Skip to content
GharKundli

Amul New Manibhuvan

by AMUL ENTERPRISES · Andheri, Mumbai 400057Also near Vile Parle East, Vile Parle West, Vileparle EastRegistered on MahaRERA as “NEW MANIBHUVAN”

What’s in the report? →

Possession date of Amul New Manibhuvan (MahaRERA PM1180002502660): 30 April 2027. It has 28 homes (1 BHK, 2 BHK and 3 BHK, 240–1171 sq ft carpet), 7% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PM1180002502660, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PM1180002502660, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Amul New Manibhuvan?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Amul New Manibhuvan has moved

  1. 31 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Amul New Manibhuvan’s extension records on MahaRERA (PM1180002502660), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Amul New Manibhuvan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PM1180002502660
Status
Registered and active
Builder
AMUL ENTERPRISES
Location
Andheri, Mumbai · 400057
Project type
Mixed
Registered on
9 Mar 2026
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
28
Sold or booked
7%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Amul New Manibhuvan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NEW MANIBHUVAN / WING A100%70%22%10%
NEW MANIBHUVAN / WING B100%70%60%10%

Commencement certificate (CC), as filed on MahaRERA

  • NEW MANIBHUVAN: covers Gr.+1 floor
  • NEW MANIBHUVAN: covers Gr.+3 floors

Latest CC order on MahaRERA: dated 22/01/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Amul New Manibhuvan every 1–2 months.

Amul New Manibhuvan: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK240 – 59211
2 BHK795 – 1,0169
3 BHK1,159 – 1,1718
Shops473 – 1,4302
Other486 – 1,1682
  • Buildings: NEW MANIBHUVAN (7 floors, 12 units) · NEW MANIBHUVAN (7 floors, 20 units)
  • Car parking: 25 covered
  • Land: 1,069 sq m (about 0.3 acres) · sanctioned built-up 2,620 sq m · recreational space 87 sq m
  • Boundaries filed include: PRARTHANA SAMAJ ROAD
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Amul New Manibhuvan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Amul New Manibhuvan: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Amul New Manibhuvan

What is the possession date of Amul New Manibhuvan?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Amul New Manibhuvan in Andheri, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Amul New Manibhuvan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Amul New Manibhuvan's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Amul New Manibhuvan?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Amul New Manibhuvan in Andheri, Mumbai is PM1180002502660.

Is Amul New Manibhuvan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Amul New Manibhuvan is registered as PM1180002502660 and its status is "Registered and active".

What is the current construction status of Amul New Manibhuvan? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Amul New Manibhuvan's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 70% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Amul New Manibhuvan have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Amul New Manibhuvan safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Amul New Manibhuvan is registered on MahaRERA as PM1180002502660, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Amul New Manibhuvan?

Amul New Manibhuvan is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Amul New Manibhuvan are 240 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Amul New Manibhuvan?

For a flat in Amul New Manibhuvan (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Amul New Manibhuvan received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Amul New Manibhuvan is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Amul New Manibhuvan a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Amul New Manibhuvan is a redevelopment: 18 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Amul New Manibhuvan uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Amul New Manibhuvan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Amul New Manibhuvan's possession date changes?

The latest dates are on Amul New Manibhuvan's MahaRERA page (PM1180002502660). GharKundli's Kundli Watch sends a free WhatsApp update on Amul New Manibhuvan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Amul New Manibhuvan have?

According to GharKundli's check of MahaRERA records (updated October 2026), Amul New Manibhuvan has 2 buildings filed: NEW MANIBHUVAN with 7 floors and 12 units; NEW MANIBHUVAN with 7 floors and 20 units.

What are the flat sizes (carpet area) in Amul New Manibhuvan?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Amul New Manibhuvan: 1 BHK: 240 to 592 sq ft carpet (11 homes); 2 BHK: 795 to 1016 sq ft carpet (9 homes); 3 BHK: 1159 to 1171 sq ft carpet (8 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Amul New Manibhuvan have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 25 covered car parking spaces for Amul New Manibhuvan.

How big is the land of Amul New Manibhuvan?

According to GharKundli's check of MahaRERA records (updated October 2026), Amul New Manibhuvan stands on 1,069 sq m of land (about 0.3 acres), with 2,620 sq m of sanctioned built-up area and 87 sq m of recreational open space.

What are the reviews of Amul New Manibhuvan?

Google Maps has reviews of Amul New Manibhuvan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Amul New Manibhuvan?

Amul New Manibhuvan by AMUL ENTERPRISES is in Andheri, Mumbai, pincode 400057 (near Vile Parle East, Vile Parle West, Vileparle East), Maharashtra, and is registered on MahaRERA as PM1180002502660, per GharKundli's check of MahaRERA records. Its boundaries filed there include PRARTHANA SAMAJ ROAD. GharKundli lists all 251 MahaRERA projects in Vile Parle East (400057).

How many flats are in Amul New Manibhuvan, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Amul New Manibhuvan has 28 homes in 2 towers registered on MahaRERA, and 7% of them are sold or booked.

When was Amul New Manibhuvan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Amul New Manibhuvan was registered on MahaRERA on 9 March 2026. GharKundli did not find a title report on the land on file there.

Does Amul New Manibhuvan have any legal issues or court cases?

No court cases are listed for Amul New Manibhuvan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Amul New Manibhuvan?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AMUL ENTERPRISES.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Vile Parle East (400057)

All 251 projects in Vile Parle East (400057) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.