SERENE SHELTER

by NISHAT ATAULLAH ANSARI · Nehru Nagar, MumbaiAlso near Kurla East, Kurla West, Bhandup West

Possession date of SERENE SHELTER: 30 April 2027, moved from 31 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800045597, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SERENE SHELTER?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SERENE SHELTER has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA28042620765)

    Reason the builder gave MahaRERA: “Delay in getting Environmental clearance due to Flamingo & related ecological protection issue and construction project located in critically polluted area”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SERENE SHELTER’s extension records on MahaRERA (P51800045597), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SERENE SHELTER

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800045597
Status
Registered and active
Builder
NISHAT ATAULLAH ANSARI
Location
Nehru Nagar, Mumbai · 400024
Project type
Residential / Group Housing
Registered on
26 May 2022
Completion date at registration
December 2025
Latest completion date
April 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
38
Sold or booked
27%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of SERENE SHELTER, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SERENE SHELTER - 15TH TO 18TH FLOOR0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • SERENE SHELTER - 15TH TO 18TH FLOOR: covers 4 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SERENE SHELTER every month.

SERENE SHELTER: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SERENE SHELTER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SERENE SHELTER: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SERENE SHELTER

What is the possession date of SERENE SHELTER?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SERENE SHELTER in Nehru Nagar, Mumbai is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SERENE SHELTER?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SERENE SHELTER's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SERENE SHELTER extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SERENE SHELTER's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Delay in getting Environmental clearance due to Flamingo & related ecological protection issue and construction project located in critically polluted area". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SERENE SHELTER?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SERENE SHELTER in Nehru Nagar, Mumbai is P51800045597.

Is SERENE SHELTER registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SERENE SHELTER is registered as P51800045597 and its status is "Registered and active".

What is the construction status of SERENE SHELTER?

According to GharKundli's check of MahaRERA records (updated November 2026), SERENE SHELTER's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SERENE SHELTER - 15TH TO 18TH FLOOR is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does SERENE SHELTER have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SERENE SHELTER safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SERENE SHELTER is registered on MahaRERA as P51800045597, its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SERENE SHELTER's possession date changes?

The latest dates are on SERENE SHELTER's MahaRERA page (P51800045597). GharKundli's Kundli Watch sends a free WhatsApp update on SERENE SHELTER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SERENE SHELTER have?

According to GharKundli's check of MahaRERA records (updated November 2026), SERENE SHELTER has one building filed: SERENE SHELTER - 15TH TO 18TH FLOOR with 5 floors and 41 units.

How big is the land of SERENE SHELTER?

According to GharKundli's check of MahaRERA records (updated November 2026), SERENE SHELTER stands on 5,112 sq m of land (about 1.3 acres), with 10,510 sq m of sanctioned built-up area.

Where can I read reviews of SERENE SHELTER?

Google Maps has reviews of SERENE SHELTER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SERENE SHELTER?

SERENE SHELTER by NISHAT ATAULLAH ANSARI is in Nehru Nagar, Mumbai (pincode 400024), near Kurla East, Kurla West, Bhandup West, Maharashtra, and is registered on MahaRERA as P51800045597, per GharKundli's check of MahaRERA records.

How many homes are in SERENE SHELTER?

According to GharKundli's check of MahaRERA records (updated November 2026), SERENE SHELTER has 38 homes in 1 tower registered on MahaRERA, and 27% of them are sold or booked.

When was SERENE SHELTER registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SERENE SHELTER was registered on MahaRERA on 26 May 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on SERENE SHELTER?

No court cases are listed for SERENE SHELTER on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SERENE SHELTER?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NISHAT ATAULLAH ANSARI.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400024

All 85 projects in Kurla East (400024) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.