Asmi Business Centre
by ASMI CORPORATION · Goregaon East, Mumbai 400063Also near Malad East, Goregaon west, Andheri West
What’s in the report? →Possession date of Asmi Business Centre (MahaRERA P51800046269): 31 December 2028, moved from 31 December 2025 (36 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800046269, and currently active.
Source: MahaRERA website — records for P51800046269, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Asmi Business Centre?
4 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Asmi Business Centre has moved
31 December 2025
Completion date given when the project was registered
31 December 2028
Extended at the builder's request (MahaRERA application EA17122518730)
Reason the builder gave MahaRERA:
“We, Asmi Corporation, are the promoters of the real estate project known as "ASMI BUSINESS CENTRE" bearing Maha RERA Registration No. P51800046269. We would like to respectfully bring to your attention that the project has encountered certa…” Read the full reason
“We, Asmi Corporation, are the promoters of the real estate project known as "ASMI BUSINESS CENTRE" bearing Maha RERA Registration No. P51800046269. We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the following reasons for the delay: 1. Delay in removing encroachment We had encroachment in our plot on East side. East side encroachment was removed by competent authority after many follow ups. 2. Waiting to demo…”
Source: Asmi Business Centre’s extension records on MahaRERA (P51800046269), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Asmi Business Centre
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 court cases, and how it ended
- Construction pace against the December 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800046269
- Status
- Registered and active
- Builder
- ASMI CORPORATION
- Location
- Goregaon East, Mumbai · 400063
- Project type
- Commercial
- Registered on
- 20 Jun 2022
- Completion date at registration
- December 2025
- Latest completion date
- December 2028
- Delay so far
- 36 months
- Homes
- 0
- Sold or booked
- 54%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 4
- Title report on file
- Not found
Construction progress of Asmi Business Centre, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ASMI BUSINESS CENTRE | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- ASMI BUSINESS CENTRE: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Asmi Business Centre every 1–2 months.
Asmi Business Centre: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 364 – 2,590 | 164 |
- Buildings: ASMI BUSINESS CENTRE (27 floors, 164 units)
- Land: 1,882 sq m (about 0.5 acres) · sanctioned built-up 5,712 sq m
- Boundaries filed include: GOREGAON MULUND LINK ROAD
- Land, as filed: SURVEY NO.3 PART HISSA NO.6 OLD CTS NO.51 PART AND NEW CTS NO 51A/B
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Asmi Developers (a group of 3 linked companies) has 3 projects on MahaRERA since 2021, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 16 months late). 3 complaints on MahaRERA across 1 project.
Read Google reviews of Asmi Business Centre →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Asmi Business Centre: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Asmi Business Centre
What is the possession date of Asmi Business Centre?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Asmi Business Centre in Goregaon East, Mumbai is 31 December 2028 — 36 months later than 31 December 2025, the date given at registration.
The date has already moved 36 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Asmi Business Centre?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Asmi Business Centre's builder has filed on MahaRERA, the official one, is 31 December 2028, already 36 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Asmi Business Centre extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Business Centre's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "We, Asmi Corporation, are the promoters of the real estate project known as "ASMI BUSINESS CENTRE" bearing Maha RERA Registration No. P51800046269. We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the following reasons for the delay: 1. Delay in removing encroachment We had encroachment in our plot on East side. East side encroachment was removed by competent authority after many follow ups. 2. Waiting to demo…".
What is the RERA number of Asmi Business Centre?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Asmi Business Centre in Goregaon East, Mumbai is P51800046269.
Is Asmi Business Centre registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Business Centre is registered as P51800046269 and its status is "Registered and active".
What is the current construction status of Asmi Business Centre? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Business Centre's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ASMI BUSINESS CENTRE is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Asmi Business Centre have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Asmi Business Centre safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Business Centre is registered on MahaRERA as P51800046269, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Asmi Business Centre?
Asmi Business Centre is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Asmi Business Centre?
For a flat in Asmi Business Centre (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Asmi Business Centre received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Business Centre is still under construction, with 31 December 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Asmi Business Centre uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Asmi Business Centre was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Asmi Business Centre's possession date changes?
The latest dates are on Asmi Business Centre's MahaRERA page (P51800046269). GharKundli's Kundli Watch sends a free WhatsApp update on Asmi Business Centre every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Asmi Business Centre have?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Business Centre has one building filed: ASMI BUSINESS CENTRE with 27 floors and 164 units.
How big is the land of Asmi Business Centre?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Business Centre stands on 1,882 sq m of land (about 0.5 acres), with 5,712 sq m of sanctioned built-up area.
What is the track record of Asmi Business Centre's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Developers (a group of 3 linked companies) has 3 projects on MahaRERA since 2021, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 16 months late). 3 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Asmi Business Centre?
Google Maps has reviews of Asmi Business Centre written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Asmi Business Centre?
Asmi Business Centre by ASMI CORPORATION is in Goregaon East, Mumbai, pincode 400063 (near Malad East, Goregaon west, Andheri West), Maharashtra, and is registered on MahaRERA as P51800046269, per GharKundli's check of MahaRERA records. Its boundaries filed there include GOREGAON MULUND LINK ROAD. Its land is filed as SURVEY NO.3 PART HISSA NO.6 OLD CTS NO.51 PART AND NEW CTS NO 51A/B. GharKundli lists all 151 MahaRERA projects in Goregaon East (400063).
How many flats are in Asmi Business Centre, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Business Centre has 0 homes in 1 tower registered on MahaRERA, and 54% of them are sold or booked.
When was Asmi Business Centre registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Asmi Business Centre was registered on MahaRERA on 20 June 2022. GharKundli did not find a title report on the land on file there.
Does Asmi Business Centre have any legal issues or court cases?
4 court cases are listed for Asmi Business Centre on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Asmi Business Centre?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ASMI CORPORATION.
Check it yourself on MahaRERA
- How to check the possession date of Asmi Business Centre
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Goregaon East (400063)
- 104 East
- Sheetal Sangam
- Astoria Tower B
- Avant Hillway
- Avant Hillway
- Satellite Elegance
- Sejal Square
- S-city-r2
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.