DB Ozone
by NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED · Goregaon East, ThaneAlso near Jogeshwari West
Possession date of DB Ozone: 30 December 2024, moved from 31 December 2019 (60 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700003433. Status: Lapsed (registration period ended). 71 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2024) has passed.
What do you want to know about DB Ozone?
How the possession date of DB Ozone has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51700003914)
Reason the builder gave MahaRERA:
“* The Status of Construction of Building no. 1,2,3,4,6,7,8,9,10 are at final stage of Completion. Installation of lift is going on in building nos. 11,12,14,16 &17 and will be ready to handover for fit out Possession in the month of January…” Read the full reason
“* The Status of Construction of Building no. 1,2,3,4,6,7,8,9,10 are at final stage of Completion. Installation of lift is going on in building nos. 11,12,14,16 &17 and will be ready to handover for fit out Possession in the month of January 2020. The other facilities/amenities such as Electricity, Water connection, Fire Fighting, Solar Panel, Children’s Play area already functional. The Photographs of the same are annexed herewith as Annexure A. * The NBFC crisis has been a tip of the iceberg of the ongoing headwinds faced by the real estate industry with the slower receivable cycles and fu…”30 December 2024
Extended at the builder's request (MahaRERA application EXT51700010187)
Reason the builder gave MahaRERA:
“1) The Applicant states that the project was delayed on account of various factors as below : i. There was non-availability of sand for the construction of the project as mining was banned in all Coastal Regulated areas across the State of…” Read the full reason
“1) The Applicant states that the project was delayed on account of various factors as below : i. There was non-availability of sand for the construction of the project as mining was banned in all Coastal Regulated areas across the State of Maharashtra. ii. The Quarrying for stones was simultaneously banned in the State by the Environment Ministry resulting into non-availability of stones on construction and which correspondingly caused delay in completion of the project. iii. In view of the Hon’ble Bombay High Court in PIL No. 138 of 2006 on account of the ban, the stone Vendors were unable…”
Source: DB Ozone’s extension records on MahaRERA (P51700003433), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on DB Ozone
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 71 complaints and 120 court cases, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700003433
- Status
- Lapsed (registration period ended)
- Builder
- NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED
- Location
- Goregaon East, Thane · 400063
- Project type
- Residential / Group Housing
- Registered on
- 5 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2024
- Delay so far
- 60 months
- Homes
- 3,396
- Towers
- 25
- Complaints on MahaRERA
- 71
- Court cases listed
- 120
- Appeals at the tribunal
- 55
- Title report on file
- Not found
Construction progress of DB Ozone, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building No 28 | 100% | 100% | 98% | 76% |
| Building No 1 | 100% | 100% | 100% | 100% |
| Building No 2 | 100% | 100% | 100% | 100% |
| Building No 3 | 100% | 100% | 100% | 100% |
| Building No 4 | 100% | 100% | 100% | 100% |
| Building No 7 | 100% | 100% | 100% | 98% |
| Building No 8 | 100% | 100% | 100% | 98% |
| Building No 6 | 100% | 100% | 100% | 98% |
| Building No 9 | 100% | 100% | 100% | 98% |
| Building No 10 | 100% | 100% | 100% | 98% |
| Building No 11 | 100% | 100% | 100% | 92% |
| Building No 12 | 100% | 100% | 98% | 92% |
| Building No 14 | 100% | 100% | 98% | 92% |
| Building No 15 | 100% | 100% | 97% | 92% |
| Building No 16 | 100% | 100% | 98% | 92% |
| Building No 17 | 100% | 100% | 98% | 92% |
| Building No 18 | 100% | 100% | 98% | 78% |
| Building No 20 | 100% | 100% | 96% | 77% |
| Building No 21 | 100% | 100% | 96% | 77% |
| Building No 22 | 100% | 100% | 96% | 77% |
| Building No 23 | 100% | 100% | 96% | 74% |
| Building No 24 | 100% | 100% | 96% | 80% |
| Building No 27 | 100% | 100% | 90% | 76% |
| Building No 29 | 100% | 100% | 97% | 76% |
| Building No 30 | 100% | 100% | 90% | 76% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on DB Ozone every month.
DB Ozone: buildings, flats and land, as filed on MahaRERA
- Buildings: Building No 28 (25 floors) · Building No 1 (24 floors) · Building No 2 (24 floors) · Building No 3 (24 floors) · Building No 4 (24 floors) · Building No 7 (24 floors) · Building No 8 (25 floors) · Building No 6 (26 floors) · and 17 more
- Land: 38,401 sq m (about 9.5 acres) · sanctioned built-up 1,61,994 sq m · recreational space 4,740 sq m
- Boundaries filed include: Thakur Mall and International school, Sanjay Gandhi National Park, National Highway No 8
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of DB Ozone →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
DB Ozone: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about DB Ozone
What is the possession date of DB Ozone?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for DB Ozone in Goregaon East, Thane is 30 December 2024 — 60 months later than 31 December 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for DB Ozone?
Builders and listing sites often quote an earlier "target" date for handover. The completion date DB Ozone's builder has filed on MahaRERA, the official one, is 30 December 2024, already 60 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of DB Ozone extended?
According to GharKundli's check of MahaRERA records (updated November 2026), DB Ozone's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2020, giving the reason "* The Status of Construction of Building no. 1,2,3,4,6,7,8,9,10 are at final stage of Completion. Installation of lift is going on in building nos. 11,12,14,16 &17 and will be ready to handover for fit out Possession in the month of January 2020. The other facilities/amenities such as Electricity, Water connection, Fire Fighting, Solar Panel, Children’s Play area already functional. The Photographs of the same are annexed herewith as Annexure A. * The NBFC crisis has been a tip of the iceberg of the ongoing headwinds faced by the real estate industry with the slower receivable cycles and fu…"; to 30 December 2024, giving the reason "1) The Applicant states that the project was delayed on account of various factors as below : i. There was non-availability of sand for the construction of the project as mining was banned in all Coastal Regulated areas across the State of Maharashtra. ii. The Quarrying for stones was simultaneously banned in the State by the Environment Ministry resulting into non-availability of stones on construction and which correspondingly caused delay in completion of the project. iii. In view of the Hon’ble Bombay High Court in PIL No. 138 of 2006 on account of the ban, the stone Vendors were unable…".
What is the RERA number of DB Ozone?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of DB Ozone in Goregaon East, Thane is P51700003433.
Is DB Ozone registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), DB Ozone is registered as P51700003433 and its status is "Lapsed (registration period ended)".
What is the construction status of DB Ozone?
According to GharKundli's check of MahaRERA records (updated November 2026), DB Ozone's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 25 towers. GharKundli's full report compares construction progress with the deadline.
Does DB Ozone have complaints on MahaRERA?
71 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is DB Ozone safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), DB Ozone is registered on MahaRERA as P51700003433, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 60 months since registration and 71 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if DB Ozone's possession date changes?
The latest dates are on DB Ozone's MahaRERA page (P51700003433). GharKundli's Kundli Watch sends a free WhatsApp update on DB Ozone every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does DB Ozone have?
According to GharKundli's check of MahaRERA records (updated November 2026), DB Ozone has 25 buildings filed: Building No 28 with 25 floors; Building No 1 with 24 floors; Building No 2 with 24 floors; Building No 3 with 24 floors; Building No 4 with 24 floors; Building No 7 with 24 floors; and 19 more.
How big is the land of DB Ozone?
According to GharKundli's check of MahaRERA records (updated November 2026), DB Ozone stands on 38,401 sq m of land (about 9.5 acres), with 1,61,994 sq m of sanctioned built-up area and 4,740 sq m of recreational open space.
Where can I read reviews of DB Ozone?
Google Maps has reviews of DB Ozone written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 71 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is DB Ozone?
DB Ozone by NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED is in Goregaon East, Thane (pincode 400063), near Jogeshwari West, Maharashtra, and is registered on MahaRERA as P51700003433, per GharKundli's check of MahaRERA records. Its boundaries filed there include Thakur Mall and International school, Sanjay Gandhi National Park, National Highway No 8.
How many homes are in DB Ozone?
According to GharKundli's check of MahaRERA records (updated November 2026), DB Ozone has 3,396 homes in 25 towers registered on MahaRERA.
When was DB Ozone registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), DB Ozone was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on DB Ozone?
120 court cases are listed for DB Ozone on MahaRERA, and 55 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of DB Ozone?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of DB Ozone
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400063
- ASTORIA TOWER B
- AVANT HILLWAY
- AVANT HILLWAY
- Satellite Elegance
- 104 EAST
- SEJAL SQUARE
- S-CITY-R2
- Sheetal Sangam
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.