Sayba Signature Spaces
by STAR SAPPHIRE (Gagangiri) · Goregaon, Mumbai 400063Also near Malad East, Santacruz West, Dindoshi Malad
What’s in the report? →Possession date of Sayba Signature Spaces (MahaRERA P51800056477): 30 October 2027. It has 62 homes (1 BHK, 314–318 sq ft carpet), 62% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800056477, and currently active. Its completion date is now October 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51800056477, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Sayba Signature Spaces?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sayba Signature Spaces has moved
30 June 2027
Completion date given when the project was registered
30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sayba Signature Spaces’s extension records on MahaRERA (P51800056477), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sayba Signature Spaces
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800056477
- Status
- Registered and active
- Builder
- STAR SAPPHIRE
- Location
- Goregaon, Mumbai · 400063
- Project type
- Others
- Registered on
- 5 Jun 2024
- Completion date at registration
- June 2027
- Latest completion date
- October 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 62
- Sold or booked
- 62%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Sayba Signature Spaces, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 100% | 100% | 100% | 100% |
| WING B | 100% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- WING A: covers 25 floors
- WING B: covers 21 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sayba Signature Spaces every 1–2 months.
Sayba Signature Spaces: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 321 – 2,379 | 68 |
| 1 BHK | 314 – 318 | 62 |
| Shops | 70 – 1,384 | 16 |
- Buildings: WING A (25 floors, 73 units) · WING B (16 floors, 73 units)
- Land: 1,302 sq m (about 0.3 acres) · sanctioned built-up 6,290 sq m
- Boundaries filed include: EXPRESS MALL, PANDIT MOTILAL NEHRU ROAD
- Land, as filed: CTS NO 5
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Gagangiri Construction (a group of 15 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 8 finished, 7 within the promised date and 1 needed more time (typically 15 months); 14 still being built, none past the promised date yet; 1 lapsed. 7 complaints on MahaRERA across 3 projects.
Read Google reviews of Sayba Signature Spaces →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sayba Signature Spaces: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sayba Signature Spaces
What is the possession date of Sayba Signature Spaces?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sayba Signature Spaces in Goregaon, Mumbai is 30 October 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Sayba Signature Spaces?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sayba Signature Spaces's builder has filed on MahaRERA, the official one, is 30 October 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Sayba Signature Spaces?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sayba Signature Spaces in Goregaon, Mumbai is P51800056477.
Is Sayba Signature Spaces registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sayba Signature Spaces is registered as P51800056477 and its status is "Registered and active".
What is the current construction status of Sayba Signature Spaces? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Sayba Signature Spaces's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Sayba Signature Spaces have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sayba Signature Spaces safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sayba Signature Spaces is registered on MahaRERA as P51800056477, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sayba Signature Spaces?
Sayba Signature Spaces is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Sayba Signature Spaces are 314 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sayba Signature Spaces?
For a flat in Sayba Signature Spaces (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Sayba Signature Spaces received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sayba Signature Spaces is still under construction, with 30 October 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Sayba Signature Spaces a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Sayba Signature Spaces is a redevelopment: 73 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Sayba Signature Spaces uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sayba Signature Spaces was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Sayba Signature Spaces's possession date changes?
The latest dates are on Sayba Signature Spaces's MahaRERA page (P51800056477). GharKundli's Kundli Watch sends a free WhatsApp update on Sayba Signature Spaces every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sayba Signature Spaces have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sayba Signature Spaces has 2 buildings filed: WING A with 25 floors and 73 units; WING B with 16 floors and 73 units.
What are the flat sizes (carpet area) in Sayba Signature Spaces?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Sayba Signature Spaces: 1 BHK: 314 to 318 sq ft carpet (62 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Sayba Signature Spaces?
According to GharKundli's check of MahaRERA records (updated October 2026), Sayba Signature Spaces stands on 1,302 sq m of land (about 0.3 acres), with 6,290 sq m of sanctioned built-up area.
What is the track record of Sayba Signature Spaces's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Gagangiri Construction (a group of 15 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 8 finished, 7 within the promised date and 1 needed more time (typically 15 months); 14 still being built, none past the promised date yet; 1 lapsed. 7 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Sayba Signature Spaces?
Google Maps has reviews of Sayba Signature Spaces written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sayba Signature Spaces?
Sayba Signature Spaces by STAR SAPPHIRE (Gagangiri) is in Goregaon, Mumbai, pincode 400063 (near Malad East, Santacruz West, Dindoshi Malad), Maharashtra, and is registered on MahaRERA as P51800056477, per GharKundli's check of MahaRERA records. Its boundaries filed there include EXPRESS MALL, PANDIT MOTILAL NEHRU ROAD. Its land is filed as CTS NO 5. GharKundli lists all 151 MahaRERA projects in Goregaon East (400063).
How many flats are in Sayba Signature Spaces, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Sayba Signature Spaces has 62 homes in 2 towers registered on MahaRERA, and 62% of them are sold or booked.
When was Sayba Signature Spaces registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sayba Signature Spaces was registered on MahaRERA on 5 June 2024. GharKundli did not find a title report on the land on file there.
Does Sayba Signature Spaces have any legal issues or court cases?
No court cases are listed for Sayba Signature Spaces on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Sayba Signature Spaces?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is STAR SAPPHIRE, the company Gagangiri files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Sayba Signature Spaces
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Goregaon East (400063)
- 104 East
- Sheetal Sangam
- Astoria Tower B
- Avant Hillway
- Avant Hillway
- Satellite Elegance
- Sejal Square
- S-city-r2
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.