra CHS LTD Lotus Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Vrundavan Sra CHS LTD Lotus Tower?

Vrundavan Sra CHS LTD Lotus Tower by SHREE VARADKRUPA TOWERS LLP is in Ghatkopar West Bhatwadi, Mumbai, pincode 400086 (near Ghatkopar East, Vile Parle West, Dahisar East), Maharashtra, and is registered on MahaRERA as P51800045859, per GharKundli's check of MahaRERA records. Its land is filed as CTS 54 (PT), 54/70 TO 54/93. GharKundli lists all 83 MahaRERA projects in Ghatkopar West (400086).

How many flats are in Vrundavan Sra CHS LTD Lotus Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Sra CHS LTD Lotus Tower has 52 homes in 1 tower registered on MahaRERA.

When was Vrundavan Sra CHS LTD Lotus Tower registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Sra CHS LTD Lotus Tower was registered on MahaRERA on 15 June 2022. GharKundli did not find a title report on the land on file there.

Does Vrundavan Sra CHS LTD Lotus Tower have any legal issues or court cases?

No court cases are listed for Vrundavan Sra CHS LTD Lotus Tower on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Vrundavan Sra CHS LTD Lotus Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE VARADKRUPA TOWERS LLP.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Ghatkopar West (400086)

All 83 projects in Ghatkopar West (400086) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.