What’s in the report? →Possession date of Skyline Ashwin (MahaRERA P51800056201): 30 September 2025, and it has already passed. It has 23 homes (2 BHK, 650–713 sq ft carpet), 27% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800056201. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800056201, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (September 2025) has passed.
What do you want to know about Skyline Ashwin?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
GharKundli’s full report on Skyline Ashwin
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800056201
- Status
- Lapsed (registration period ended)
- Builder
- SKYLINE LANDMARK PROJECTS PRIVATE LIMITED
- Location
- Jayprakash Nagar Goregaon East, Mumbai · 400063
- Project type
- Residential / Group Housing
- Registered on
- 21 May 2024
- Completion date at registration
- September 2025
- Homes
- 23
- Sold or booked
- 27%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Skyline Ashwin, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ASHWIN CHSL | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- ASHWIN CHSL: covers FULL
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Skyline Ashwin every 1–2 months.
Skyline Ashwin: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 650 – 713 | 23 |
- Buildings: ASHWIN CHSL (9 floors, 23 units)
- Car parking: 26 covered
- Land: 600 sq m (about 0.1 acres) · sanctioned built-up 1,621 sq m
- Boundaries filed include: PAHADI SCHOOL ROAD, PAHADI MUNICIPAL SCHOOL
- Land, as filed: 303
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Skyline Landmark Projects has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Skyline Ashwin →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Skyline Ashwin: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Skyline Ashwin
What is the possession date of Skyline Ashwin?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Skyline Ashwin in Jayprakash Nagar Goregaon East, Mumbai is 30 September 2025. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Skyline Ashwin?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Skyline Ashwin's builder has filed on MahaRERA, the official one, is 30 September 2025, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Skyline Ashwin?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Skyline Ashwin in Jayprakash Nagar Goregaon East, Mumbai is P51800056201.
Is Skyline Ashwin registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Ashwin is registered as P51800056201 and its status is "Lapsed (registration period ended)".
What is the current construction status of Skyline Ashwin? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Ashwin's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on ASHWIN CHSL is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Skyline Ashwin have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Skyline Ashwin safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Ashwin is registered on MahaRERA as P51800056201, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Skyline Ashwin?
Skyline Ashwin isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Skyline Ashwin start at 650 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Skyline Ashwin?
For a flat in Skyline Ashwin (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Skyline Ashwin received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Ashwin isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Skyline Ashwin?
According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Ashwin's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Is Skyline Ashwin a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Ashwin's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.
Has Skyline Ashwin uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Skyline Ashwin was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Skyline Ashwin's possession date changes?
The latest dates are on Skyline Ashwin's MahaRERA page (P51800056201). GharKundli's Kundli Watch sends a free WhatsApp update on Skyline Ashwin every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Skyline Ashwin have?
According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Ashwin has one building filed: ASHWIN CHSL with 9 floors and 23 units.
What are the flat sizes (carpet area) in Skyline Ashwin?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Skyline Ashwin: 2 BHK: 650 to 713 sq ft carpet (23 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Skyline Ashwin have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 26 covered car parking spaces for Skyline Ashwin.
How big is the land of Skyline Ashwin?
According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Ashwin stands on 600 sq m of land (about 0.1 acres), with 1,621 sq m of sanctioned built-up area.
What is the track record of Skyline Ashwin's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Landmark Projects has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Skyline Ashwin?
Google Maps has reviews of Skyline Ashwin written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Skyline Ashwin?
Skyline Ashwin by SKYLINE LANDMARK PROJECTS PRIVATE LIMITED is in Jayprakash Nagar Goregaon East, Mumbai, pincode 400063 (near Goregaon West, Goregoan East, Andheri West), Maharashtra, and is registered on MahaRERA as P51800056201, per GharKundli's check of MahaRERA records. Its boundaries filed there include PAHADI SCHOOL ROAD, PAHADI MUNICIPAL SCHOOL. Its land is filed as 303. GharKundli lists all 151 MahaRERA projects in Goregaon East (400063).
How many flats are in Skyline Ashwin, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Ashwin has 23 homes in 1 tower registered on MahaRERA, and 27% of them are sold or booked.
When was Skyline Ashwin registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Ashwin was registered on MahaRERA on 21 May 2024. GharKundli did not find a title report on the land on file there.
Does Skyline Ashwin have any legal issues or court cases?
No court cases are listed for Skyline Ashwin on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Skyline Ashwin?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SKYLINE LANDMARK PROJECTS PRIVATE LIMITED, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Skyline Ashwin
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Goregaon East (400063)
- 104 East
- Sheetal Sangam
- Astoria Tower B
- Avant Hillway
- Avant Hillway
- Satellite Elegance
- Sejal Square
- S-city-r2
Other projects by SKYLINE LANDMARK PROJECTS PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.