Maitri Icon
by MAITRI & MAITRI · Kamatghar, Thane 421302Also near Bhiwandi, Naupada
What’s in the report? →Possession date of Maitri Icon (MahaRERA P51700011301): 30 October 2027, moved from 30 December 2024 (30 months later). It has 304 homes, 49% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700011301, and currently active. Its completion date has moved from December 2024 to October 2027: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700011301, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Maitri Icon?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Maitri Icon has moved
30 December 2024
Completion date given when the project was registered
30 June 2027
Extended at the builder's request (MahaRERA application EXT51700025496)
Reason the builder gave MahaRERA:
“We are register under Maharera having registration No. P51700011301 upto 30/12/2024. On Expiry of above period we seeks to further extend period of registration till 30/06/2027. Reason for Delay : Due to the pandemic situation prevailing fo…” Read the full reason
“We are register under Maharera having registration No. P51700011301 upto 30/12/2024. On Expiry of above period we seeks to further extend period of registration till 30/06/2027. Reason for Delay : Due to the pandemic situation prevailing for almost 2 years construction activity also affected adversely. And also increase in FSI we have revised the Plan. Therefore we request you to grant further extension till 30/06/2027. We have completed work of Building No. 2, 3 and 4 A Wing. Work for Building No. 1, 3 A and 4 B wing is under Progress.”30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Maitri Icon’s extension records on MahaRERA (P51700011301), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Maitri Icon
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700011301
- Status
- Registered and active
- Builder
- MAITRI & MAITRI
- Location
- Kamatghar, Thane · 421302
- Project type
- Others
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2024
- Latest completion date
- October 2027
- Delay so far
- 30 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 304
- Sold or booked
- 49%
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Maitri Icon, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING 1 | 100% | 100% | 100% | 100% |
| BUILDING 2 | 100% | 100% | 100% | 100% |
| BUILDING 3 | 0% | 0% | 0% | 0% |
| BUILDING 4 | 100% | 100% | 100% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING 1: covers 6 floors
- BUILDING 2: covers 0 floors
- BUILDING 3: covers 5 floors
- BUILDING 4: covers 0 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Maitri Icon every 1–2 months.
Maitri Icon: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING 1 (6 floors, 197 units) · BUILDING 2 (2 floors, 52 units) · BUILDING 3 (7 floors, 26 units) · BUILDING 4 (18 floors, 199 units)
- Land: 11,000 sq m (about 2.7 acres) · sanctioned built-up 32,112 sq m · recreational space 3,036 sq m
- Land, as filed: SURVEY NO. 4942, 535 AND 538
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Maitri Icon →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Maitri Icon: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Maitri Icon
What is the possession date of Maitri Icon?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Maitri Icon in Kamatghar, Thane is 30 October 2027 — 30 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 30 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Maitri Icon?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Maitri Icon's builder has filed on MahaRERA, the official one, is 30 October 2027, already 30 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Maitri Icon extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Maitri Icon's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "We are register under Maharera having registration No. P51700011301 upto 30/12/2024. On Expiry of above period we seeks to further extend period of registration till 30/06/2027. Reason for Delay : Due to the pandemic situation prevailing for almost 2 years construction activity also affected adversely. And also increase in FSI we have revised the Plan. Therefore we request you to grant further extension till 30/06/2027. We have completed work of Building No. 2, 3 and 4 A Wing. Work for Building No. 1, 3 A and 4 B wing is under Progress.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Maitri Icon?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Maitri Icon in Kamatghar, Thane is P51700011301.
Is Maitri Icon registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Maitri Icon is registered as P51700011301 and its status is "Registered and active".
What is the current construction status of Maitri Icon? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Maitri Icon's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does Maitri Icon have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Maitri Icon safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Maitri Icon is registered on MahaRERA as P51700011301, its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Maitri Icon?
Maitri Icon is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Maitri Icon?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Maitri Icon: gharkundli.com/tools/property-cost-calculator
Has Maitri Icon received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Maitri Icon is still under construction, with 30 October 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Maitri Icon uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Maitri Icon was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Maitri Icon's possession date changes?
The latest dates are on Maitri Icon's MahaRERA page (P51700011301). GharKundli's Kundli Watch sends a free WhatsApp update on Maitri Icon every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Maitri Icon have?
According to GharKundli's check of MahaRERA records (updated October 2026), Maitri Icon has 4 buildings filed: BUILDING 1 with 6 floors and 197 units; BUILDING 2 with 2 floors and 52 units; BUILDING 3 with 7 floors and 26 units; BUILDING 4 with 18 floors and 199 units.
How big is the land of Maitri Icon?
According to GharKundli's check of MahaRERA records (updated October 2026), Maitri Icon stands on 11,000 sq m of land (about 2.7 acres), with 32,112 sq m of sanctioned built-up area and 3,036 sq m of recreational open space.
What are the reviews of Maitri Icon?
Google Maps has reviews of Maitri Icon written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Maitri Icon?
Maitri Icon by MAITRI & MAITRI is in Kamatghar, Thane, pincode 421302 (near Bhiwandi, Naupada), Maharashtra, and is registered on MahaRERA as P51700011301, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO. 4942, 535 AND 538. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).
How many flats are in Maitri Icon, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Maitri Icon has 304 homes in 4 towers registered on MahaRERA, and 49% of them are sold or booked.
When was Maitri Icon registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Maitri Icon was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Does Maitri Icon have any legal issues or court cases?
No court cases are listed for Maitri Icon on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Maitri Icon?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MAITRI & MAITRI.
Check it yourself on MahaRERA
- How to check the possession date of Maitri Icon
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Bhiwandi
- Munisuvrat Oasis
- Unity Towers
- M/s SIMCO JYOTI
- Ashoka Complex
- Kohinoor Uptown T1 & T6
- Regal Square PH 4 Tower 6 and 8
- Sai Deep Residency
- Neelkanth Sadan
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.