Zandor 27 Vidya
by Zandor Holdings LLP · Borivali W, Mumbai 400092Also near Shimpoli, Kandivali West, ChikoowadiRegistered on MahaRERA as “27 VIDYA”
What’s in the report? →Possession date of Zandor 27 Vidya (MahaRERA P51800054694): 30 April 2027, moved from 30 April 2025 (24 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800054694, and currently active.
Source: MahaRERA website — records for P51800054694, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Zandor 27 Vidya?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Zandor 27 Vidya has moved
30 April 2025
Completion date given when the project was registered
30 April 2027
Extended at the builder's request (MahaRERA application EA21102518158)
Reason the builder gave MahaRERA: “Contractor unable to complete the projects on the given date .”
Source: Zandor 27 Vidya’s extension records on MahaRERA (P51800054694), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Zandor 27 Vidya
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800054694
- Status
- Registered and active
- Builder
- Zandor Holdings LLP
- Location
- Borivali W, Mumbai · 400092
- Project type
- Residential / Group Housing
- Registered on
- 6 Feb 2024
- Completion date at registration
- April 2025
- Latest completion date
- April 2027
- Delay so far
- 24 months
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Zandor 27 Vidya, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Basement and Plinth | 100% | 40% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Basement and Plinth: covers 0 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Zandor 27 Vidya every 1–2 months.
Zandor 27 Vidya: buildings, flats and land, as filed on MahaRERA
- Buildings: Basement and Plinth (2 floors)
- Land: 612 sq m (about 0.2 acres)
- Land, as filed: 620C
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Zandor Holdings has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA.
Read Google reviews of Zandor 27 Vidya →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Zandor 27 Vidya: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Zandor 27 Vidya
What is the possession date of Zandor 27 Vidya?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Zandor 27 Vidya in Borivali W, Mumbai is 30 April 2027 — 24 months later than 30 April 2025, the date given at registration.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Zandor 27 Vidya?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Zandor 27 Vidya's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 30 April 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Zandor 27 Vidya extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Zandor 27 Vidya's builder applied to MahaRERA to extend the completion date once: to 30 April 2027, giving the reason "Contractor unable to complete the projects on the given date .".
What is the RERA number of Zandor 27 Vidya?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Zandor 27 Vidya in Borivali W, Mumbai is P51800054694.
Is Zandor 27 Vidya registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Zandor 27 Vidya is registered as P51800054694 and its status is "Registered and active".
What is the current construction status of Zandor 27 Vidya? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Zandor 27 Vidya's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Basement and Plinth is 40% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Zandor 27 Vidya have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Zandor 27 Vidya safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Zandor 27 Vidya is registered on MahaRERA as P51800054694, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Zandor 27 Vidya?
Zandor 27 Vidya is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Zandor 27 Vidya?
For a flat in Zandor 27 Vidya (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Zandor 27 Vidya received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Zandor 27 Vidya is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Zandor 27 Vidya a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Zandor 27 Vidya's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Zandor 27 Vidya uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Zandor 27 Vidya was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Zandor 27 Vidya's possession date changes?
The latest dates are on Zandor 27 Vidya's MahaRERA page (P51800054694). GharKundli's Kundli Watch sends a free WhatsApp update on Zandor 27 Vidya every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Zandor 27 Vidya have?
According to GharKundli's check of MahaRERA records (updated October 2026), Zandor 27 Vidya has one building filed: Basement and Plinth with 2 floors.
How big is the land of Zandor 27 Vidya?
According to GharKundli's check of MahaRERA records (updated October 2026), Zandor 27 Vidya stands on 612 sq m of land (about 0.2 acres).
What is the track record of Zandor 27 Vidya's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Zandor Holdings has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Zandor 27 Vidya?
Google Maps has reviews of Zandor 27 Vidya written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Zandor 27 Vidya?
Zandor 27 Vidya by Zandor Holdings LLP is in Borivali W, Mumbai, pincode 400092 (near Shimpoli, Kandivali West, Chikoowadi), Maharashtra, and is registered on MahaRERA as P51800054694, per GharKundli's check of MahaRERA records. Its land is filed as 620C. GharKundli lists all 362 MahaRERA projects in Borivali West (400092).
When was Zandor 27 Vidya registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Zandor 27 Vidya was registered on MahaRERA on 6 February 2024. GharKundli did not find a title report on the land on file there.
Does Zandor 27 Vidya have any legal issues or court cases?
No court cases are listed for Zandor 27 Vidya on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Zandor 27 Vidya?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Zandor Holdings LLP, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Zandor 27 Vidya
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Borivali West (400092)
- Skylark Heights
- Gaurav Galaxy
- Soni Arcade, Building No 2
- Fortune Avirahi Wing A
- Shraddha Skyline
- Sparkle Umadarshan
- I Space Urban Vista
- Hiranandani Bluecrest
Other projects by Zandor Holdings LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.