Mohan Terrace 'A' CHSL
by Zandor Holdings LLP · Borivali West, Mumbai
Registered on MahaRERA under PR1180002600046, and currently active. Its completion date has moved from March 2028 to July 2028, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
- MahaRERA registration
- PR1180002600046
- Status
- Registered and active
- Builder
- Zandor Holdings LLP
- Location
- Borivali West, Mumbai · 400092
- Project type
- Residential / Group Housing
- Registered on
- 9 Apr 2026
- Completion date at registration
- March 2028
- Latest completion date
- July 2028
- Delay so far
- 4 months
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
GharKundli’s full report on Mohan Terrace 'A' CHSL
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Kundli Watch
Mohan Terrace 'A' CHSL: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Mohan Terrace 'A' CHSL
Is Mohan Terrace 'A' CHSL registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Mohan Terrace 'A' CHSL is registered as PR1180002600046 and its status is "Registered and active".
Where is Mohan Terrace 'A' CHSL?
Mohan Terrace 'A' CHSL by Zandor Holdings LLP is in Borivali West, Mumbai (pincode 400092), Maharashtra, and is registered on MahaRERA as PR1180002600046, per GharKundli's check of MahaRERA records.
When is possession of Mohan Terrace 'A' CHSL due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mohan Terrace 'A' CHSL in Borivali West, Mumbai is 31 July 2028 — 4 months later than 31 March 2028, the date given at registration.
Does Mohan Terrace 'A' CHSL have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Mohan Terrace 'A' CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Zandor Holdings LLP, which has 1 other project registered on MahaRERA.
Other projects in pincode 400092
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.